SiD Engineering and Solenoid Kurt Krempetz (Layer 5) (Layer 1) VXD.

Slides:



Advertisements
Similar presentations
SiD Surface assembly Marco Oriunno (SLAC) MDI-CFS Meeting Sep. 4-6, 2014, Ichinoseki (Japan)
Advertisements

Assembly Hall in Hybrid-A’ and ILD 2014/9/6 Yasuhiro Sugimoto 1.
Global Design Effort Detector concept # Plenary introductory talk IRENG07 Name September 17, 2007.
NLC - The Next Linear Collider Project IR Layout Tom Markiewicz SLAC LCWS Cornell 15 July 2003.
DH in Hybrid-A and ILD 2014/9/5 Yasuhiro Sugimoto 1.
Experimental hall in Japanese mountain site Y. Sugimoto ILD MDI/Integration 1.
Push Pull Considerations
Global Design Effort Detector concept Plenary introductory talk IRENG07 Kurt Krempetz September 17, 2007.
3 March 2009M. Breidenbach1 SiD LoI Costs M. Breidenbach.
1 Design of Solenoid and iron yoke for GLD KEK Hiroshi Yamaoka Ken-ichi Tanaka July 13, ‘05.
Tracking Integration Challenges Y. meeting 2013/9/25.
1 ILD/CMS Engineering Meeting M. Joré – ILD integration philosophy Integration philosophy of ILD Matthieu Joré – January 21st Integration of the subdetectors.
SID Engineering Marco Oriunno (SLAC), Jan CLIC Workshop, CERN Toward the TDR.
1 Alternative assembly option of ILD Y.Sugimoto 2010/10/18 ILD Integration
Experimental hall in Japanese mountain site Y. Sugimoto 1.
SiD Engineering Status Report Kurt Krempetz (Layer 5) (Layer 1) VXD.
Philip Burrows SiD Meeting, Paris 11/02/081 Machine Detector Interface Issues Philip Burrows John Adams Institute Oxford University Thanks to: Tom Markiewicz.
September 18, 2007H. J. Krebs1 SiD Collaboration One Piece End Door Design Concept plus Forward Equipment Interfaces H. James Krebs SLAC September 18,
SiD Engineering: Iron and Solenoid Design Kurt Krempetz (Layer 5) (Layer 1) VXD.
KEK Hiroshi Yamaoka Task list for Magnet/Iron yoke Solenoid magnet Iron yoke Experimental hall and other facilities May 11, ’05.
1 GLD and GLDc Sep. 12, 2007 Y. Sugimoto KEK. 2 Compact GLD Option Motivation –GLD and LDC will write a common LoI –The detector design should have common.
Zian Zhu Magnet parameters Coil/Cryostat/Support design Magnetic field analysis Cryogenics Iron yoke structure Mechanical Integration Superconducting Magnet.
HCAL Mechanical Design Victor Guarino HEP-ANL. Work to date.. Have been thinking about how to construct individual modules and assemble them into a barrel.
SiD IR & MDI Engineering Progress Prelude to a Discussion of Integration with ILD and Based on Marco Oriunno’s Jan 2008 Talk at SiD CM Tom Markiewicz/SLAC.
SiD Engineering Design for the LOI Kurt Krempetz (Layer 5) (Layer 1) VXD.
CEA DSM Irfu - F. KIRCHER - [Seoul Workshop, Feb 16-18, 2009] 1 ILD detector magnet: LoI version F. Kircher, O. Delferrière CEA Saclay, DSM/Irfu/SACM.
SiD Conceptual Engineering Status Report Kurt Krempetz (Layer 5) (Layer 1) VXD.
MDI DBD Editors Report Tom Markiewicz/SLAC SiD Collaboration Meeting, SLAC 22 August 2012.
SiD R&D tasks for the LOI - Subsystem R&D tasks - Summary of SiD R&D - Prioritization of R&D tasks -> Document for DoE/NSF ~Feb 2009 (Mainly based on Marty’s.
Aki Maki1 GLD Costing Aki Maki KEK 27/4/2006. Aki Maki2 Cost Summary 27/04/06 GLD COST SUMMARY –Solenoid Magnet**-** B JPY –Cryogenic System***** B JPY.
The HCAL barrel absorber structure
MEA Machine and Experiment Assembly Norbert Meyners, MEA 17. Sept. 2007ILC IRENG07; SLAC1 LDC Engineering Design (Status)
GLD experimental hall and detector assembly Y.Sugimoto KEK 27 Sep
SiD Collaboration Meeting Highlights Tom Markiewicz/SLAC ILC BDS Meeting 08 May 2007.
Global Design Effort Magnetic and Mechanical FEA of SiD IRENG07 Bob Wands September 18, 2007.
Assembly scenario of ILD Si trackers 2015/4/21 Yasuhiro 1.
September 20, 2007H. J. Krebs/B. Wands/B. Cooper1 SiD Collaboration Preliminary End Door Design Concept Support of Forward Systems H. James Krebs Bob Wands.
ILD and SiD in Japanese site (from discussions in SiD/ILD E/D Interface Working Meeting) Yasuhiro Sugimoto, Marco Oriunno 2011/12/15 SiD
SiD MDI Issues Tom Markiewicz/SLAC Beijing ACFA/GDE Meeting 05 February 2007.
Experimental hall in Japanese mountain site 2011/11/30 Yasuhiro CFS Webex meeting 1.
MEA Machine and Experiment Assembly Norbert Meyners, MEA 12. July 2007ILC IRENG07 WG-A1 LDC Engineering Design (Status) Introduction General Design Detector.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
1 Implementation at RAL Iouri Ivaniouchenkov on behalf of Elwyn Baynham, Tom Bradshaw, Tony Jones, Jim Rochford Engineering Department, RAL MICE Collaboration.
Philip Burrows SiD Monthly Phone Meeting, 4/10/071 IR Issues from IRENG07 Philip Burrows John Adams Institute Oxford University.
12 July 2007IRENG07 WG-A M. Breidenbach1 SiD Concept SiD is relatively modest in scale compared to the LHC detectors, and comparable to SLD: Tracker Radius.
June 2, 2008 Bill Wisniewski1 BaBar Disassembly and Disposal Overview.
Octobre LAL Orsay Report from the IRENG07 workshop at SLAC W. Lohmann, DESY from Septembre 17 – 21, ~ 100 participants - plenary and parallel sessions.
An idea of ILD general assembly plan 2015/10/8 Yasuhiro Integration Meeting 1.
M.Oriunno, SLAC 1 SiD installation with horizontal access shafts Marco Oriunno, SLAC SiD/ILD Engineering Meeting SLAC, December 2011.
What’s new at LAL-LLR ( MDI issues) M.Jore, C.Clerc Visit at CMS Forward detectors meeting at LLR Vacuum in Beam pipe, first LAL results.
1 Update of detector hall in mountain regions Y.Sugimoto in Granada.
Experimental Hall in Mountain Regions
2016/9/30 Yasuhiro Infra/CFS mini-ws
Yasuhiro Sugimoto 2012/2/1 ILD integration meeting
Experimental hall design in Japanese site
Layout of Detectors for CLIC
SiD Muon Yoke Structure - Deformation Studies -
Update of experimental hall in Japanese mountain site
SiD Solenoid Status and Plans
LumiCal mechanical design, integration with LDC and laser alignment
SiD LoI Costs M. Breidenbach 29 July 2010 M. Breidenbach.
Detector hall in mountain regions
Changes to SiD since the DBD
Sub-Detector Assembly Area Summary of discussion at ALCW2015
ILD-0 overall dimensions C.Clerc ILD meeting, Seoul 17/02/09
SiD Engineering Status Report
SiD IR Layout M. Breidenbach, P. Burrows, T. Markiewicz
Detector hall in mountain regions
Extract from today’s talk given to DCB
A 12-min Introduction to The ILC Machine Detector Interface and SiD
Presentation transcript:

SiD Engineering and Solenoid Kurt Krempetz (Layer 5) (Layer 1) VXD

Kurt KrempetzALCPG-10/072 SiD Engineering Group Engineers Physicists –ANL Victor Guarino  Hcal –FNAL Bob Wands  FEA Bill Cooper Joe Howell Kurt Krempetz  Integration Walter Jaskierny  Solenoid Electrical –PSL Farshid Feyzi  Muon Steel –SLAC Jim Krebs  EndDoorsMarty Breidenbach Marco Oriunno  Ecal Tom Markiewicz Wes Craddock  Solenoid –RAL Andy Nichols  TrackingPhil Burrows

Kurt KrempetzALCPG-10/073 SiD Engineering Group Function/Purpose Realism into the Detector Supports Tolerances Fabrication Limitations Cost Estimates Safety Issues Help integrate the detector sub-system into an overall Detector Define Clearances –Assembly –Cables and utilities Document the design choices and the design Document and manage changes

Kurt KrempetzALCPG-10/074 Plans/Schedule-Now Moving forward to LOI 10/07 to 2/08 Identify liaison from each Sub-detector group to work closely with SiD Engineering group. Understand and refine the DOD SiD starting point. Define the sub-detector space and parameters(Global Parameters) –Sub-detector modules-weight/size/cables/utilities/dead space –Sub-detector assemblies-clearances/dead space –Sub-detector assembly supports Create Control Board/Committee Create engineering drawing/database

Kurt KrempetzALCPG-10/075 Moving Forward Subsystem Liaisons –Vertex  Bill Cooper –Silicon Tracker  Tim Nelson –Ecal  Marty Breidenbach –Hcal  Andy White –Muons  Henry Band –Forward  Bill Morse –MDI  Tom Markiewicz

Kurt KrempetzALCPG-10/076 Global Parameters DOD

Kurt KrempetzALCPG-10/077 Global Parameters Marty’s Spreadsheet DetectorRadius (m)Axial (z) (m) MinMaxMinMax Vertex Detector Central Tracking Endcap Tracker Barrel Ecal Endcap Ecal Barrel Hcal Endcap Hcal Coil Barrel Iron Endcap Iron Inter-Detetcor Gapsm DR_GAP_Trkr_EMCal0.015 DR_GAP_EMCal_Hcal0.015 DR_GAP_Hcal_Cryostat0.030 DR_Gap_Cryostat_Steel0.030 Gap between Barrel and End cal DR_Gap_BEcal_ECEcal=.02m DR_Gap_BHcal_ECHcal=.01m DZ_Gap_CT_ECEcal=.01m DZ_Gap_BEcal_ECHcal=0 DZ_Gap ECEcal_ECHcal=0 DZ_Gap_BHcal_EndIron=.01m

Kurt KrempetzALCPG-10/078 IR Engineering Meeting-SLAC Sept Assembly Scenario Solenoid tested to full field on surface Other Sub-systems are also constructed and tested on surface. Defines a surface building –Roughly 24mX24mX24m –500 tonnes crane (smaller hoists should also be available)

Kurt KrempetzALCPG-10/079 IR Engineering Opening Procedures on beamline –Need to access Electronics  End caps open 2m Roughly 16m total –Small Crane system (~5tons) –Time Duration  20hrs Power down magnet-4hrs Open End Caps- 4hrs Perform work- 4hrs Close End Caps- 4hrs Power up magnet- 4hrs

Kurt KrempetzALCPG-10/0710 IR Engineering Detector Opened 2 M

Kurt KrempetzALCPG-10/0711 IR Engineering Opening Procedures off beamline –Detector Motion  End caps open 2m Frequently for Electronics maintenance –Detector Motion  End caps open 3m Possible every 6 months for Vertex and Tracker maintenance Possible every few years for Vertex Detector replacement Time Duration for Opening or Closing  about 1 week –Detector Motion  End caps open 6m Possible every 5 years for Upgrades –Tracker Detector System –ECal Silicon Detectors –HCal RPC’s –Muon RPC’s –Crane System for above scenarios (~25 tons plus another smaller hoist)

Kurt KrempetzALCPG-10/0712 IR Engineering Detector Opened 6M

Kurt KrempetzALCPG-10/0713 IR Engineering Opening Procedures For Major Issues –Solenoid Repair –Absorber Plates Replacement Under Shaft –Safety issues maybe a problem

Kurt KrempetzALCPG-10/0714 IR Engineering General Safety Radiation –Self Shielding Detector Fire Safety –No Flammable Gases –Halogen-free Cables –Smoke Sensor in all sub detectors Seismic Safety –Looking for guidance; Site dependent ODH Issues –Looking for guidance

Kurt KrempetzALCPG-10/0715 IR Engineering Alignment Issues Positioning accuracy needed for detector after it was moved to IP in push-pull operation –1 to 2mm Final/fine adjustment done by a positioning system; Frequency Scanning Intereferometer (FSI) approach is being considered. –Positions Vertex Detector Beam pipe LumCal,GamCal and BeamCal QDO

Kurt KrempetzALCPG-10/0716 IR Engineering Stability of IR Hall Settlement of Floor –<1-2 mm/Detector Exchange Temperature –21 Degrees C –Plus or minus 1 Degrees C variation with time –Plus or minus 3 Degrees C at different hall locations Dewpoint –< 12 Degrees C or 56% relative humidity

Kurt KrempetzALCPG-10/0717 IR Engineering Stability of IR Hall Settlement of Floor –<1-2 mm/Detector Exchange Temperature –21 Degrees C –Plus or minus 1 Degrees C variation with time –Plus or minus 3 Degrees C at different hall locations Dewpoint –< 12 Degrees C or 56% relative humidity

Kurt KrempetzALCPG-10/0718

Kurt KrempetzALCPG-10/0719 IR Engineering Summary Most of the Detector Assembled at Surface Push-Pull Scenario 18m Diameter Shaft for each Detector Weight to be lower down shaft  TBD ton cranes in IR Hall 23m crane travel in IR Hall –IR Hall width ~25m if one includes alcoves

Kurt KrempetzALCPG-10/0720 IR Engineering Baseline Global Design Decisions Moving Large pieces around Air Pads vs Hillman Rollers  Hillman Rollers Platform vs no-platform  No platform Self-Shielding vs Shielding walls  Self Shielding Major Assembly above Ground vs Underground  Above Ground

Kurt KrempetzALCPG-10/0721 Hcal Engineering Activity Define some engineering specifications –Barrel IR=1420mm OR=2370mm Z=+-2780mm Cables/Utilities come out at end of barrel Barrel installed as one complete unit into Solenoid Support of Hcal Barrel to Solenoid inner shell is at ~3 and ~9 o’clock positions along length Hcal modules(not absorber plates) removal in IR garage position from barrel ends Ecal and Silicon tracker weights are carried by Hcal. –EndCap IR=200mm OR=1410mm Z=+-1820mm to 2780mm Cables and Utilities come out radically (outer) from disk Endcap is one unit which is support by cantilevering it from the End Iron Endcap modules (not absorber plates) removal in IR garage position-radically

Kurt KrempetzALCPG-10/0722 Hcal Absorber Plates Try to design one common absorber plate configuration –Plate thickness-20mm –Gap thickness-8mm –No point cracks to IP, minimize all cracks/dead space –Detector modules are removable from gap –Absorber Material might change

Kurt KrempetzALCPG-10/0723 Hcal Questions 1.Max/Min Size of a Detector Module Width? Length? Height? 2. Shapes that modules can be formed into? Rectangles? Must they be flat, can edges be tapered? 3. Dead space between detector module edge and active area? 4. Clearance between detector module edge and next detector module edge? 5. Can the detector module support themselves? 6. Where can the detector module be support from? 7.Utilities needed in and out of the detector module? Gas? High voltage? Cooling? Power cables? Signal cables? 8. Where are the utilities coming out of the detector module, sides, ends, top, bottom? 9. How well must the detector module be held in the gap? Positioning x,y,z tolerances? 10. Detector modules have fiduals? Detectors get survey after installation? –

Kurt KrempetzALCPG-10/0724 SiD Solenoid Baseline 5 Tesla 5m diameter clear bore 5m Long 6 Layers Stored Energy 1.4 GJ Water Cooled Dump Resistor

Kurt KrempetzALCPG-10/0725 Flux Return Octagonal Barrel and Endcaps Fringe Field Issues outside the detector –<100 gauss Thickness of plates, number of plates/gaps are being studied

Kurt KrempetzALCPG-10/0726 The Two Iron Geometries plates are 20 cm; gaps are 5 cm clearance is 1 cm

Kurt KrempetzALCPG-10/0727

Kurt KrempetzALCPG-10/0728 Increase thickness of outer barrel by 0.2 m, increase radial thickness of endwall corner by 0.2 m distance - m

Kurt KrempetzALCPG-10/0729 Summary Lots of work ahead People are stepping forward ……… but we need more!!! A great relationship between Engineers and Physicists is need so an excellent LOI can be developed.