Calder Hall Sellafield Decommissioning Martin Adam Heriot-Watt Edinburgh 2008.

Slides:



Advertisements
Similar presentations
Trainers Notes This package provides an overview of the major issues likely to impact on Group Training Organisations with the Introduction of the new.
Advertisements

Barhale Procedure for Site Establishment
Optimisation of New Build Spent Fuel Management and Disposal Peter Haslam Public Policy Advisor Nuclear Industry Association 25 January 2011.
1 KRB-A (Grundremmingen, Germany). 2 Type:Boiling Water Reactor Power: 250 MW(e) Started in 1966, shut down in 1977 First commercial power reactor in.
Vermont Yankee Presentation to VSNAP 7/17/13 VY/Entergy Fukushima Response Update Bernard Buteau.
Objectives: Understand importance of utility and maintenance system in industry/plant.
5/19/2015 Segmentation of the Legacy C Area Disassembly Spent Fuel Pool Prepared by: Jon Guy, N&CSE Spent Fuel Project Lead UNCLASSIFIED DOES NOT CONTAIN.
Decommissioning of Nuclear Power Plants Case Study: Dounreay Nuclear Facility Case Study: Dounreay Nuclear Facility Samuel Chapman Heriot-Watt University.
Dounreay Nuclear and Chemical Land Contamination.
UK Nuclear Policy Andrew Beirne
School for drafting regulations Nuclear Safety Decommissioning Vienna, 2-7 December 2012 Tea Bilic Zabric.
Industry information day INDUSTRY INFORMATION DAY Assembly & Installation Laurent Schmieder Buildings Infrastructure and Power Supplies Project.
The Cons of Nuclear Reactors By Michelle Trojanowsky.
Nucular Waste A Technical Analysis Ian Baird 5/12/08.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.7 Commissioning Geoff Vaughan University of Central.
Staff Induction-Environmental Awareness
MODULE “STRATEGY DEVELOPMENT”
Setting the Stage: Review of 2013 IEPR Nuclear Recommendations Danielle Osborn Mills Former Senior Nuclear Policy Advisor to the California Energy Commission.
UK Cleanup Market Overview A Strategic approach to Cleanup & Hazard Reduction Nov 2010 Marcus Mackay mercury stone.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/2 Design Geoff Vaughan University of Central Lancashire,
Hazardous Waste and Emergency Response
Recycling Nuclear Waste: Potentials and Global Perspectives Mikael Nilsson Department of Chemical Engineering and Materials Science University of California,
Technical Meeting on Evaluation Methodology for Nuclear Power Infrastructure Development December, 2008 Nuclear Safety in Infrastructure Building.
Standard WBS Version 1.0 WBS2-3.pptPage 1 Standard Work Breakdown Structure Legend = Decomposes to lower level WBS elements 4.0 Implementation 4.0 Implementation.
Authorization and Inspection of Cyclotron Facilities Authorization for the Decommissioning of the Facility.
Chapter 4 Nuclear Energy. Objectives Describe how nuclear fuel is produced. List the environmental concerns associated with nuclear power. Analyze the.
IAEA International Atomic Energy Agency Reviewing Management System and the Interface with Nuclear Security (IRRS Modules 4 and 12) BASIC IRRS TRAINING.
Group New Projects Related to Decommissioning. 29 th May 2008 KNPP Richard Benbow – Head of Kozloduy PMU.
VERMONT YANKEE Transitioning into SAFSTOR ​SEPTEMBER 2, 2015 Paul Paradis Director Decommissioning.
August 4,  Vermont Yankee Nuclear Power Station (VYNPS) ceased power operations on December 29, 2014 after 633 days of continuous power operation.
MODULE “PROJECT MANAGEMENT AND CONTROL” ORGANIZATION AND ADMINISTRATIVE CONTROL SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP ,
MODULE “COST ESTIMATION, CALCULATION AND COST CONTROL” SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP , Programme “Leonardo da.
Nuclear Fuel Cycle.  According to World Nuclear Association:  The nuclear fuel cycle is the series of industrial processes which involve the production.
MODULE “PROJECT MANAGEMENT AND CONTROL” SAFETY ASSESSMENT DURING DECOMMISSIONING SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP ,
Former DuPont Barksdale Works Project Update December 14, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center.
Nuclear Decommissioning in the UK Presented by Chris Jones.
Main Requirements on Different Stages of the Licensing Process for New Nuclear Facilities Module 4.5/1 Design Geoff Vaughan University of Central Lancashire,
1 Addressing Deferred Maintenance, Infrastructure Costs, and Excess Facilities at Portsmouth and Paducah William E. Murphie Manager Portsmouth/Paducah.
MODULE “PREPARING AND MANAGEMENT OF DOCUMENTATION” SAFE DECOMMISSIONING OF NUCLEAR POWER PLANTS Project BG/04/B/F/PP , Programme “Leonardo da Vinci”
1 ESTABLISHMENT OF REQUIREMENTS Module “DECOMMISSIONING PROCESS” Project BG/04/B/F/PP , Program “Leonardo da Vinci”
International Atomic Energy Agency Roles and responsibilities for development of disposal facilities Phil Metcalf Workshop on Strategy and Methodologies.
IAEA International Atomic Energy Agency IAEA Safety Standards for Research Reactors W. Kennedy Research Reactor Safety Section Division of Nuclear Installation.
Regional Meeting on Applications of the Code of Conduct on Safety of Research Reactors Lisbon, Portugal, 2-6 November 2015 Diakov Oleksii, Institute for.
-1- UNRESTRICTED / ILLIMITÉ Demonstrating the Safety of Long-Term Waste Management Facilities Dave Garrick 2015 September.
November 4,  Vermont Yankee Nuclear Power Station (VYNPS) ceased power operations on December 29, 2014 after 633 days of continuous power operation.
Think safe. Act safe. Be safe. LEHR Site Annual Soil Management Plan Training Sue Fields, Environmental Health & Safety Sept,
 Before a company decides to close it’s power reactors the facility must be put in to a state that no longer has a residual radioactive level, clean.
The Curious Absence of New Nuclear Michael Hoeger Presented 02/06/2012.
GCSE Science A Physics 1 Generation of Electricity Learning Outcomes Be aware of the significance of commissioning, running and decommissioning costs for.
DECOMMISSIONING OF NUCLEAR POWER PLANTS IN THE CZECH REPUBLIC Peter Lietava Division of Radioactive Waste and Spent Fuel Management State Office for Nuclear.
International Atomic Energy Agency V. Nys Definition and practical application of demonstration of operational and long-term safety for predisposal RWM.
CDM Construction Design and Management
Nuclear power plant Performed by Zhuk A.D.. Purpose of this presentation is to show importance and danger of nuclear power plant. My opinion: I think.
P4 Part 2 Carl James.
Spent Fuel Management and Nuclear Materials (SFM&NM) July 2016 Update
PhD Bursary Scheme Rick Short, Research Manager 1
Preliminary Decommissioning Plan for the Canadian Light Source
Occupational Radiation Protection during High Exposure Operations
János Krutzler Hungarian Atomic Energy Authority
EPA Options for the Federal Regulation of Coal Combustion Waste Lisa Evans Earthjustice October 22, 2010.
Vermont Yankee Decommissioning Update
Janet R. Schlueter Senior Director, Radiation and Materials Safety
Research Reactor Decommissioning Demonstration Project (R2D2)
Management of Radioactive Waste
Construction (Design and Management) Regulations (CDM) 2015
CR3 and Crystal River Energy Complex
Possible Transition from Operating to Decommissioning
J. Seeman Assistant Director for PPA/LCLS
Northeast High-Level Radioactive Waste Transportation Task Force
Santa Teresa Landfill and Remediation Project
Presentation transcript:

Calder Hall Sellafield Decommissioning Martin Adam Heriot-Watt Edinburgh 2008

History Located in Cumbria, England Worlds First Commercial Nuclear Power Station Construction started 1953, completed 1956 Her Majesty the Queen Opened the Power Station on 17 October 1956 Generated Power Until March 2003 Consisted of 4 Magnox reactors each capable of 50 Mwe of power each. Produced over 70TWh of electricity in its operational life.

History Its early life primary function was to produce weapons grade plutonium From 1964 it was mainly used for commercial fuels Although it was not until 1995 when the UK government announced that all production of plutonium for weapons had ceased

Calder Hall Site Mission: Safely, securely and cost-effectively remove all fuel and buildings from site To processes, treat and dispose of all waste arise To remediate the ground, where necessary and make the land available for reuse.

Current plan Stage 1: Defuelling & Preparations 2003 – 2008 Stage 2: Intermin Decommissioning 2004 – 2011 Stage 3: Care & Maintenance 2011 – 2105 Stage 4: Final Site Clearance

Defuelling & Preparations: Remove all spent fuel and transfer it to Sellafeild Fuel Handling Plant Arrangements must be taken to improve nuclear safety before defuelling can commence Removal of all fuel elements from the reactor core Despatch of all spent fuel from the station Calder Hall has four reactors, with each reactor holding 1696 fuel channels holding either five or six fuel elements Therefore the site had approx 40,000 elements to remove This phase also deals with maintenance issues dealing with both the defuelling process and the ongoing site management.

Intermin Decommissioning: Will begin in parallel with the defuelling process. Reactor 1 and Turbine Hall A, are currently under a request to become listed buildings. Conservation of remaining 3 reactors into safehouses to be used during the care & maintenance phase Hazard reduction activities; Asbestos removal from heat exchangers and from within the turbine halls Removal of redundant facilities (cooling systems, utilities, generators ext.) Cooling towers were demolished on 29 th of September 2007 All Plant not required for industrial Heritage purpose or C&M removed. Reactors 2, 3 & 4 heat exchangers dismantled and removed.

Intermin Decommissioning: Intermediate waste arising will be transported to the low level waste repository in sellafield New construction activities are required Three reactors will require weather proofing and conversion. This will involve re-cladding the roofs which will also have to been replaced/refurbished every 30 years during the care and maintenance phase Modification to existing facilities to maintain services such as water, telecommunication, fire detection and security system A new electrical ring main will be installed, to allow safe termination of existing services Before C&M can start all hazards must be immobilised in a safe and secure way

Care & Maintenance: This stage is designed to ensure that minimal human intervention is needed during the 100-year Care and Maintenance Program Initial phase will last 5 years where the site will remain staffed After this phase, surveillance, safety and security will be of great importance Safehouses will be routinely maintained, inspected regularly and will undergo periodic surveys. The Scope will also include inspections following severe weather conditions to check for any failure of the watertight envelope. Weekly external inspections (e.g. identification of any damage) Monthly ground maintenance on the site Half-yearly external engineering inspections for minor maintenance issues Annual internal engineering inspections for minor maintenance issues External/Internal inspections at 25 year intervals for major maintenance issues

Final Site Clearance: To facilitate this stage a suitable site infrastructure will be installed A waste management facility (WMF) will be constructed to process the waste arising during this phase Wastes will be transferred in a controlled manned to the WMF, monitored and sentenced  Active waste will be packed in a waste disposal boxes, transported off site and disposed off  Clean waste will be used of infilling voids or disposed of off site Reactor 1 and Turbine Hall A are assumed to no longer be listed buildings, therefore will be removed

Final Site Clearance: Entry to safehouse will be gained during early phases of clearance to carry out preliminary structural and radiological surveys In turn a section of each safehouse roof will be removed to allow large items of the plant to be lifted out Once all active plant and any contamination have been removed from the safehouses they will be demolished and any voids below GWL backfilled Near the end of the phase all services, structures installed to support the project will be deplanted, demolished and removed.

Cost: Total overall estimated cost around 1 Billion GBP Cost Distribution by Key Phase (£k)

Thank You For Your Attention