BLIP Operations – 162 days of operation o Safety o Forklift needs a new tire o Production o Sr-82 targets out of beam as of 14 Jun o New Sr-82 targets in 16 Jun o Next Sr-82 production starts 1 Jun o New Be-7 chemistry testing last week and this week Anna Goldberg 16 Jun 2015
BLIP Operations – 162 days of operation o BLIP Maintenance o Last one on 10 Jun (~7 hr) o Next scheduled for 24 Jun o Research o Ac-225 out of beam 14 Jun (10 day irradiation) o Two Pt targets for 1 hr each (15 & 16 Jun) o As target safety submission this week Anna Goldberg 16 Jun 2015