Community Development Department Royal Palms Parkway City Council Workshop July 29, 2014
Community Development Department Scope of Work Project Length: 2.2 Miles Roadway resurfacing with new four foot paved shoulders New Eastbound Left Turn Lane at Royal Palms Pkwy and Rickenbacker Drive – Improves safety and intersection capacity New Eastbound Right Turn Lane at Royal Palms Pkwy and Belle Terre Pkwy – Improves safety and intersection capacity Safety improvements for path to Lehigh Trail at the intersection of Royal Palms Pkwy and Rymfire Drive –Three Rectangular Rapid Flashing Beacons (RRFB) –Median Refuge
Community Development Department Pedestrian Improvements Royal Palms Pkwy & Rymfire Drive
Community Development Department Map Area Project Start Project End US 1 Royal Palms Pkwy Belle Terre Pkwy
Community Development Department Original Estimated Construction Budget – $900k Proposed FY 2015 Budget - $1.33 Million Actual Cost –Construction Bid – $1.18 million –Contingency, CEI & Misc Expenses – $150k –Total – $1.33 million Project Budget