Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,

Slides:



Advertisements
Similar presentations
IEFC Workshop – 22/03/2011 JJ Gras on behalf of BE-BI 1.
Advertisements

BI Outlook for BI Day 2012 Based on latest (last Monday) feedback from EN/EL XXX As foreseen originally Partially ‘As foreseen originally‘ Postponed.
SPS New Wire Scanner Mechanics Review
BI SW for LINAC4 On behalf of BE/BI/SW BI software development process Specifications List of BI Systems – Not covered: PSB ring systems Conclusions Lars.
Matching and Synchrotron Light Diagnostics F.Roncarolo, E.Bravin, S.Burger, A.Goldblatt, G.Trad.
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
Linac4 FBCT’s 18/ L4 BI BCT review Lars Søby On the behalf of: M. Andersen, D. Belohrad, L. Jensen, Franco Lenardon and J. C. Allica Santamaria.
Status Report of the PSB Half-Sector and Stripping Foil Test in L4T
Linac-4 current situation and outlook U. Raich, F. Roncarolo, F. Zocca.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
The Stripping Foil Test Stand in the Linac4 Transfer Line
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
LIU-ABT systems: SPS B.Balhan, J.Borburgh, H.Day 20 th November 2015.
Based on Lars’ progress report of LIU SPS BI Status of follow-up 13/10/2015Lars K. Jensen, V. Kain1.
Next Steps, Priorities, Strategy for Spares Ray Veness.
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
Beam Instruments PSB + Transfer Lines B. Mikulec, J-F. Comblin.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
BI Activities for LS2 Ray Veness for BE-BI.
Overview Consolidation projects for PS LIU-PS Main observable review Conclusion Acknowledgements S. Gilardoni R. Steerenberg G. Metral H. Damerau BI colleagues.
Updated Overview of Run II Upgrade Plan Beam Instrumentation Bob Webber Run II Luminosity Upgrade Review February 2004.
The 1 st year of TMS operations Stéphane Bart Pedersen BE-BI-SW November 2011.
PSB Injection Overview + Specification changes ABT LIU Project Review Wim Weterings.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
LIU-SPS action list for BE/BI L. Jensen with input from BL, PI, QP, PM 27/08/2015Lars K. Jensen BE/BI/SW1.
LIU-SPS progress for BE/BI L. Jensen on behalf of BE/BI 27/08/2015Lars K. Jensen BE/BI/SW1.
PSB H- injection concept J.Borburgh, C.Bracco, C.Carli, B.Goddard, M.Hourican, B.Mikulec, W.Weterings,
L4 BCC – 1 Sep 2011 F. Roncarolo, U. Raich L.Soby, J.Tan, C.Zamantzas, F. Lenardon, C.Vuitton, G-J.Focker.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
INJECTORS BLM SYSTEM: PROGRESS REPORT Christos Zamantzas on behalf of the BLM team. MSWG 28/08/2015.
Linac4 Project Meeting 1/2011 3/3/2011 M. Vretenar Update on schedule and structure 1.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
LIU EL-FC ACTIVITIES Georgi Minchev Georgiev EN-EL-FC EDMS
Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo,
PS-LIU status S. Gilardoni – BE/ABP H. Damerau – BE/RF LIU-PT 27 Aug
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
Linac4 BCC 14/10/2010 Linac4 Measurement and Dump Lines BCC on the Linac4 Transfer Line Status.
LIU-PSB Working Group meeting: 25/06/2015, Markus Zerlauth Consolidation of magnet interlocks in the PS complex – Warm magnet Interlock System (WIC) R.Mompo,
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
Cost and schedule for ELENA Beam Transfer Systems W. Bartmann, J. Borburgh, E. Carlier, L. Ducimetiere, T. Fowler, M. Hourican, R. Ostojic, L. Sermeus.
ELENA installation progress F. Butin / ELENA collaboration.
Wim Weterings Remy Noulibos
26/11/2015 LIU-PSB meeting, Status of BE and BT kickers and septa 2 Extraction and Recombination Septa and Kickers status Jan Borburgh, M. Atanasov, W.
Status of the BI Work Package in the LIU-PSB frame
Linac4-PSB 160 MeV connection readiness review
Experience with beam instrumentation at Linac4
BE-CO Activities for LIU-CPS and LIU-SPS
J.-L. Sanchez Alvarez(PSB-EIC)
LINAC4 ADVISORY COMMITTEE
Brief Status SPS Prototype PSB Prototype Installed in LS1
EYETS David Hay EN-OSS.
ELENA installation and commissioning status
LIU Wire Scanner Milestones June 2017
LIU – EVM status and next steps
Injectors BLM system: PS Ring installation at EYETS
LIU–PLI report LIU PSB meeting.
EC Activities Status for the LIU
BE-BI Software for LINAC4
F. Zocca, F. Roncarolo, B. Cheymol, A. Ravni,
BE/RF-IS Contribution to LIU C. Rossi and M. Paoluzzi
Status of the BI Work Package in the LIU-PSB frame
HALF SECTOR TEST: a test for the future PSB injection
WPs concerned by L4 connection:
PSB-PS instrumentation for LIU
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
Remote setting of LHC BLM thresholds?
CONSOLIDATION CPS-BL SYSTEM
Status of the BI Work Package in the LIU-PSB frame
SPS Injection BIS - Draft requirements
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

Status of the BI Work Package in the LIU-PSB frame Jocelyn TAN, BE-BI Thanks to the contributions of the WU holders: J. Belleman, P. Odier, F. Roncarolo, S. Burger, D. Gerard, C. Zamantzas, B. Dehning. LIU-PSB meeting, 21 st Speptember 2015

Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS −LS2 Summary 3

LIU-PSB-BI Work Package Total budget: 3635 kCHF 5 budget codes 4 cost drivers represent 79.8 % of the WP budget −Wire Scanners: 970 kCHF −Booster TMS: 750 kCHF −Upgrade for L4:648 kCHF −BLMs: 532 kCHF 4 Machine sectorTotal: 20 Work Units BI line2 H - Injection & Half Sector Test6 + 3 Ring5 Extraction lines4

LIU-PSB Milestones LS1: 1.5 year Half Sector Test −Part 1: L4T  Q −Part 2 : HST  Q EYETS = Extended-Year-End Technical Stop −16 weeks, from Dec to March 2017 −All WPs related to Linac4 connection: end 2016, should ● Linac2 fail all of a sudden. ● LHC experience a major problem LS2 for the PSB −Upgrade: 15.5 months, from 07 January 2018 to 16 April 2019 −All WPs related to PSB energy upgrade −Linac4 connection to PSB if not done during EYETS Presently there is no management decision to relax on the end-2016 deadline for the Linac4 connection to the PSB. Therefore this has to stay the baseline for our planning. 5

Upgrade of BPMs in BTM & BTP extraction lines −8 monitors + 2 spares −New front and back end electronics for compatibility with Linac4 beams −New lab test bench −Budget : 264 kCHF −COMPLETE 6 Work Units completed during LS1 BTP.BPM10

Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS −LS2 Summary 7

HST Part1 One BTV in L4T (permanent installation for stripping foil) HST Part2: Temporary installation One BTV in front of proton dump (AD type) Two FBCTs (cost free) One BTV system for foil inspection – To be re-used Courtesy: S. Burger New H - charge-exchange injection system Beam Profile and Foil Inspection Half Sector Test Part1Half Sector Test Part2BTV screens at stripping foil Budget91 KCHF110 kCHF StatusCabling: COMPLETEDesign, integration: COMPLETE Production of 4 monitors +2 spares: COMPLETE DIC: SUBMITTED 2015Q3: interlock system under test Q4: monitors’ assembly 2016Q3: InstallationQ4: Installation EYETS Cabling and Installation BaselineQ3 2016Q4 2016End 2016 Open actionCF flanges for BTV exchange and spare status: can be closed

HTS Part1 only electronics for stripping foil current monitoring in L4T HST Part2 Titanium plates to be installed in front of one H0/H- dump for H0/H- current monitoring New H - charge-exchange injection system H0/H - Current Monitor Courtesy: F. Roncarolo Half Sector Test PART1Half Sector Test PART2H0/H- current monitoring Budget10 kCHF50 kCHF StatusDIC: SUBMITTED Mechanical design APPROVED Electronics design: REVIEWED WITH OP An Engineering Specification Document being prepared. To be discussed with OP. 2015Fall Q3: Amplifier prototypeQ4: Monitors’ production Q1: Commissioning VME+ADC Q3: Installation Q4: Installation EYETS Cabling BaselineQ3 2016Q4 2016End 2016 Open actionSpares status and cost (4 spares, aligned with magnets): can be closed

10 New H - charge-exchange injection system Beam Loss and Interlock Systems beam Half Sector TestBLMs for MonitoringBLMs for Observation BUDGET5 kCHF30 kCHF137 kCHF StatusBLM support design and integration: COMPLETE DIC: SUBMITTED 2015Installation + cablingElectronic board validationDiamond detector procurement 2016Q3: CommissioningElectronic board procurement EYETS Installation and Cabling BaselineQ3 2016End 2016 Ionization chambers : x6 LHC type Monitoring foil degradation Machine protection (H0/H - dump) Interlock Diamond: x8 Monitor fast losses & foil degradation Optimize stripping efficiency, OASIS aqn. Both detectors share the same support system Courtesy: W. Weterings, C. Zamantzas

Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS −LS2 Summary 11

12 Courtesy: M Hourican New injection septum for 160 MeV beams Based on existing system: linear, no interlock, OASIS Specifications −Ensure the distributed beams are centered in their respective apertures for incoming beams only −input plates: stripped electrons charge deposition BEAM PROFILE BI.SMV position measurement plates w/ Linac4 New BI.SMV BI.SMV Position plates BUDGET50 kCHF Status Integration by ABT: COMPLETE 4 Ti plates assemblies, 3 assemblies for the instrumentation supports: DELIVERED. In metrology’s hands DIC: SUBMITTED 2015Q4 : Installation in BI.SMV EYETS Cabling BaselineEnd 2016 Open actionPosition for outgoing beams ruled out: can be closed

BEAM PROFILE New Housing for BI.BTV30 Courtesy: D. Gerard MOTIVATION: The need of longer magnetic length for BI.SMV induced by Linac4 beam energy BI.BTV30 BUDGET60 kCHF StatusDesign: COMPLETED EN-MME jobs: STARTED 2015 ECR: to be issued in the shadow of BI.SMV’s ECR EYETS installation BaselineEnd 2016 Open action2015: ECR pending

14 BEAM PROFILE Turn by turn meas. for injection matching w/ Linac4 Courtesy: F. Roncarolo Section 4L1 SEM H+V SEM grids for PSB ring3 BUDGET135 kCHF Status DIC: SUBMITTED No mechanical design started. Proposed SEM’s integration: section 4L1 Electronics design: only just started for PSB, but with slight modifications can also be used for PS, where it will probably first be tested. Radiation hot spot there: 22 kGy/year (2013). RadMons added by RP on Sept. 2 nd fall 2015: SRR / Q1 2016: ECR EYETS Installation and Cabling BaselineEnd 2016 Open actions BI proposes to postpone installation to YETS – old PS SEM gets priority Decision on spare grids to be taken once the final design is clear Specifications : SEM grids injection of half a PSB turn to well separate turn-by-turn profiles (over 20turns) External condition interlock : to shorten the Linac4 pulse (1turn max) PPM In/Out: ruled out option Permament implementation for commissioning, MDs and operation

BEAM INTENSITY Measurement of injection efficiency with Linac4 15 Courtesy: P. Odier BR.TMD in 8L1 section BUDGET198 kCHF Status DIC: SUBMITTED One BCT available (without shielding) in the laboratory Bld 109 : not needed for machining. Dose rate in Section 8L1 is reasonably low: ~1.6 kGy/y Work Dose Planning for 30.3 man.days: submitted to RP 2016 Acquisition chain: HW production, SW specification Spare ceramic chamber EYETS Refurbish the monitors in the BI radioactive workshop; installation and cabling BaselineEnd 2016 Open actionsALARA: can be closed Specifications Four monitors BR.TMD in 8L1, installed in ’72, un-used since early 80s’ Analog turn by turn acquisition, up to 100 turns Watchdog : comparison with BI.BCT20 after 100 turns

BEAM INTENSITY Quantify total intensity transmission during PSB cycle 16 Courtesy: P. Odier DC Current Transformer BUDGET114 kCHF Status Acquisition chain: upgraded ADC and Expert GUI Front End Electronics: assembled but not installed due to higher priorities Test of the new B-Train Receiver Installation of the new Front End Electronics (YETS 15-16) EYETS Installation of the new B train Receiver Adaptation for Linac4 intensities BaselineEnd 2016 CommentNow with Linac2: Np=1E13p per ring. Is 2.5e13 per ring still realistic with Linac4 ? Can we relax this specs. ? Summary Four monitors BR.BCTDC in section 9 (DCCT) Upgrade of the acquisition chain

17 BEAM POSITION Ring Trajectory Measurement System Courtesy J. Belleman Booster Trajectory Measurement System BUDGET750 kCHF Status DIC: SUBMITTED One full ring can be acquired, multiplexed Software: FESA interface, with hooks for YASP and the Sampler + Expert GUI TS3: Three new passive front ends installed. We’re still using the old front-end electronics Amplifiers still need some work but are located outside the tunnel Fall 2015: Demonstrating 200  m resolution down to a beam intensity of 1e10p/b EYETS Cabling: About 250 cables to converge towards BOR ! Electronics deployment Software upgrade for Gain, Calibration, etc… BaselineEnd 2016 Comments Decommissioning of old system : no way back After cabling complete, at least one month needed to fully test the system: will this be available ? Open action Demonstrating reliable operation with new firmware/software: can be closed Fall 2015: Demonstrating 200  m resolution down to a beam intensity of 1e10p/b Specifications − Bunch-by-bunch, turn-by-turn trajectories over the whole cycle − Various derived averages (Orbits, MRP) − Position resolution 200μm − No more multiplexing over the four rings − New front-end electronics with settable gain Front-end boxes: dated from 1974

18 BEAM POSITION Wide Band BPM in the BTP line Courtesy J. Belleman Wide Band Pick-Up in BTP line BUDGET75 kCHF Status DIC: SUBMITTED Production design: under approval FE electronics: being assembled 2015 ECR approved but for installation during YETS 15-16: we are not ready Q4: BPM production EYETS Installation and Cabling BaselineEnd 2016 Comments ECR: modification for installation in EYETS Specifications Spot transverse instabilities during beam transfer between PSB and PS Based on existing PS design (section 94) Acquisition : OASIS WB pick-up Proposed layout in BTP

19 BEAM LOSS PSB and Transfer lines BLM system ICs for L2 sectionICs for Transfer linesFICs for L3 sections Budget127 kCHF211 kCHF164 KCHF StatusCKC50 cables: produced. Supports: installed. Rack: Installed & connected. Electronics:produced, tested DIC, DIR, DEC: submitted monitors & electronics: procured. L3 section supports: designed. BLM supports: tested during TS DIC, DIR, DEC: submitted 2015Validation of electronic board. ICs and spare channels to be installed September: integration check and then production 2016Electronic board productionECR EYETS Cabling : DIC, DIR, DEC submitted BaselineLS1End 2016 CommentsBLM’s specs: Partial agreement of Rende, who needs internal discussion with PS team. Will finalize soon. Ionization Chambers in Transfer lines : 36 ICs +7 spares from LHC, not paid by LIU Flat Ionization Chambers in L3 section: 32 new FICs

20 BEAM TUNE New Tune pick-ups in 3L1 Present capacitive pick-up in 3L1 3L1 Tune pick-ups BUDGET100 kCHF Status Specifications: under discussion New WU request. Not approved yet BaselineEnd 2016 Comments Deadline is unrealistic Need to prioritise w/ BI-ML between Ring3 SEMs, BWS, and tune PUs Availability of EN-MME to be discussed Budget not yet allocated MOTIVATION: Poor sensitivity of present pick-ups for LHCPROBE beams

Outline Foreword BI Milestones −LS1 −New injection section & Half Sector Test −EYETS −LS2 Summary 21

BEAM PROFILE New Housings for BT.BTV10 and 30 Courtesy: D. Gerard MonitorBT.BTV10BT.BTV30 Budget84 KCHF StatusTanks installedDesign: COMPLETE ECR: approval closed. To be released mechanical parts : production ECR: approval closed. To be released Tank, mechanical parts : production EYETS Modification of adjacent pipes LS2Monitors installation – earlier if possible (EYETS 16-17) BaselineLS2 MOTIVATION: The need of longer magnetic length for Septa induced by increased beam energy

23 BEAM PROFILE Wire Scanner Aim : adaption of the scanner design for the PS and SPS to the limited space in the PSB First proposal : Section 11L1 Courtesy: B. Dehning 2nd section: 4L1, shared with SEMs Wire scanner BUDGET970 kCHF Status Development of control end acquisition electronics advancing Integration: sections 11L1 + 4L1 possible Two prototypes (SPS + Lab) are used for optimisation and development of controls electronics 2015 To do: SRR + ECR + DIC EYETS production of a prototype scanner for installation in the PSB 2017 PSB Prototype commissioning BaselineLS2 Comments WU is out of the critical path Fall 2015: Engineering specification Mid 2016: Final cost updated once prototype is built

Summary LS1: one WU completed HST: on time Part 1 & Part 2 Open actions: a few left to be addressed EYETS −H - injection section, BLMs and BTMS: A large cabling effort required −Late WU request: Tune pick-ups in 3L1. Baseline unrealistic for BI YETS −Proposed installation date for the injection matching monitor, ie 1 year after baseline LS2 −BWS: A prototype for test in the PSB during the run WU is out of the critical path, Budget −All planned activities are within the budget… BUT −BWS: final cost known by Mid’ 2016 −Missing 100 kCHF for the tune pick-ups −Most WUs includes spares 24

THANK YOU FOR YOUR ATTENTION!