January 4, 2007 RHIC II Project Internal Cost Review Existing RHIC power supply Modifications Don Bruno & George Ganetis January 4, 2007 Power Supply Modifications.

Slides:



Advertisements
Similar presentations
MICE Coupling Coil Testing at Fermilab MICE Collaboration Meeting Ruben Carcagno March 15, R. Carcagno - MICE CC Testing at Fermilab3/15/2012.
Advertisements

André Augustinus 16 June 2003 DCS Workshop Safety.
Mar 13, Low-energy RHIC electron Cooler (LEReC) CRYOGENICS Mar 13, 2014.
1 Powering Tests and Safety Electrical Safety Hugues Thiesen Power Converter Group.
G2P Target installation and Beyond. Schedule Pivot before.
Muon g-2 Muon g-2 Experiment Quarterly Report Aria Soha All Experimenter’s Meeting March 2, 2015.
M. Jimenez AT/VAC Room Temperature (LSS) Vacuum Systems M. Jimenez.
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
PEP-II Ramp Down to a Minimum Maintenance State J. Seeman DOE PEP-II Ramp Down-D&D Review August 6-7, 2007.
March 14, 2003 MICE Absorber/Coil Integration MICE LH2 Absorber 1.Assembly 2.Safety 3.Staging 4.Instrumentation.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
HQ TEST CERN by Marta Bajko CERN TE-MSC TF For Hi Lumi and LARP the 16 th of November 2011 CERN.
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
Cryo AIP Muon Campus AIP Review Arkadiy Klebaner January 23, 2012.
Workshop 12/04/2006AT/MTM SM18 Test Facility A. Siemko "Workshop on Test Facilities and measurement equipment needed for the LHC exploitation"
January 4, 2007 RHIC II Project Internal Cost Review Gary McIntyre RHIC Ring Modifications January 4, 2007 Project Overview.
Superconducting IR Magnets CHEN, Fusan May 11, 2007.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
SC Project Review of NCSX, April 8-10, 2008 NCSX Coil Services P.L. Goranson Work Package 161.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
Big Magnet Design II: a) solenoid and cable concept b) short section test V.V. Kashikhin and A.V. Zlobin.
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT 24 Feb 2004 R. BossertCERN/KEK/FNAL Meeting 1 Inner Triplet Interconnects Electrical Connections.
BGV 05-may-2015CERNMassimiliano Ferro-Luzzi 1 BGV cooling : test & installation plans  point 8  LHC tunnel.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review Vacuum Systems H.-C. Hseuh January 4, 2007 Vacuum Systems.
October, 2009 Magnet Electrical Systems Bob Lambiase October, 2009 Internal Review.
The Operation of the Tevatron Vacuum system Authors David Augustine Alex Chen Scott McCormick 1.
Extraction Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
LHC Enhanced Quench Protection System Review 24 – 26 February 2009.
October 4-5, Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule.
JRA on Development of High Temperature SC Link Motivation Work Packages Partners & resources Amalia Ballarino Esgard open meeting CERN,
Spreaders & Recombiners Beam Transport Michael Bevins May 30, GeV Upgrade - Beam Transport Spreader/Recombiner Dipoles and Layout, & Installation.
Plan for test station Marta Bajko For the Technical Review of FReSCa2 June 2015 Saclay Paris.
Vacuum, H-C. Hseuh January 4, 2007 RHIC II Project Internal Cost Review H.-C. Hseuh Vacuum Systems January 4, 2007 Project Overview.
RHIC SYSTEMS Power Supplies, Superconducting Magnets, Quench Protection, etc. 7/11/06.
AP2-Debuncher Injection Area 2004 Shutdown Work August 2, 2004.
ABT review on the LIU-PSB Systems PSB KSW Magnets September 10 th 2014 L. Feliciano TE/ABT.
RISE Research Bradley Gratton. Center for Environmental Energy Engineering (CEEE) I was able to work with a multitude of different graduate and doctorate.
SPHENIX MECHANICAL D. Lynch & R. Ruggiero July 31, /29/2014sPHENIX Mechanical Design.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
Haixin Huang AGS Cold Snake: Status and Plans.
Thomas Jefferson National Accelerator Facility Page 1 CEBAF Cryo & SRF Workshop April 3, 2014 Mathew Wright Cryogenic Systems Operations Engineer
Magnet R&D for Large Volume Magnetization A.V. Zlobin Fermilab Fifth IDS-NF Plenary Meeting 8-10 April 2010 at Fermilab.
LMC 1 (Pre Chamonix) DN200 relief valve position DN200 relief valve position On top wherever possible. Open W bellows for MLI protection. On top wherever.
8/29/07K. C. Wu - Brookhaven National Lab1 Major Components in ILC IR Hall Interchangeable Detectors.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Development of Cryo-Module Test Stand (CMTS) for Fermi Lab (R.L.Suthar, Head,CDM, BARC) Cryo-Module Test stand (CMTS) is a very sophisticated equipment.
Superconducting Cryogen Free Splittable Quadrupole for Linear Accelerators Progress Report V. Kashikhin for the FNAL Superconducting Magnet Team (presented.
Inner Triplet Review 1 H. Prin AT/MEL Activities on the triplets at CERN Reception and Acceptance Triplet String Assembly in Building 181 Handling and.
SIS 100 Vacuum chamber Recooler String system Components
Cryoplant Controls Installation
Task 5: High-Tc superconducting link Summary of work-package
HL-LHC IT STRING and Series test of SC link
Testing of SC Magnets Status - November 2010
Powering the LHC Magnets
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
PSS0 Design & Concept of Operations
as a prototype for Super c-tau factory
J. Fleiter, S. C. Hopkins, A. Ballarino
Presentation transcript:

January 4, 2007 RHIC II Project Internal Cost Review Existing RHIC power supply Modifications Don Bruno & George Ganetis January 4, 2007 Power Supply Modifications

January 4, B Service Building

January 4, Design Goals This lattice design goals for magnets and p.s.’s were to: –Accommodate ratings of shunt buses –Get polarities of magnets correct –Use existing leads in valve box –Minimize the amount of works on the magnets in the tunnel.

January 4, Magnets & P.S.’s Being Removed Magnets Q4, Q5 and the DHX and DH0’s are being removed Q4 is being installed in place of Q6 Inner Q7 p.s.’s become a stand alone p.s.’s tq-4 and tq-5 p.s.’s are being removed. Q89 bipolar 300A p.s.’s are being removed. Number of p.s.’s will go from 37 to 34 in 1002B

January 4, Valve Box Modifications Use existing leads at the top of the valve box No piping changes are required at the top for leads or for Cold Crossing bus Have to re-wire internal wiring chamber and external connections Can salvage four 1600 Gas Cooled Leads to use on separately powered inner Q7. Use existing Cold Crossing bus (CCB) and make splices to it to extend length to new triplet location For the short lengths requires the project can use spare CCB, but this has to be reviewed. We may have to order some to replace the spare.

January 4, Existing Power Supply Circuit

January 4, New Power Supply Circuit

January 4, New RHIC p.s. classes in 1002B VratingIrating Quantity for blue and yellow We can use from existing 1002B p.s.'s Need to order Spares to order Total to order bi Total

January 4, Scope Perform Engineering and Design efforts –Quench Protection/Detection –Power Supplies –Valve Box Modifications –Ring Modifications (Interconnects to be re-done to change shunt busses) –Cold Crossing Bus Splicing

January 4, Scope Buy –Quench Protection Assemblies –Power Supplies –New Quench Detection cards –Parts for Valve Box Modifications, cold crossing bus modifications –Material Ring Modifications, Electrical Interconnects –Material for inner Q7 power leads (using 1600A leads possible solution – needs to be reviewed by cryo) Installation –Quench Protection Assmeblies and Power Supplies –Quench Detector re-wiring and new card installation –Valve Box Modifications –Electrical Interconnecting and Test

January 4, Costs by WBS

January 4, Major Procurements (direct $) High Level –Power Supplies – estimated at $1029K –Quench Protection Assemblies - $420K Low Level –Valve Box Modifications - $30K –Ring Modifications – $20K –Cold Crossing Bus Modifications - $5K –Electrical Interconnecting & Test - $10K –New In-Tunnel Power Leads - $10K

January 4, Contingency & Risk Depending on installation times more technicians may be needed. The technician workforce has been scattered throughout the lab and outside the lab. We may need to bring some of these technician’s back to work on the valve boxes and electrical interconnects of magnets. We have a design from accelerator physics but the desogn is being optimized for margin on the superconducting bus and we are hoping it won’t change now.

January 4, Milestones Design –Power Supplies and Quench Protection Assembly designs exist with the vendors. –Room Temperature external Terminal Connections –Valve box internal modification designs –Magnet electrical and mechanical interconnect designs (Tunnel) Procurement –All systems ordered –All equipment received and tested Installation –Equipment installed –System tests into shorts and with cold magnets.

January 4, Assumptions We are counting on being able to use experienced technicians or extensive training will be required. There are safety concerns: an external breathing apparatus is required. Funding is available as planned/needed