Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013.

Slides:



Advertisements
Similar presentations
Accelerator Complex Status P. Collier. Linac2, Booster and PS Startup on-time, according to the schedule. Only minor problems Rapidly set-up the major.
Advertisements

LS1 Status Report – 116 th LHCC Frédérick Bordry 4 th December 2013.
February 2009 Summary of Chamonix 09 Steve Myers.
CURRENT STATUS OF CV INSTALLATIONS, WORKS DURING LS1 AND PROBLEMS ENCOUNTERED DURING START-UP NORTH AREA Bill Bannister / Jani Lehtinen EATM – 7 th October.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
CRYOGENICS AND POWERING
CV activities on LHC complex during the long shutdown Serge Deleval Thanks to M. Nonis, Y. Body, G. Peon, S. Moccia, M. Obrecht Chamonix 2011.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
LS1 : EL Upgrades & Consolidation Chamonix– February 8 th 2012 F. Duval on behalf of EN/EL The goal of LS1 is to implement everything needed for a safe.
R2E Report M. Brugger for the R2E Study Group RadWG Meeting, August 20 th 2009.
R2E Status Report 18 th LSC Meeting, August 18 th 2013 CERN Radiation 2 Electronics (R2E) Project 18 th LSC Meeting August 16 th 2013 R2E Status Report.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
LHC Insertions Upgrade Working Group (LIUWG) Space available in tunnel Y. Muttoni.
Partikeldagarna, Göteborg 21 September 2007 LHC: Status and Plans Lyn Evans.
Cooling and Ventilation Activities M. Battistin – EN/CV/PJ IEFC Workshop th March 2012 « CONSOLIDATION and UPGRADE PLANS for the INJECTOR COMPLEX.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
EN-CV interventions during YETS
Status of LS1 collimator maintenance O. Aberle – 03/03/14 With input from P. Bestmann, S. De Man and J. Lendaro.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
R2E relocation & shielding activities Anne Laure Perrot EN/MEF- LE R2E project meeting, 23 rd October 2012.
LS1preparation & planning status A L Perrot on the behalf of EN/MEF R2E project meeting 11 th May 2012 EN.
Overview of the main events related to TS equipment during 2007 Definition Number and category of the events Events and measures taken for each machine.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
R2E Availability October 15 th 2014 Experience from Past LHC and Injector Operation and scaling to the future G. Spiezia.
Eric Prebys/LARP 2/17/2016.  CERN has taken unprecedented steps to control information about this event, including altering the electronic LHC log to.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
4 December 2007Sylvain Weisz - LEMIC1 Status of LHC installation.
Planning of Injector Activities for Linac4-to-PSB Connection and LS2 Thanks to all the valuable input from the LIU project leaders and LIU work- package.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
Beam Instrumentation during LS1 Ray Veness on behalf of the BE/BI group.
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Quality Assurance Overview Ranko Ostojic 12 Nov 2012.
Injectors & LHC report K. Foraz on behalf of OSS members 01/08/2013LSC - K. Foraz1.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
TE-CRG Activities D. Delikaris, TE-CRG.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
LHCf collaboration meeting, Nagoya, January 2009A. L. Perrot LHC news A. L. Perrot CERN, EN/MEF-LE LHCf collaboration meeting, Catania, 6 th July 2009.
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
EDMS N° V.1 TE-EPC Activities during LS1 V. Montabonnet [TE-EPC]
Overall planning, consolidation, stops, time line K. Foraz MAC – April 27th 2010 April 27th 20101K. Foraz - Machine Advisory Committee.
R2E/Availability Workshop Report - RadWG October 22 nd 2014 R2E/Availability Workshop 2014 October th 2014 R2E/Availability Workshop RadWG - Brief.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
K. Foraz on behalf of OSS members
CONS and HL-LHC day Analysis of needs from TE-EPC
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
TE-MSC activities in SPS during LS2
SMACC Tenth report [15 min] 13/09/2013
Status of LHC installation & New Installation Schedule
K. Foraz on behalf of OSS members
The LHC - Status Is COLD Is almost fully commissioned
M. Alcaide Leon, Paolo Fessia
Long Shutdown for the LHC: Vacuum Beam Pipes
M. Alcaide Leon, Paolo Fessia
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS EN-CV Planning LS (initial draft)
K. Foraz on behalf of OSS members
PS Booster Report from: David HAY, Cyrille BEDEL 12-Jan-2018
Experimental Areas – LS2 planning
Review of hardware commissioning
Presentation transcript:

Long shutdown 1 LHC Machine Status Report K. Foraz June 12 th, 2013

IIntroduction LLHC –P–Preliminary phase –S–SMACC project –R–R2E project –M–Maintenance and consolidation of Infrastructure IInjectors CConclusion 12/06/2014K. Foraz - 114th LHCC2

LS1 - Accelerator complex FMAMJJASONDJFJFMAMJJASOND MA beam to beam available for works Physics Beam commissioning Shutdown Powering tests 12/06/2014K. Foraz - 114th LHCC3

LS1 LHC – Scope of work  Take all measures for a safe and reliable operation of 7TeV/beam  Consolidate superconducting magnets and circuits  SMACC  Relocate radiation sensitive electronics  R2E  Perform full maintenance of all equipment's  …. Powering tests Warm-upMaintenance & consolidation Cool-down Powering tests 12/06/2014K. Foraz - 114th LHCC4

S 12 P1P1 S 23 P2P2 S 34 P3P3 S 45 P4P4 S 56 P5P5 S 67 P6P6 S 78 P7P7 S 81 P8P8 F eb. M ar. A pr. M ay J un. J ul. A ug. S ep. O ct. N ov. D ec. J an. F eb. M ar. A pr. M ay J un J ul. A ug. S ep. O ct. N ov. D ec. J an. F eb. M ar. A pr. M ay J un LHC LS1 schedule (v3.0) Powering TestsSplices Warm-up & preliminary testsPreparation for cool-down Cool-down R2E Splices Warm-up & preliminary tests PT Warm-up & preliminary tests CSCM PT Warm-up & preliminary tests PT Warm-up & preliminary tests PT Warm-up & preliminary tests PT Warm-up & preliminary tests PT Warm-up & preliminary tests Splices Machine check-out and beam commissioning Physics R2E 12/06/2014K. Foraz - 114th LHCC5

 Introduction  LHC – Preliminary phase – SMACC project – R2E project – Maintenance and consolidation of Infrastructure  Injectors  Conclusion 12/06/2014K. Foraz - 114th LHCC6

LHC Preliminary tests  Powering tests – 40 circuits were tested: (almost) all circuits were powered up to 7 TeV equivalent current – 773 successful tests were executed in 10 days – All circuits reached the nominal 7 TeV equivalent current, but RD3.L4, commissioning stopped at 6.9 TeV (long training), but can be possibly pushed further RQ5.R2 – I_Nom reduced to 4100 A from 4310 A (OK for 7 TeV) RCBYHS5.R8 – Tested successfully to 20 A, but cannot be powered up to the nominal 72 A (a similar failure was observed on the same corrector in 8L and that was replaced with a normal conducting magnet) RQTL11.R5B1 – I_Nom reduced to 450 A from 550 A RQTL11.L6B1 – I_Nom reduced to 350 A from 400 A RCSSX3.L1 – I_Nom reduced to 60 A from 72 A RQTL9.R3B2 – I_Nom reduced to 425 A from 450 A 12/06/2014K. Foraz - 114th LHCC7

LHC Preliminary tests  Electrical Quality Assurance (ELQA) – ELQA at 1.9K and at room temperature were performed in all sectors and are just finished – 37 NCs revealed. Most of them will be solved at warm, during SMACC. No showstopper!  Warm-up is finished 12/06/2014K. Foraz - 114th LHCC8

LHC Preliminary leak tests Leak tests  Arc subsectors all tested: 20 internal helium leaks identified  14 identified to component (for repair).  For 6 leaks not identified to component, further tests to be performed in phase 2.  QRL  2 existing internal leak known  5 new internal leaks – under investigation  After warm-up and before consolidation RF ball tests are performed in each sector  6/8 sectors tested  2 PIMs collapsed 12/06/2014K. Foraz - 114th LHCC9

 Introduction  LHC – Preliminary phase – SMACC project – R2E project – Maintenance and consolidation of Infrastructure  Injectors  Conclusion 12/06/2014K. Foraz - 114th LHCC10

SMACC project

SMACC progress  W opening – Completed in sector 56 – In progress in sector 67  Interconnection train – Sector 56 – Sector 67 Diode container 1 st shunt resolder 26/04/13 M line opening 12/06/2014K. Foraz - 114th LHCC12

SMACC progress  DFBA consolidation in sectors 56, 67, 81  DN200 in progress in sector 78 (not started in sector 81)  Magnets replacement in sector 78 1 st sleeves cut in DFBAK HCM DN200 Magnet exchange 12/06/2014K. Foraz - 114th LHCC13

 Introduction  LHC – Preliminary phase – SMACC project – R2E project – Maintenance and consolidation of Infrastructure  Injectors  Conclusion 12/06/2014K. Foraz - 114th LHCC14

R2E project - Goal  – Analyze and mitigate all safety relevant cases and limit global impact  – Focus on long downtimes and shielding  LS1 (2013/2014) – Final relocation and shielding  LS1-LS2 ( ) – Tunnel equipment and power converters ~250 hours Downtime ~400 hours Downtime Aiming for <0.5 dumps / fb-1 ~12 dumps / fb -1 ~3 dumps / fb -1 12/06/2014K. Foraz - 114th LHCC15

R2Eproject during LS1 UJ76 TZ76 UJ14/16 UL14/16 RR13/17 UJ/UP56 UL557/8 RR53/57 US85 UL84/86 UA83/87 UX45 US45 UL44/46 12/06/2014K. Foraz - 114th LHCC16

R2E project progress  Point 1 – Power converter dismantling in progress – Electrical infrastrucuture in progress  Point 5 – Power converters disconnected – Preparation and protection before drilling in progress – Piping installation almost finished  Point 7 – Power converters disconnection and cable removal in progress – TZ76 – demolition wall in progress UJ56 TZ76 Wall-E in action P1 -shielding dismantling 12/06/2014K. Foraz - 114th LHCC17

 Introduction  LHC – Preliminary phase – SMACC project – R2E project – Maintenance and consolidation of Infrastructure  Injectors  Conclusion 12/06/2014K. Foraz - 114th LHCC18

Infrastructure  Maintenance and consolidation of 400kV and 60kV June 3 rd – August 3 rd Power limited to 50 MW Nominal configurationPower from SIGPower from 400kV EHT3 12/06/2014K. Foraz - 114th LHCC19

Infrastructure  Full maintenance of all the equipment in progress  Several consolidation and upgrade in progress according to schedule – Demineralised water production – Additional cooling towers – UPS replacement – Replacement of the ducts of water cooled cables –…–… – And of course cabling ! Flexwell removal Electrical P8 Water Cooled cables removal New cooling P6 12/06/2014K. Foraz - 114th LHCC20

 Introduction  LHC – Preliminary phase – SMACC project – R2E project – Maintenance and consolidation of Infrastructure  Injectors  Conclusion 12/06/2014K. Foraz - 114th LHCC21

Injectors  Main activities – Preliminary powering tests complete – Full maintenance of all the equipment – PS Booster & PS Installation of the new access systems Cooling and ventilation renovation Upgrade of the RF systems Improve the radiation shielding over the PS and Septum 16 – SPS Consolidation of 18kV transformers Replacement of irradiated cables in BA1 and in TCC2 Installing new Fibres systems in BA5, BA6 and BA1 New coated magnets in BA5 Major consolidation of the valves – CV Vertical realignment in BA6  Progress status – overall progress is good SPS irradiated cables Magnet exchange in SPS SPS – LSS1+ - test with robot Goward road 12/06/2014K. Foraz - 114th LHCC22

 Introduction  LHC – Preliminary phase – SMACC project – R2E project – Maintenance and consolidation of Infrastructure  Injectors  Conclusion 12/06/2014K. Foraz - 114th LHCC23

Dashboards  General and detailed progress 12/06/2014K. Foraz - 114th LHCC24

General progress So far, so good throughout accelerator complex LHC – Preparatory phase almost complete Machine is warm Electrical preliminary tests complete – SMACC IC train in 2 sectors – good progress 1 st magnets exchanged – R2E Good progress Preparatory works almost finished – Infrastructure activities on schedule 12/06/2014K. Foraz - 114th LHCC25