RAYAN PLAST Survey Report Conducted By: Green Line Company
Power Factor Readings: Off Load: 10% Load Percentage: Predicting the Energy savings Before Installing Powerboss Off Load: / (100) = Formula: Ave kW / Ave Kvar (100) = Saving Factor Power Readings: Grinder 1 (60Hp Motor) On Load: 90% On Load: / (100) = Off Load Full Load
Power Savings
Consumption & Savings 3.313kWh per 5mins kWh per Hour kWh per Day kWh per Week Power Consumption kW: Power Saving kW: 3.2% kWh per Year 1.863Kvarh per 5mins Kvarh per Hour Kvarh per Day Kvarh per Week Power Consumption Kvar: kWh per Year Note: Operation is 24 hours a day, 6 days a week and §§50 weeks a year Kvarh per Year Power Saving Kvar: 5.1 % Kvarh per Year
Power Factor Readings: Load Percentage: Predicting the Energy savings Before Installing Powerboss Formula: Ave kW / Ave Kvar (100) = Saving Factor Power Readings: Mixer (75kW Motor) On Load: 100% On Load: / (100) = 59.57
Power Savings
Consumption & Savings 3.377kWh per 8mins kWh per Hour kWh per Day kWh per Week Power Consumption kW: Power Saving kW: 8% kWh per Year 5.477Kvarh per 8mins Kvarh per Hour Kvarh per Day Kvarh per Week Power Consumption Kvar: kWh per Year Note: Operation is 24 hours a day, 6 days a week and 50 weeks a year Kvarh per Year Power Saving Kvar: 28 % Kvarh per Year
Benefits from PowerBoss This machines can benefit greatly from Powerboss. The softstart function will reduce both starting current drawn by the motor and mechanical strain on bearings, gears, belts and etc. The reduction in starting current will also increase motor’s life. The optimization function will reduce the power supplied to the Motor without changing its torque and rpm. Reducing the power supplied to the motor will significantly reduce the heat, vibration and noise. Reducing wasted energy will also reduce the maintenance cost and production downtime.