What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003.

Slides:



Advertisements
Similar presentations
Main Injector Gap clearing kickers Phil Adamson (#) AEM 14th March 2011.
Advertisements

Proton Beam Measurements in the Recycler Duncan Scott On Behalf of the Main Injector Group.
Chris Smith Booster RF Cavity Upgrade Contents: The Booster Existing RF Cavities Why Upgrade? New Cavities Prototype Plans University Involvement Prototype.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Near Term* Plans for the Fermilab Proton Source Eric Prebys FNAL Accelerator Division *Near term = “prior to proton driver”
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Proton Plans at Fermilab Robert Zwaska - Fermilab Science and Engineering at Henderson- DUSEL Capstone Workshop Stony Brook University May 5, 2006 Outline.
Commissioning of the Fermilab Accelerators for NuMI Operation Robert Zwaska University of Texas at Austin NBI 2003 November 7, 2003.
F MI High Power Operation and Future Plans Ioanis Kourbanis (presented by Bruce Brown) HB2008 August 25, 2008.
Getting Beam to NuMI (It’s a worry!) Peter Kasper.
Run II DOE Review - Booster Eric Prebys Booster Group Leader FNAL Beams Division.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
AAC February 4-6, 2003 Protons on Target Ioanis Kourbanis MI/Beams.
Proton Planning Eric Prebys FNAL Accelerator Division.
Experimenter Contributions to Booster Improvements Eric Prebys FNAL Accelerator Division.
Dog( leg )s of War Eric Prebys Run II Meeting March 13, 2003.
Proton Study Meeting 4/19/05 Eric Prebys 1 Proton Plan Stage I Eric Prebys.
Proton Source: Linac and Booster Elliott McCrory AAC Review February 4, 2003.
Booster Operation in Support of the Collider Program
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Diagnostics in the Fermilab Proton Source (Linac + Booster) Eric Prebys FNAL Beams Division.
The “Run II Era” The proton source is very close the the specifications in the Run II Handbook. Although it’s the highest priority, support of collider.
Booster Issues for NuMI Eric Prebys FNAL Beams Division.
Overview of Booster PIP II upgrades and plans C.Y. Tan for Proton Source group PIP II Collaboration Meeting 03 June 2014.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Source 1/12/07 E Prebys 1 Proton Delivery Because MiniBooNE is off.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
F All Experimenters' Mtg - 2 Jun 03 Weeks in Review: 05/19/03 –06/02/03 Keith Gollwitzer – FNAL Stores and Operations Summary Standard Plots.
Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues.
Booster Losses Keith Gollwitzer PIP and MI 700 kW review January 2015.
Proton Planning – Major Projects, Schedule, Decisions, and Projections Eric Prebys FNAL Accelerator Division.
Doug Michael Sep. 16, GeV protons 1.9 second cycle time 4x10 13 protons/pulse 0.4 MW! Single turn extraction (10  s) 4x10 20 protons/year 700.
Proton Plan PMG 2/23/06 E Prebys 1 Proton Plan Status January Report Eric Prebys.
Proton Plan Expectations Eric Prebys AD/Proton Source.
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
Main Injector Beam Position Monitor Upgrade: Status and Plans Rob Kutschke All Experimenters’ Meeting April 3, 2006 Beams-doc-2217-v3.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
High Intensity Booster Operations William Pellico PIP II collaboration Nov. 9 th 2015.
Users' Mtg - 4 Jun 08 FNAL Accelerator Complex Status Ron Moore Fermilab – AD / Tevatron Dept.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Summary Director’s Review August 2006 Eric Prebys.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
Dave Johnson July 12, 2010 NOvA/ANU Recycler Upgrades Review Optics, Apertures, and Operations Nova-doc 4930.
Setting BLM Limits in the Booster The Booster is now delivering all the protons needed by the collider program, and about 40% of the protons needed by.
The Proton Source (mostly Booster) in the “Collider Era” Eric Prebys February 3, 2003.
Early Beam Injection Scheme for the Fermilab Booster: A Path for Intensity Upgrade Chandra Bhat Fermi National Accelerator Laboratory DPF2015, ANN ARBOR,
Proton Plan Director’s Review 8/15/06 Prebys Proton Plan Answers to Questions Director’s Review August 2006 Eric Prebys.
Proton Plan Eric Prebys, FNAL Accelerator Division.
Proton Plan PMG 4/18/05 E Prebys/J. Sims 1 Proton Plan Status March Report Eric Prebys Jeff Sims.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Toward a Proton Plan Eric Prebys Fermilab Accelerator Division.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PAC Meeting, December 12, Prebys 1 The Problem.
Run II Status Keith Gollwitzer Temple Review July 1, 2003.
Intensity Dependent Quad Ramps We know that in order to get the most intensity, the quad ramps must be tuned for a particular intensity. The way this is.
Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets.
MI/RR Operation Status Ioanis Kourbanis August 21, 2014.
Booster Status, September 4, 2003 – E. Prebys 1 Frantic Shutdown Preparations Continue…
Maximum Credible Beam Loss in the Main Injector D. Capista January 26, 2012.
Proton Economics Eric Prebys FNAL Accelerator Division.
Booster Corrector Review, Oct. 10 th, 2006 E. Prebys Introduction/Specifications Eric Prebys Proton Plan Manager.
Presentation transcript:

What’s Up in the Booster Eric Prebys February 27, 2002 and March 6, 2003

Demand for 8 GeV Protons Present Operating Level Fancy MI Loading schemes

Some Cold Hard Facts about the Proton Future Running as we are now, the Booster can deliver a little over 1E20 protons per year – this is about a factor of six over typical stacking operations, and gives MiniBooNE about 20% of their baseline. NuMI will come on line in 2005, initially wanting about half of MiniBooNE’s rate, but hoping to increase their capacity – through Main Injector Improvements – until it is equal to MiniBooNE. Whatever the lab’s official policy, there will be great pressure (and good physics arguments) for running MiniBooNE and NuMI at the same time. -> By 2006 or so, the Proton Source will be called upon to deliver 10 times what it is delivering now. At the moment, there is NO PLAN for achieving this, short of a complete replacement! 1.8E20 ten33% 6

Limitations to Total Booster Flux Total protons per batch: 4E12 with decent beam loss, 5E12 max. Average rep rate of the machine: –Injection bump magnets (7.5Hz) –RF cavities (7.5Hz, maybe 15 w/cooling) –Kickers (15 Hz) –Extraction septa (now 4Hz, 7.5 after Jan. shutdown) Beam loss –Above ground: Shielding Occupancy class of Booster towers –Tunnel losses Component damage Activiation of high maintenance items (particularly RF cavities) Of particular interest to NUMI Our biggest concern

Proton Timelines Everything measured in 15 Hz “clicks” Minimum Main Injector Ramp = 22 clicks = 1.4 s MiniBoone batches “sneak in” while the MI is ramping. Cycle times of interest –Min. Stack cycle: 1 inj + 22 MI ramp = 23 clicks = 1.5 s –Min. NuMI cycle: 6 inj + 22 MI ramp = 28 clicks = 1.9 s –Full “Slipstack” cycle (total 11 batches): 6 inject + 2 capture (6 -> 3) + 2 inject + 2 capture (2 -> 1) + 2 inject + 2 capture (2 -> 1) + 1 inject + 22 M.I. Ramp clicks = 2.6 s

Summary of Proton Ecomomics Booster Hardware Issues Radiation Issues MiniBooNE baseline  5E20 p/year *assuming 5E12 protons per batch NUMI “baseline” = 13.4E12 pps x 2E7 s/year  2.7E20 p/year Right now we’re at roughly 1/3 of the MiniBooNE baseline

Typical Booster Cycle Various Injected Intensities Transition Intensity (E12) Energy Lost (KJ) Time (s)

Booster Losses (Normalized to Trip Point) BRF11: 200 1ft BRF15: 300 1ft

Booster Tunnel Radiation Levels On the last access The people doing the radiation survey got about 20 mR. Two technicians received 30 mR doing a minor HV cable repair. We’re at (or past??) the absolute limit on our overall activation

Hardware Improvements to Booster Shielding and reclassification of Booster towers: complete 2001 New extraction septum (MP02) power supply: complete 11/02 New extraction septum: magnet complete. To be installed 1/03 Collimation system: complete, but cannot be used until… Collimation system shielding: 75 tons of steel to be stacked 1/03 Time line improvements (very important for MiniBooNE operation): more or less complete. More cables for extraction septum (will allow 15 Hz operation): ?? New injection bump magnets and PS: ?? New RF cavities: ??

Near Term Plan All near term hardware improvements will be complete by summer At the point the Booster will physically be able to run a 7.5 Hz. Proceed with tuning improvements (C. Ankenbrandt coor.): –Orbit correctors: complete, working out operational issues –Precision lattice measurement: Transition studies (gamma-t jump??): –Damping improvements: Pellico + ?? –Dogleg compensation?? –37MHz laser prechopping. –Ramping stopband correction. –Injection bump lengthening. –Injection tune manipulation. –Etc.

Dogleg Problem Because of edge effects, the vertical dogleg magnets which steer beam around the extraction septa distort the injection lattice badly. Considering several solutions: –Two large aperture lattice magnets (best idea, lots of money) –Stretch out or redesign doglegs. Can minimize but not eliminate the problem. –Correction quads. No magic solution found. Took advantage of the recent TeV failure to move the dump septum and turn off its dogleg. Doing studies now.

Effect of Doglegs on Booster Dispersion

RF Project RF cavities form the primary aperture restiction in the Booster (2 ¼” vs 3 ¼” beam pipe). Slight modified design will have 5” beam pipe. Powered prototype built and tested. Two vacuum prototypes will be fabricated with fabrication done largely by MiniBooNE and NuMI universities. These will be installed in the summer shutdown. Full project ~$5.5M, maybe less with university help. New solid state power supplies also ~$5.5M, but largely a separate (and separately justifiable!) project.

Upgrade Cost Estimate Summary: ~$260K per cavity, of which $160K goes for the three tuners. A roughly equal amount for the power supply chain. About 20 cavities. -> $11M total

Vague Longer Term Plans Dogleg improvements? –Separate downstream doglegs –beta-bump correctors –Large aperture lattice magnet. Injection bump improvements? –New magnets? –Move existing magnets further apart and redisign injection girder (requires new injection “Lambertson”). –Improved power supply (being designed but on the back burner).

Big Projects Which Have Nothing to Do with Intensity New Linac Lambertson (done, will be installed in summer). New EDWA magnets in MI-8 line (ditto). New vacuum system (Eats up ~1 engineer). Finished by summer? LLRF upgrade. Slowly but surely. New MP01, ML01 + PS. Replace VBC1 with ML02. (magnets not built, no installation plan).

Conclusions We are at or near the present limit of the Booster output. This is a factor of up to six away from what is needed. Current plans might realistically increase things by a factor of two or three, tops. Getting further will be hard!!! The Proton Source CANNOT achieve its goals parasitically. The pressure from the collider program is not going to go away, so we have to come up with a plan to live together.