TC meeting P2 planning wks 9&10 A.Tauro 28-2-2012.

Slides:



Advertisements
Similar presentations
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

Far side Near side -Z End +Z End 5m Wed Dec 7 ECAL CMXZEC CSC REDT+ RBTK FPIXSurvey HCAL TE-VSCEN Dept SL CP Availability.
LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 7&8 A.Tauro
DCS - general Unscheduled power cut Wed. morning ( , human error) –DCS (and HLT) off, due to UPS on bypass –In the middle of DB migration, had.
winter shutdown preparatory meeting A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
winter shutdown planning A.Tauro
LS1 reference slides LS1 plans Detector’s plans Services and central systems availability 8/2/13LS1 planning meeting - A.Tauro1.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
LS1 planning meeting Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore.
ALICE 5 o’clock meeting Wk 49
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
Livoti Drawing and Painting 6/8 to 6/12. Mon 6/8 Final Exam Multiple Choice testing.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
ALICE TC meeting – Plans for the next technical stop A. Tauro.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
ALICE planning meeting /2/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
winter shutdown planning A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
Overview of also works.
ALICE 5 o’clock meeting Wk 49
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
25/3/2009Detector Cooling Project Meeting I1 Running consolidation activities of ALICE Detector Cooling Systems A.Tauro.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
EYETS planning A.Tauro.
ALICE 5 o’clock meeting Wk 51.
5 Day Forecast Mon Tues Wed Thu Fri.
TS2 preparatory meeting
LS1 planning meeting - A.Tauro
LS1 planning meeting
Pronouns and Antecedents Chapter 5 Pronouns and Antecedents Chapter 5
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
ALICE TC meeting – Plans for the next technical stop
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
ALICE 5 o’clock meeting Wk
Time Revision.
MON TUE WED THU
2017 Jan Sun Mon Tue Wed Thu Fri Sat
Jan Sun Mon Tue Wed Thu Fri Sat
2008 Calendar.
Sun Mon Tue Wed Thu Fri Sat
Sun Mon Tue Wed Thu Fri Sat
1/○~1/○ weekly schedule MON TUE WED THU FRI SAT SUN MEMO
2016 | 10 OCT SUN MON TUE WED THU FRI SAT
Sun Mon Tue Wed Thu Fri Sat
2008 Calendar.
Presentation transcript:

TC meeting P2 planning wks 9&10 A.Tauro

Planning wk9 DSO test: no access UX25 on Thu 1 st Mar (and on 2 nd, as a reserve) PH-DT (gas-group): upgrade of the PLC and PVSS codes. The intervention will last about 8 hours Mon 27th TPC laser (start on Wed PM) SPD cooling  drill SR7 on Mon Transport + P2tech: PX24 plug (small blocks, Mon) Close hole in MNF shielding (Tue) Restart L3 and Dipole cooling (test on Tue between 10:00 and 12:00) Removal A.C. from CR2 (Thu) MTG: restart isobuthane (Tue) HMP: restart methane (Tue) Muon TRK: –Repair slats on ST3-ST4-ST5 BE-ABP-SU: survey ST3-4-5 and network measurement with new instrument. Scan L3+MNF from low-beta (if possible) EN-CV: install and commissioning new PMD ventilator unit EN-CV-DC: finalize TPC-RR filters installation and SSD-SDD ramp-up 28/2/12TC meeting - A.Tauro

Planning wk10 SPD cooling P2tech: reinstall green fences C-side Muon TRK: –Repair slats on ST3-ST4-ST5 Move PMD to final position (Mon) Reinstall ADA BE-ABP-SU: PMD survey (Tue) EN-HE: removal crane electronics (Fri) EN-CV-BE: start-up and commissioning new ITS dehumidifier (5 th Mar) TE-VSC: open manual valve in MNF (Fri) T0: check electronics (9 to 12/3) ONET: cleaning UX25 cavern INEO: install 220V sockets in backframe (Tue) and miniframe (Wed) 28/2/12TC meeting - A.Tauro

AOB Confined training course tomorrow, Wednesday, at 9:00 at P2 –See with Fernando if you are interested to follow the course 28/2/12TC meeting - A.Tauro