Nodal Program Update Mike Cleary Sr. VP and Chief Technology Officer.

Slides:



Advertisements
Similar presentations
June 26, 2008 TAC Texas Nodal Market Implementation: Program Update Jerry Sullivan.
Advertisements

1 April 2010 TX SET Timeline Project Conceptualization 11 weeks Market Requirements 12 weeks ERCOT Requirements 12 weeks Conceptual Design 6 weeks Detail.
1 Project Update and Summary of Project Priority List (PPL) Activity RMS August 4, 2015.
January 8, 2009 TAC Texas Nodal Program Implementation: P rogram Update Ron Hinsley.
November 1, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan, Executive Director.
© Property of ERCOT /8/20061 TPTF ERCOT 30/60/90 day Plan Raj Chudgar, Nodal Program Manager February 20, 2006.
1 Texas Nodal Texas Nodal Program Implementation TPTF June 6, 2006 Agenda.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
ERCOT and Utilicast Public Document ERCOT Board of Directors Meeting April 22, 2009 Nodal Program Oversight Report 10 – Infrastructure.
April 9, 2009 Technical Advisory Committee Meeting Texas Nodal Program Implementation: Program Update Mike Cleary Sr. VP and Chief Technology Officer.
1 Single Entry Model (SEM) Go-Live Update ROS Update July 16, 2009.
July 9, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
Market Implementation Board Presentation July – v1.1F 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program.
March 20, 2008 TPTF CIM Update Raj Chudgar Program Director for Market Redesign.
Nodal COMS Update Commercial Operations Subcommittee January 13, 2009 Clay Katskee ERCOT - Market Operations Division Projects Organization.
Texas Nodal Timeline Options, TPTF Jul 11, Timeline Options Trip Doggett TPTF
September 8, 2008 TPTF Nodal Core Projects Updates Nodal Project Managers.
TPTF Meeting Texas Nodal Program Update Market Readiness Metrics Update Chris Wilkinson PMO.
Presentation to House Regulated Industries Committee Chairman Phil King Trip Doggett Chief Operating Officer The Electric Reliability Council of Texas.
TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.
Lead from the front Texas Nodal 1 Texas Nodal Critical Path Update TPTF Date xxx.
March 11, 2008 Texas Nodal Market Redesign Program Commercial Operations Subcommittee.
February 5, 2009 Technical Advisory Committee Meeting Texas Nodal Program Implementation: Program Update Trip Doggett.
April 1, 2008 TPTF Quality Center Update Eileen Hall.
ROS Meeting – 05/15/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 05/15/08.
January 15, 2008 Monthly Board of Directors Meeting Texas Nodal Market Implementation Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Texas Nodal Congestion Revenue Rights (CRR) EDS 3 Release 7 - Overview EDS 3 Phase 2 MP Planning.
Retail Business Processes PR 50121_07 Project Update Retail Market Subcommittee September 13, 2006 Adam Martinez Mgr, Market Operations DPO.
Credit Monitoring and Management Status TPTF December 17, 2007.
July 7, 2008 TPTF Texas Nodal Market Implementation: - Program Update - Market Readiness Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF - November 6 th, 2006.
September 25, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
August 25, 2008 TPTF Nodal Status Report: Projects Status Updates Adam Martinez.
EDS 2 Early Delivery Systems Release 3 – Workshop August 16, 2007.
Outage Scheduler Transition Plan Kenneth Ragsdale NATF.
1 Single Entry Model (SEM) Go-Live Update Special TAC Meeting (Updated) August 18, 2009.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board Of Directors – August 15, 2006 TPTF Meeting August.
2009 Project Prioritization Troy Anderson ERCOT Program Management Office February 20, 2008.
August 25, 2008 TPTF Nodal Status Report: Quality Center Update Eileen Hall.
August 25, 2008 TPTF Nodal Status Report: Integrated Schedule Update Change Control Update Adam Martinez Troy Anderson.
Texas Nodal Program ERCOT Readiness Update TPTF June 23, 2008.
Integrated Release Approach and Update TPTF 11/10/2008 Matt Mereness.
TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
17 February 2009 ERCOT Board of Directors Texas Nodal Market Implementation: Program Update Trip Doggett Sr. Vice President and Chief Operating Officer.
Objectives: Upgrade Siebel to a supported application Upgrade Oracle database to current version Deliver all existing user functionality with no degradation.
1 Market Trials Update NATF May 4, 2010.
October 8, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan Program Director, Market Redesign.
November 29, 2007 TAC Meeting Texas Nodal Program Update Jerry Sullivan, Executive Director.
September 22, 2008 TPTF Nodal Status Report: Project Status Updates Nodal Project Managers.
PMO Update to PRS Troy Anderson ERCOT Program Management Office June 17, 2010.
August 11, 2008 Texas Nodal - Integrated Schedule Update Integrated Schedule Update for TPTF Janet Ply.
August 27, 2007 Executive Committee Meeting Texas Nodal Program Update Jerry Sullivan.
Lead from the front Texas Nodal 1 Reduction of MMS Vendor Effort for TPTF January 8, 2008 Murray Nixon Sai Moorty.
1 Texas Nodal Texas Nodal Program Implementation TAC July 6, 2006 Agenda.
Retail Workshop ERCOT Nodal Update October 06, 2010.
Network Operations Model Go-Live Decision Kenneth Ragsdale TAC July 1, 2010.
October 2, 2008 TAC Texas Nodal Market Implementation: Program Update Ron Hinsley.
January 3, 2008 TAC Meeting Texas Nodal Program Update Jerry Sullivan.
June 5, 2008 TAC Texas Nodal Market Implementation Program Update Jerry Sullivan.
October 27, 2008 TPTF Nodal Status Report: Program Update Ron Hinsley.
Lead from the front Texas Nodal 1 Texas Nodal EDS4 - Approach 11/28/2007.
1 Single Entry Model (SEM) Go-Live Update TAC Update August 6, 2009.
October 13, 2008 TPTF Nodal Status Report: Program Update Ron Hinsley.
August 11, 2008 TPTF Early Delivery Systems Status Daryl Cote.
The Texas Nodal Market Trip Doggett ERCOT Interim President and Chief Executive Officer Mike Cleary ERCOT Chief Technology Officer Executive Briefing 28.
August 11, 2008 TPTF EDS Sequence and Durations Discussion Daryl Cote.
1 1 Texas Nodal Program UpdateMarch 21, 2008 Nodal SAS70 Audit – Readiness Approach & Timeline March ‘08June ‘08 Sept ‘08 Dec ‘08 Jan ‘09 Define Readiness.
Texas Nodal Program Current Schedule and Recent Changes
2011 Prioritization Update to Market Subcommittees
Presentation transcript:

Nodal Program Update Mike Cleary Sr. VP and Chief Technology Officer

2 Technical Advisory Committee9 July 2009 Agenda Current Timeline Recent Achievements Systems Update Integrated Testing Update Program Control & Review Risks & Issues

3 Nodal Timeline 9 July 2009Technical Advisory Committee

4 9 July 2009 CMM/NMMS Milestone Slips CMM –Excessive defects found in custom components delivered in July –CMM 4.1 custom components required for end-to-end testing will be delivered on-time –Key functionality: Credit monitoring (8 custom components) –ERCOT will complete CMM 4.2 custom components in house and deliver by February 2010 –Key functionality: Internal reports, report management –CMM 4.3’s components rolled into 4.1 and 4.2 NMMS 7 –One week delay exiting FAT due to testing-resource constraints (due June 23, delivered June 30)

5 Significant Accomplishments 9 July 2009Technical Advisory Committee All Vendor Software Deliveries Complete –MMS 5 delivered to iTest July 7 (3 days ahead of schedule) –EMS 6 delivered to iTest July 1 –NMMS 7 exited FAT June 30 SEM Go-Live on Track for August 31 Vendor Contract Re-Negotiations –5 targeted vendor contracts re-negotiated –Results: –Lower rates –More ERCOT control and oversight –Cleaned up unfavorable language in contractual documents

6 Market Systems Update Technical Advisory Committee9 July 2009 ProjectSub- Project StatusOpen Critical Defects June 12/July 2 MMS On schedule MMS 5 final release; currently in FAT and scheduled to exit Aug. 21 MMS 5 Patch 1 preliminary drop to iTest July 7 (scheduled July 10) 14 interfaces to test by Sept. 1; test planning underway Market Manager UI to exit FAT July 16 MMS5 Sev 1s Sev 2s Sev 3s  CRR On schedule CRR 1.9 final release; currently in FAT and scheduled to exit Aug of 9 interfaces in iTest, 2 in FAT, 4 in execution phase CRR 1.9 Sev 1s Sev 2s Sev 3s  COMSCMM Behind schedule CMM 4.1 in FAT; on schedule to exit July 31 Two CMM 4.2 components scheduled to exit FAT by July 31; remaining components combined with CMM 4.3 and to exit FAT February 2010 (internal functions only) 4 of 5 interfaces currently in iTest Outstanding release: CMM 4.2 CMM 4.1 Sev 1s Sev 2s Sev 3s  S&B FAT testing complete; 7 of 8 interfaces currently in iTest Targeting refactoring completion by September 2009 Sev 1s Sev 2s Sev 3s  CSI FAT testing complete Targeting refactoring completion by August 2009 Sev 1s Sev 2s Sev 3s  REG Nearing completion All 3 interfaces currently in iTest; 96% of testing complete Sev 1s Sev 2s Sev 3s 

7 Reliability Systems Update Technical Advisory Committee9 July 2009 ProjectStatusOpen Critical Defects June 12/July 2 NMMS On schedule NMMS 7 final release; exited FAT June 30 All 3 interfaces have exited FAT and are currently in iTest NMMS 7 Sev 1s Sev 2s Sev 3s  EMS On schedule EMS 6 Patch 3 deployed to iTest July 1 All 13 interfaces’ test plans now complete SPR Patch 3 completed FAT June 30 SPR Patch 3 Sev 1s Sev 2s Sev 3s  OS On schedule Common test plan for 12 of 13 interfaces complete 2 defect patches planned for OS UI OS Sev 1s Sev 2s Sev 3s *  * excluding ROO defects

8 Market Verification Update Technical Advisory Committee9 July 2009 ProjectStatusOpen Critical Defects June 12/July 2 Interface/Adapter Testing Data management strategy undergoing review and approval System-to-system testing of connectors in progress using Common Data Set MMS 5 available for I/A testing Level 1/Level 2 testing running behind, but working on efficiency gains in automation areas, early Level 3 testing and other adjustments FAT Defects Sev 1s Sev 2s Sev 3s  iTest Defects Sev 1s Sev 2s Sev 3s  End-to-End Testing Early E2E testing started with CRR auction settlement Additional E2E testing planned in July (7 functional strings in total) Full E2E to start in late September Market Trials Detailed plan to be rolled out at August TAC meeting SEM Go-Live training for TSPs began June 23 Market Trials submission testing begins in October 2009 Market Readiness In detailed planning phase ERCOT Readiness In detailed planning phase Operational Readiness Schedule is being finalized NMMS performance testing under way System cutover validation and implementation under way

9 Integrated Testing Update Technical Advisory Committee9 July 2009 Connectors to be Tested: 82 DefinitionIn ProgressCompleted Level 1Connector installed; one record transferred through connector (“smoke test”) 268 Level 2Connector tested using a common data set with multiple records 119 Level 3System-to-system functional test; connector tested with system-generated data 70 Target Completion: Sept. 22, 2009 (Levels 1-2) Nov. 13, 2009 (Level 3) Status: On Schedule

10 Program Review & Control Traceability –Protocols Requirements Prioritization of the effort into tiers Tier 1 (Significant/high volume of changes): 3, 4, 5, 6, 7, 8, 9, 16, 17 Tier 2 (Moderate): 10, 11, 12, 13, 20, 22 Tier 3 (Low impact): 1, 2, 14, 15, 18, 19, 21, 23, 24 Identify alignment issues First-level analysis: Bob Spangler, Floyd Trefny Meet with business owners for validation Provide information to ERCOT Readiness Team for reporting –7: ERCOT to review late July –3, 4, 5, 6: ERCOT to review Sept./Oct. –8, 9, 16, 17: ERCOT to review Oct./Nov. Technical Advisory Committee9 July 2009

11 Technical Advisory Committee9 July 2009 Risks & Issues to Achieving Nodal’s Major Milestones Complete Integrated Systems ( ) –Issue: Resource constraints for program –Issue: Handling CMM delays for program Market Trials ( ) –Risk: Reconciling protocols, systems and market expectations Nodal Go-Live ( ) –Risk: Data Center capacity concerns –Risk: Integrity of network model data from market participants

12 Questions ?