F Booster Long Straight Corrector Package Installation Craig Drennan 2007 Shutdown Planning Meeting April 6, 2007.

Slides:



Advertisements
Similar presentations
EMMA LAYOUT Neil Bliss, Bruno Muratori EMMA LAYOUT - EC Meeting ERLP EMMA RING EMMA layout is required to fit within equipment and emergency.
Advertisements

System Wiring Communications & Power. RS-485 Cable The standard wire used in RS-485 wiring is Belden 9842 – 24 AWG stranded (7x32) TC (tinned copper)
Industrial Automation. May 4, 2015Confidential: Unauthorized Use Prohibited2 Industrial Automation Alpha Wire’s Value Proposition: Quick delivery for.
Qualified Partner Program Installation Cables Felice Guarna, Training Program Manager Wetzikon, Dec
11-13/10/2007 ILC BDS Kick-Off Meeting, SLAC, US 1 BDS Vacuum System Dr. Oleg B. Malyshev ASTeC Daresbury Laboratory.
Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
RHIC CRYOGENICS SYSTEM Time meeting /28/20141TIME MEETING RUN 14 –CRYOGENIC.
Booster Corrector Upgrade October William Pellico.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
Telecommunications cable types
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
Equipment Installation, piping & wiring Variable Water Flow System.
1 CCTV SYSTEMS PAN, TILT AND ZOOM CAMERAS. 2 CCTV SYSTEMS A PTZ camera is a pan, tilt, and zoom camera that is different from a fixed dome camera in that.
Warm magnets and the remote handling system in the J-PARCν beam line E. Hirose, K. H. Tanaka, Beam Channel Group.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
Motor Supply Cables Product & Application Training.
IHEP participation in SIS300 production UNILAC SIS 18 SIS 100/300 HESR Super FRS NESR CR RESR Institute for High Energy Physics Protvino, Russia FAIR meeting.
1 LEReC Funded! From: Fedotov, Alexei Sent: Thursday, May 14, :04 PM Subject: LEReC project approved Dear All, FYI. The LEReC project is now formally.
ATF2 optics … 1 3 rd Mini-Workshop on Nano Project at ATF ATF2 optics, tuning method and tolerances of initial alignment, magnets, power supplies etc.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
Proton Plan Director's Review 8/15/06 – Booster Corrector UpgradeDrennan1 Proton Plan Booster Corrector Upgrade Directors Review August 2006 Presenter:
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
1 BROOKHAVEN SCIENCE ASSOCIATES Abstract Magnet and Girder Integration Lewis Doom, NSLS-II Project National Synchrotron Light Source II (NSLS-II) will.
Injector/Re-injection Chicane Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
1 Booster Corrector BPM Status AD/ Instrumentation Jim Fitzgerald.
FAIR PROJECT COST BOOK. FAIR cost 1.2 mld euro 1. Civil construction and infrastructure 322Meuro 2. Accelerator systems 592 Meuro 3. Experimental facilities.
F Booster Long Straight Corrector Upgrade Technical Status and Schedule for Installation Craig Drennan DOE Tevatron Operations Review March 27, 2007.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
Beam Line Layout – Cooling Section There seems to be two options for energy measurement: at the 180 dipole and/or in a diagnostic branch at the end of.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
MBA Magnets MultiBend Achromat Magnets 9/27/2013 Review By Mark Jaski.
Analysis of Multipole and Position Tolerances for the ATF2 Final Focus Line James Jones ASTeC, Daresbury Laboratory.
Substation L1/ Booster Substation Y-BE2 Update #3 August 15,2012.
Experience Fabricating the Storage Ring Vacuum Chambers for NSLSII
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Extraction Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
MTA Installation Meeting March 7, 2007 Agenda 1)Progress report (Fernanda) 2)Water skid discussion (Maurice) 3)Alignment needs (O’Sheg + all) 4)AOB Key.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
Proton Plan PMG 5/25/06 David Harding Booster Correctors Status and CR David Harding.
MTA Installation Meeting February 21, 2007 Agenda 1)Progress report (Fernanda+Carol) 2)Floor Plan layout (Fernanda+Larry) 3)AOB Key Red – critical Orange.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
Date 2007/Sept./12-14 EDR kick-off-meeting Global Design Effort 1 Cryomodule Interface definition N. Ohuchi.
Update: Puck and Gun Magnet March 1, Magnetized Gun 2 K 2 CsSb Preparation Chamber HV Chamber.
Thermal measurements of TPG and Diamond I. Bonad, R. Bates and F. McEwan.
Recycler/Ecool Shutdown Planning Meeting (6/4/2010)
March 7 th Shutdown Shutdown Begins: Monday morning, March 7 th :00 Beam OFF Safety System Testing 08:00 Rack out KRSS, switch MI house power to.
Beam Line Layout – Cooling Section (to be installed by 1 Dec ember 2015) J. Kewisch wants to move the 20 dipole, yellow (to the right) toward the triplet.
09/21/07Shutdown’07 Week 7 F.G. Garcia1 MTA beam line installation Weekly Report September 21, 2007 Period covered: September 14 th September 21 th (Week.
1 BROOKHAVEN SCIENCE ASSOCIATES Beam Stability Overview NSLS-II CFAC Meeting May 8, 2007 S. Krinsky.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
RAMI Paul Aden. RAMI Analysis Reliability Visual inspection during each shutdown Service schedule for necessary components Majority of components to have.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
MI/RR Shutdown 2012 Dec Gev Lines/Injection region: Staging equipment, cleaning and prepping new part to start vacuum work. Preparing to modify the.
Booster Corrector Review, Oct. 10 th, 2006 E. Prebys Introduction/Specifications Eric Prebys Proton Plan Manager.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
AD ops. - NUMI July 7, 2006 Jim Hylen/FNAL Page 1 Had been having problem with water collecting in tank under horn 1, instead of coming back to surge tank,
Magnet Power Supply System Overview
FFAG Magnets and Girders Meeting
C50 Cavity pair Assembly Changes
SWITCHES W. C. “Buster” Hounshell Spring 2002.
Maser Cable Training Level 1
Potential Use of PEP-II Magnets by Project X
FRACTIONAL ARC TEST GIRDER DESIGN REVIEW
Electron Collider Ring Magnets Preliminary Summary
Presentation transcript:

f Booster Long Straight Corrector Package Installation Craig Drennan 2007 Shutdown Planning Meeting April 6, 2007

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 2 Installation Tasks  General Installation Tasks  Pulling Power Cables.  Removing Old Correctors.  Installing New Correctors.  Vacuum Leak Checking and Pump Down.

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 3 Installation Tasks  Radiation Level Measured in March  Above 500 mrem  L6  L13  Above 100 mrem  L1  L3  L7  L8  L9

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 4 Pulling Power Cables  Task Manager: James Ranson  Man-Power: Crew of 3 Electricians  Task: Run the cables necessary for 4 each, 6 element corrector packages from 6 Booster gallery locations.

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 5 Pulling Power Cables  Cable Specification (Beams-doc-2599-v1)  Type 1  2 Conductor, Twisted Pair, 8 AWG, Strand Tinned Copper. Insulation Color Coded Red and Black, PVC*, 105 degC rating. Overall Foil Shield With 12 AWG Drain Wire. PVC Tray Cable Jacket, 105 degC rating The jacket is to be marked with incrementing numbers every foot. 10 Each, Continuous 500 foot Reels, Jacket Color Green 10 Each, Continuous 500 foot Reels, Jacket Color White 10 Each, Continuous 500 foot Reels, Jacket Color Red 10 Each, Continuous 500 foot Reels, Jacket Color Black  Type 2  4 Conductor, Twisted Pair, 8 AWG, Strand Tinned Copper. Insulation Color Coded 2 Red and 2 Black, PVC*, 105 degC rating. Overall Foil Shield With 12 AWG Drain Wire. PVC Tray Cable Jacket, 105 degC rating The jacket is to be marked with incrementing numbers every foot. 10 Each, Continuous 500 foot Reels, Jacket Color Black

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 6 Pulling Power Cables  Cable Specification -Cont.-  Type 3  2 Conductor, Twisted Pair, 12 AWG, Strand Tinned Copper. Insulation Color Coded Red and Black, PVC*, 105 degC rating. Overall Foil Shield With Drain Wire. PVC Tray Cable Jacket, 105 degC rating The jacket is to be marked with incrementing numbers every foot. 10 Each, Continuous 500 foot Reels, Jacket Color Black * All PVC insulation is to have an oxygen index greater than 28 ======================================================================== The reel size and weights as follows: 2/C 8awg: 18" diam X 10" wide reels. Approx 98 lbs. per reel. Can fit 12 per skid. 4/C 8awg: 20" diam X 12" wide reels. Approx 170 lbs. per reel. Can fit 8 per skid 2/C 12awg: 16" diam X 10" wide reels. Approx 52 lbs per reel. Can fit 27 reels per skid. Vendor will combine the reels and will have a total of 4 skids shipped. ========================================================================

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 7 Pulling Power Cables  Cable Specification -Cont.-  Type 4  2 Pair Individually Shielded, 22 AWG, 7x30 Strand. Insulation Color Coded Green, White and Red, Black. Belden P/N Each, Continuous 1000 foot Reels, Jacket Color Grey

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 8 Pulling Power Cables  Cable Connections to Each Corrector Elements  Vertical Dipole 2 Conductor, 8 AWG (Type 1), Green Jacket  Horizontal Dipole 2 Conductor, 8 AWG (Type 1), White Jacket  Normal Sextupole 2 Conductor, 8 AWG (Type 1), Red Jacket  Skew Sextupole 2 Conductor, 8 AWG (Type 1), Black Jacket  Normal Quadrupole 4 Conductor, 8 AWG (Type 2), Black Jacket  Skew Quadrupole 2 Conductor, 12 AWG (Type 3), Black Jacket  Klixon Sensor 2 Pair, 22 AWG (Type 4), Grey Jacket  RTD Sensor 2 Pair, 22 AWG (Type 4), Grey Jacket

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 9 Pulling Power Cables

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 10 Pulling Power Cables Cable - Penetration Power Tests (Beams-doc-2599-v1)  Sample run of cables have been tested in a Booster penetration

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 11 Pulling Cables –cont.- Details for Cable Pull (1 of 2)

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 12 Pulling Cables –cont.- Details for Cable Pull (2 of 2)

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 13 Pulling Cables –cont.-  Additional Cables to Pull  8 each, 2 pair, 22 AWG Twisted Shielded Pair cable for KLIXON’s and RTD’s Assumes 1 Klixon and 1 RTD per corrector package.

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 14 Pulling Power Cables  Sub-Tasks for Pulling Cables  Cable labeling database entries are submitted and labeling is procured.  Remove poly-beads from penetrations Vacuuming beads from an empty penetration from gallery end has proven cleaner. Removing beads from gallery end can begin immediately after beam is locked off from the Booster and the Rad- Tech is informed. Will require 3 to 4 each 50 gallon drums.  Cable is delivered from the warehouse and staged near installation location.  A rope pull is made to get an accurate length for each cable run.

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 15 Pulling Power Cables  Sub-Tasks –cont.-  Electricians will layout, measure cable lengths and label cable ends in the gallery.  Cables are pulled from gallery, through penetrations to specific corrector location.

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 16 Removing Old Correctors  Task Manager: Danny Douglas  Man-Power: 2-3 Crews of 3 Technicians  Multiple crews needed to manage individual dose levels.  Task: Remove old correctors, BPM’s and vacuum valves.

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 17 Removing Old Correctors  Standard Installation

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 18 Removing Old Correctors  Sub-Task for Typical Removal  Resource: One 3 man crew

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 19 Removing Old Correctors Special Case 1: L3 Dogleg  The new corrector package will mount between the dogleg magnets and the BEX magnet will move to where the current corrector is now.

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 20 Removing Old Correctors  Sub-Task for Special Case 1 Removal  Resource: One 3 man crew

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 21 Removing Old Correctors Special Case 2: Injection Girder

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 22 Removing Old Correctors  Sub-Task for Special Case 2 Removal  Resource: One 3 man crew

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 23 Installing New Correctors  New Correctors Are Delivered From MTF

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 24 Installing New Correctors  New Corrector Support

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 25 Installing New Correctors  Mechanical Design Schedule

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 26 Installing New Correctors  Sub-Task for Typical Corrector Installation  Resource: One 3 man crew

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 27 Installing New Correctors  Sub-Task for Special Case 1 Corrector Installation  Resource: One 3 man crew

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 28 Installing New Correctors  Sub-Task for Special Case 2 Corrector Installation  Resource: One 3 man crew

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 29 Other Tasks  Further Installation Tasks  Corrector Power Connection  BPM Cable Connection  Surveying of the the Correctors and BPM’s  Vacuum Leak Checking and Pump Down

f 2007 Shutdown Planning 4/6/2007 – C. Drennan 30 Other Tasks  Related Tasks for Future Development and Review  Power outage related task from J. Ranson  Surveying in of Correctors and BPM’s  Early Power Testing of Power Supplies and Corrector Magnets. Specific LOTO need to be developed.