PASI OsC meeting 12th July 2012

Slides:



Advertisements
Similar presentations
RFQ development for high power beams
Advertisements

MICE RF Cavities and RFCC Module Update Derun Li Lawrence Berkeley National Laboratory MICE RF Workshop Daresbury Laboratory, UK April 17, 2012 April 17,
COOLING TUBE ACCELERATING STRUCTURE MANIFOLD COUPLER VACUUM INTERFACE FLANGE RF INTERFACE FLANGE TUNING STUD ENGINEERING DESIGN AND FABRICATION OF X-BAND.
Laboratori Nazionali di Legnaro (Italy) DTL design status A. Pisent.
Vacuum Vessel Production Readiness Review
Status of the SPL cavities at CERN I.Aviles & N. Valverde on behalf of SPL team 1I. Aviles & N. ValverdeLund, 11 December 2013.
RF Measurement Plan Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory January 20, 2011 MICE Video Conference Meeting.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Status of the 201 MHz Cavity and Coupling Coil Module Steve Virostek Lawrence Berkeley National Laboratory MICE Video Conference March 10, 2004.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM26 at Riverside California March 26, 2010.
Richard F Boyce Injector UpdateL0-1 Accelerator 3 November L0-1 Design, Manufacturing & Testing R. F. Boyce, SLAC.
Target Assembly and Installation Update 20 th August 2009 Paul Hodgson The University of Sheffield.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
324MHz FETS RFQ RF measurement and components By Aaron Cheng 18 December 2006.
Dr. Michael Peiniger Superconducting RF activities at RI Research Instruments with a focus on EXFEL cavity production.
Single-Cavity Module Installation at MuCool Test Area Yağmur Torun MICE Collaboration Meeting February 15, 2013.
Front End Test Stand Klystron Commissioning Alan Letchford UKNF Plenary Meeting 22 nd April 2009.
Alain FRANCE for the ESS RFQ Team at CEA Saclay
Status of X-band program at RadiaBeam
RFQ Thermal Analysis Scott Lawrie. Vacuum Pump Flange Vacuum Flange Coolant Manifold Cooling Pockets Milled Into Vanes Potentially Bolted Together Tuner.
International Workshop on Linear Colliders 2010 Design and fabrication update on PSI/Trieste X-band phase- space rotator structure Dmitry Gudkov 21-OCT-2010.
1 Progress On The Design And Manufacture Of The New Stator Geoff Barber Imperial College.
RF power & FPC status Eric Montesinos, CERN BE-RF on behalf of all people involved, great thanks to all of them !
F.E.T.S. RFQ Support Structure by Peter Savage 21 ST October 2009.
PETS EuCARD. Present status and precision assembly L. Sánchez, F. Aragón, J. Calero, J.L. Gutiérrez, E. Rodríguez, F. Toral, CIEMAT 26/10/2011.
RFQ Fabrication Plan, Schedule and QC PXIE RFQ Fabrication Readiness Review LBNL – June 26, 2013 Steve Virostek - Engineering Division Lawrence Berkeley.
F.E.T.S. RFQ Mechanical Design by Peter Savage 7 th January 2010.
Vertical Test Stand in IB1 C.M. Ginsburg (Fermilab) for the IB1 VTS Group SRF R&D Meeting 6.July 2006.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
UKNF OsC RAL – 31 st January 2011 UKNF - Status, high lights, plans J. Pozimski.
News on mechanics Photon veto F. Raffaelli INFN – Sezione di Pisa CERN, January r 02 th, Status of tender Anti Status of the supporting.
Status of the Front End Test Stand April Infrastructure R8 refurbished Laser lab under construction Vacuum system for first section delivered Stands.
IMP Visit July 10, 2013 Matt Hoff LBNL July 18, 2013.
ENGINEERING DESIGN AND FABRICATION OF X-BAND DAMPED DETUNED STRUCTURE V. Soldatov¹, D. Gudkov¹, A. Samoshkin¹, G. Riddone², A. Grudiev², S. Atieh², A.
CLIC Permanent Magnet Quadrupole Engineering Development of second family member Norbert Collomb, STFC Daresbury Laboratory 1N. Collomb 07/11/2012.
MICE RF Cavities and RFCC Module Update Allan DeMello and Derun Li Lawrence Berkeley National Laboratory MICE CM32 at RAL, UK February 9, 2012 February.
Manufacturing process, validation and factory test
UK Neutrino Factory Meeting Front End Test Stand (F.E.T.S.) Engineering Status by P. Savage 22nd April 2009.
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
Xx-xx-2010, tanks arrive from Snezhinsk to Novosibirsk A.Tribendis, July 19-21, 2010, Snezhinsk 1. Check cavity dimensions on a CMM 2. Assemble and measure.
Tracker 1. Status 2. Expected delivery date of system to RAL 3. Required support infrastructure needed for setup and initial debug. Things like vacuum,
RFQ – Design, Components and Fabrication 1 We aim to design and manufacture a Radio Frequency Quadrupole (RFQ).
7-Sep-2011 CLIC RF Structure Development Meeting «BE/RF» TD26 WITH COMPACT COUPLER FOR CLEX (TD26 CC SiC) ENGINEERING DESIGN this structure will be used.
RFQ Cold model manufacture, June 2006 Peter Savage The Front End Test Stand Collaboration 1 OFC RFQ Cold Model Manufacture The first step is to convert.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Lab MICE CM25 at RAL, UK November 6, 2009.
MICE RFCC Module Update Steve Virostek Allan DeMello Lawrence Berkeley National Laboratory MICE CM27 at RAL, UK July 8, 2010.
FETS-HINS Videoconference 23rd Feb 2007 FETS Mechanical Design Issues by J. Pozimski On behalf of P. Savage.
THE LINAC4 RFQ – Experience with Design, Fabrication and Tuning C. Rossi and the RFQ Project Team GSI Review – 20 November 2013.
Wolfgang Vinzenz FAIR Proton Linac 10 th FAIR MAC November 25 th and 26 th 2013 Proton Linac 1 Status Buncher Design  Rectangular design, longitudinal.
DTL prototype summary and production sequence F.Grespan LNL _06_22 CDR.
Status of MICE RF for Step V’ (at LBNL) Derun Li Lawrence Berkeley National Laboratory December 6, 2014.
MICE RF Coupler Modifications Update 4/30/2015 Allan DeMello.
02-Dec XB Dec-2010 XB-10 Engineering design, production and follow-up of X-band RF components G. Riddone in collaboration.
201 MHz Cavity Plans Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory February 11, 2011 MAP Friday Video Conference Meeting.
PXIE RFQ Engineering Design Steve Virostek Engineering Division Lawrence Berkeley National Laboratory April 10, 2012 Project X Collaboration
RFCC Engineering Status and Plans Allan DeMello Lawrence Berkeley National Laboratory MAP Winter Meeting March 6, 2012 March 6, 2012.
RFQ Installation Plan PIP-II Meeting, 14-July-2015 C. Baffes for R. Andrews, A. Chen, Y. Czajkowski, S. Kazakov, R. Pasquinelli, D. Peterson, O. Pronitchev,
PXIE RFQ Status RFQ Fabrication Summary Module 2 bead pull test complete (Timer will give a talk next). Vane machining continues. We are.
LCWS11 WG4 Fully featured accelerating structure engineering design
Bruno POTTIN, Anne-Catherine CHAUVEAU
Completion of the MICE-US construction project
Physics design on Injector-1 RFQ
Status of the Front End Test Stand April 2007.
Optimisation of the FETS RFQ
Advanced Research Electron Accelerator Laboratory
Mechanical Engineering progress for the Front End Test Stand
System tests at CEA O. Piquet 19/03/2019
CDS-EL IRR Closeout 28 March 2019 J.G. Weisend II, Chairman.
Injector/Linac RF Status
SNS PPU CRYOMODULE PDR Cleanroom Assembly Katherine Wilson
Presentation transcript:

PASI OsC meeting 12th July 2012 RFQ Manufacturing by Peter Savage PASI OsC meeting 12th July 2012

The FETS RFQ 3MeV 65keV The FETS RFQ Physics simulations (frequency modelling and particle tracking) were complete in September 2011. The Engineering Design was complete at the same time due to our design method used – splitting particle tracking from the bulk structure. Then entered into the design for manufacturing phase and started the search for a suitable manufacturer.

Design for manufacture What does this mean? The 3D RFQ design was complete and the simulations showed the performance to be on specification. Now the design had to incorporate features that would assist the following processes: Manufacturing Inspection Lifting / Transportation Assembly Alignment To achieve this we took feedback from the manufacturing and metrology functions and modified the design accordingly. Design Manufacture Metrology

Manufacturer selection With our complete design we visited manufacturers to describe the job and to see whether they were capable of producing the RFQ. We needed a manufacturer with: Experience – R&D Equipment – scale, precision, axes and handling. Reputation – to maintain. Culture – work with the customer. The current FETS team (excluding Alan) had not built an RFQ before and neither had the manufacturer so it was important to find a manufacturer with whom we could build a relationship to develop the production technique together.

Tolerancing and Datums Defining the tolerances and datum system was a big challenge. Balance between achieving the designed performance and being practical to manufacture. Important to identify where tight tolerances were required and where we could be more relaxed. Again, the design system helped here where machining and assembly misalignments could be simulated. Several iterations were required to discover ‘the’ datum system. It needed to be one simple elegant system that would be used during the four processes of: Manufacture Inspection Assembly Alignment Degrees of freedom during assembly

What stage are we at now? All 16 RFQ pieces have been machined to within 2.5mm of their final form (including all features). The 4 pieces that make section 1 have are being finished on their outer faces now. Once completed the datum dowel holes will be added before moving on to the vane side milling. The trials are complete to perform the vane side milling operation and the surface finish has been approved.. The thread milling trials are complete. CMM refurbishment at the manufacturer is underway. The vane side milling is scheduled to begin on the week starting 23rd July. Four vanes will be machined and inspected. Delivery to RAL for stage 1 alignment following inspection approval.

Manufacturing Progress JAN 2012 MARCH 2012 JULY 2012 MAY 2012

Bead pull / RF tests We are preparing for bead pull and low power RF tests on the assembled RFQ section 1. Goal is to measure the electric field to check for manufacturing and assembly symmetry and to aid tuning to achieve a flat longitudinal electric field. Modification to existing bead-pull apparatus required. Design of dedicated end flanges and coupling loops required. RF Coupler Bead pull / RF test end flange Multi-axis bead-pull rig at RHUL

RFQ will be plumbed in to cooling manifold. Ancillary components The RFQ is often shown ‘naked’ for clarity but in reality it will be populated with dozens of assemblies for vacuum, tuning and cooling that will largely bury the copper structure. The RFQ cooling manifold has been designed and is being assembled now. The cooling water supply will be installed in R8 immediately following the completion of the cladding work. RFQ will be plumbed in to cooling manifold. 10 cooling circuits

Ancillary components The completed assembly will then be vacuum tested before being approved ready for use. Other ancillary components include: Tuners assemblies Cooling baffles Pick-ups End flange End flange insert The photo shows the current status of the production of the RFQ end flange assemblies. The next stage is to produce the stainless steel toroid covers before moving to vacuum brazing for the cooling channels. Toroid cover

The FETS Supporting Infrastructure The FETS CAD model shows the FETS beam-line sitting alone in R8 alone: In reality the FETS will require supporting infrastructure that includes: Concrete shielding for radiation safety including a personnel interlock system. Waveguide and couplers to carry power from the Klystron to the RFQ and beyond to the MEBT. Cooling systems – development work has started on the RFQ manifolds though cooling is required beyond the RFQ. Power systems and control systems for diagnostics. Vacuum systems with control.

Looking ahead By the year end we hope to have one RFQ section assembled, commissioned and aligned on the FETS rail system. In addition the remaining three RFQ sections will be manufactured and will be treated to the same commissioning processes as used for section 1. In parallel to the RFQ work the MEBT design process is gathering momentum as you will hear next........ Thank you. ...............any questions?