Presented by: Russell M. Arnold Jr., PE Director/Town Engineer Public Works Department Christopher N. Pierce, PE Wright-Pierce
WPCF Background Need for Current Project Recommended Plan Project Cost Estimate Schedule Farmington WPCF Upgrade2 Agenda
Originally Constructed 1960s Expanded in 1970 Additional Capacity Upgrade & Expansion 1994 Additional Capacity Effluent Ammonia Limits Continuous operation Farmington WPCF Upgrade3
WPCA Goals Capacity for projected flows and loads Upgrade aging infrastructure More stringent permit limits Nitrogen (Protect Long Island Sound) Phosphorus (Protect Farmington River) BOD 5 /TSS Improve Energy Efficiency Provide additional odor control 4Farmington WPCF Upgrade
5
PROJECT COMPONENTCOST CONSTRUCTION$47,460,000 CONSTRUCTION CONTINGENCY (5%)$2,370,000 TECHNICAL SERVICES (13.0%)$6,170,000 MATERIAL TESTING (0.5%)$240,000 ASBESTOS & LEAD PAINT ABATEMENT-$50,000 LEGAL / ADMINISTRATIVE / FINANCING$950,000 ENGINEERS ESTIMATE OF COST$57,240,000 6 Farmington WPCF Upgrade
CWF eligible funding $57,240,000 Anticipated grant (21.5%)-$12,306,600 Design (WPCA) -$ 2,893,000 Local share$42,040,400 Anticipated Assessments 78.1%$ 32,833,552 9.5%$ 3,993,838 6.8%$ 2,858,747 4.8%$ 2,017,939 0.8%$ 336,552 7Farmington WPCF Upgrade
Annual Debt Service $1,991,100 (net of Assessments) Increase to Tax Rate.57 Mills Average Assessment $ 232,074 Tax Impact $132.58/Year 8
9Farmington WPCF Upgrade July 8 th Council Agenda – Set Public Hearing August 12 th Council Agenda Public Hearing Section 8-24 Referral Bond Resolution Set Special Town Meeting August through October – Project Information to Public Special Town Meeting – Oct. 25 th Referendum – Nov. 4 th