June 19, 2003James T Volk F0 Lambertson Liner review J Volk WBS for Liner –Liner fabrication –Liner installation Liner installation tests at MI-60 Vacuum tests at MI-60
June 19, 2003James T Volk F0 Lambertson Liner Fabrication Jul 8 Expect first liner Jul 21Approve making next 6 Aug 13 all liners ready
June 19, 2003James T Volk F0 Lambertson Liner installation Sep 2 magnet mover To MI-60 Aug 29 2 liners installed Sep 14 Pump out begins Sep 3 all liners installed
June 19, 2003James T Volk Lambertson at MI-60 Field Free region Field Region Ledge
June 19, 2003James T Volk Liner Installation ES&H issues with Copper Beryllium –Be training for techs –No sanding, cutting, grinding, machining, ect. –Clean up afterward Support of liner during installation Push, Pull, or vacuum through the liner? Ledge at entrance Use of Stainless Steel strips to guide liner Any special tools we may need
June 19, 2003James T Volk Vacuum Tests Current vacuum at F0 on the order of Need to bake out Lambertson with liner to assure that vacuum is good with the liner If vacuum worse than we can’t install liners at F0 We are working with Bruce Hanna to get equipment at MI-60 to do full vacuum test Also measure impedance after vacuum bake out
June 19, 2003James T Volk Conclusions We have schedule for preparation and installation that fits with time constraints We will test installation and vacuum before we commit to installation There is slack time to make up for delay caused by any problems