Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma.

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

ATLAS LHCC 28/11/00 A. Henriques/CERN 1 H8 : Pixel, SCT, TRT, Tiles, LAr em barrel, Muons SPS H6: EMEC, HEC, FCAL, Background studies GIF: Muons (MDT,
P. Paolucci - I.N.F.N. di Napoli / Joint RPC-Trigger meeting EASY Crate board/cratechannel/crate (max power) power/crate# crate/rackpower/rack#
6/4/2004 CSN1L. Pontecorvo INFN-Roma1 MDT Results from H8 Test Beam End-Cap StandBarrel Stand.
Scintillation counter installation on EBC cryostat scintillators gap scintillators location of MBTS scintillators MBTS counters will be plugged into fiber.
Atlas SemiConductor Tracker Andrée Robichaud-Véronneau.
Davide Piccolo - INFN NapoliSIENA maggio 2004 Production and Quality control of RPCs for the CMS muon barrel system Davide Piccolo – INFN Napoli.
19 March 2012Muon Week - Operations1 Muon Week Muon Operations Session Introduction Status and LHC Schedule Detector Readiness + Preparation for Physics.
The Transverse detector is made of an array of 256 scintillating fibers coupled to Avalanche PhotoDiodes (APD). The small size of the fibers (5X5mm) results.
October 1st th Workshop on Electronics for LHC Experiment at Amsterdam 1 Beam Test Result of the ATLAS End-cap Muon Level-1 Trigger Chikara Fukunaga.
Malte HildebrandtMEG Review Meeting, 14th February 2007 Report of Run Coordinator Run 2006 Summary Malte Hildebrandt MEG Review Meeting, 14th February.
5 March DCS Final Design Review: RPC detector The DCS system of the Atlas RPC detector V.Bocci, G.Chiodi, E. Petrolo, R.Vari, S.Veneziano INFN Roma.
Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005.
1 HBD Commissioning (II) Itzhak Tserruya HBD group meeting November 28, 2006 Progress from October 3 to November 28, 2006.
L. Pontecorvo MDT Status: Installation and Commissioning 5 Missing 9 stations.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
Oct C. Smith - PCAL/EC Commissioning 1 PCAL/EC Commissioning Document
Status of the NO ν A Near Detector Prototype Timothy Kutnink Iowa State University For the NOvA Collaboration.
ATLAS Liquid Argon Calorimeter Monitoring & Data Quality Jessica Levêque Centre de Physique des Particules de Marseille ATLAS Liquid Argon Calorimeter.
ATLAS Muon System WBS 3.5 DoE/NSF M&O Evaluation Group Review BNL 19-Jan-06 Frank Taylor MIT V1.3.
Barrel RPC Chamber consists of 2 double-gaps, each equipped with a common plane of 96 strips read-out by 6 front-end boards. The two double- gaps have.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
1 Status and Outlook of the RPC Commissioning Marcello Maggi/INFN-Bari.
Main priorities for the next years. Where do we stand Muon system in good shape (in my opinion) – Sub-systems hardware quite robust (see later for main.
Status of NA62 straw electronics Webs Covers Services Readout.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
The Status of the ATLAS Experiment Dr Alan Watson University of Birmingham on behalf of the ATLAS Collaboration.
Luca Spogli Università Roma Tre & INFN Roma Tre
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
S.MonteilCOMMISSIONING1 PS/SPD ELECTRONICS OUTLINE 1)STATUS OF PS/SPD FE BOARDS PRODUCTION 2)PHASES OF PS/SPD COMMISSIONING 1)LEDs AND DETECTORS 2)TUBES.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
2/4/2001Ludovico Pontecorvo INFN Roma1 Plans for the H8 system test: 2001/2002 Goals for the 2001/2002 Test beam Beam layout Chamber Supports 2001 Schedule.
CF 16/Feb/20031 H8 Beam Test in 2003 ─ Preparation status TGC-Japan electronics group.
TB Peter Glässel, Heidelberg1 TPC Status Report Project leader: Peter Braun-Munzinger, GSI Darmstadt Deputy project leader: Johanna Stachel, Heidelberg.
P. Paolucci - I.N.F.N. of Napoli 1 RPC workshop, 2 march 07 RPC Power system P. Paolucci, G. Polese and D. Lomidze I.N.F.N. di Napoli.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
1 G. Aielli for the RPC community. General information  BOE to be delivered in September  Detector design is over  Production facility reviewd and.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
AFP Trigger DAQ and DCS Krzysztof Korcyl Institute of Nuclear Physics - Cracow on behalf of TDAQ and DCS subsystems.
1 HBD Commissioning Itzhak Tserruya DC meeting, BNL December 13, 2006 Progress from October 3 to November 28, 2006.
LHCf Detectors Sampling Calorimeter W 44 r.l, 1.6λ I Scintilator x 16 Layers Position Detector Scifi x 4 (Arm#1) Scilicon Tracker x 4(Arm#2) Detector size.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
Chambers to be installed in ATLAS MSW on Small Wheel MBT0 on front-face of end-cap electromagnetic calorimeter.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
1 Antonio Romanazzi 3D CFD study of the ATLAS (UX15) ventilation system.
February 26 th 2013Muon LS1 operation meeting1 Muon LS1 Status Outline Recap of last week P1 weekly schedule Muon related activities Open issues and discussions.
Siena, May A.Tonazzo –Performance of ATLAS MDT chambers /1 Performance of BIL tracking chambers for the ATLAS muon spectrometer A.Baroncelli,
Plots of RPC performance G. Cattani, University of Rome “Tor Vergata” & INFN Roma 2 on behalf of ATLAS Muon Collaboration.
Atlas status report. LHC Cooldown Status LHC is proceeding with the cooldown and the hardware commissioning L.Evans is asking the experiments to close.
TDAQ and L1Calo and Chamonix (Personal Impressions) 3 Mar2010 Norman Gee.
HEP 2007 – 20 Jul 2007 · Manchester, England Commissioning with Cosmic Rays of the ATLAS Muon Spectrometer F.Petrucci INFN Sezione di Roma Tre and Dipartimento.
Straw Working group Ferrara 4/9/2014. Outline Status and Plans Installation of Chambers 1-3 Chamber 4 Vacuum test SRB Readout, monitoring and software.
ATLAS Plenary, Feb. 18th, 05Commissioning1 Report on the commissioning activities G. Mornacchi, P. Perrodo and Sub-Systems Collaborators.
Real data in the Muon Spectrometer Bernardo RESENDE and a lot of other people not named here NIKHEF Jamboree, December 2008.
EPS HEP 2007 Manchester -- Thilo Pauly July The ATLAS Level-1 Trigger Overview and Status Report including Cosmic-Ray Commissioning Thilo.
Operation, performance and upgrade of the CMS Resistive Plate Chamber system at LHC Marcello Abbrescia Physics Department - University of Bari & INFN,
Atlas: Upgrade Phase I Massimo Della Pietra.
RPC Barrel HV & LV system Lappeenranta University
for the transition region on behalf of the RPC upgrade group
Commissioning of the MUON Spectrometers in ATLAS and CMS
ATLAS Muon Spectrometer and
Installation plans from mid 2005
Pierluigi Paolucci - I.N.F.N. Naples
RPC HV&LV status Introduction HV power supply tender
RPC Detector Control System
Bringing the ATLAS Muon Spectrometer to Life with Cosmic Rays
Pierluigi Paolucci & Giovanni Polese
RPC Detector Control System
Presentation transcript:

Atlas Muon Spectrometer: installation and commissioning L. Pontecorvo INFN Roma

2 Outlook Installation Status and perspectives Chambers Commissioning Surface Test Pit Test Cosmic runs in Sector 13 Set-up Few results from MDTs Future data taking during Thoroid Test

L. Pontecorvo INFN Roma 3 66% of the Barrel chambers have been installed Even Sectors completed except for 11 BIS chambers BMS installation : completed 84 chambs BOS installation : completed 102 chambs BIS installation: still 11 chambers to go (sect 12 and 14 side A) 117 chambs Odd Sectors: BOL Installation : 67 chambs Side C still 2 chambers on sect 13 to be installed Side A: Sects 1, 9, 11, chambs in 13, to be installed Still missing in total 2 on side C AND 27 on side A BML installation : 17 chambs Sector 5: 9 chambers (1-3 C and side A completed) installed Sector 13: 6 chambers (1-3 A and C) installed Still missing 41 on side C and 38 on side A BIL installation : 43chambs Sector 13: 9 chambers (1-3 A and side C completed ) Sector 5: 12 chambsers completed Sector 3: 12 chambers Sector 9: 2 chamber Sector 1 : 6 chambers side C completed+2 side A Still missing 34 on side C and 43 on side A Total of installed chambers :430/ EIL4 Installation rate in last months: about 3.5 /day Barrel Installation Status

L. Pontecorvo INFN Roma 4 BIL-BML status BIL: All Side C BIL will be installed by the end of this week Side C BIM-BIR (24 chambers) will be installed in 2007 when the TGC wheel will be moved to give back access to Barrel installation All Side A BIL-BIM-BIR will be installed by the end of BML: On Side C we will install the last sectors (11, 15 and part of 1 and 9) in 2007 after removing the TGC wheel All side A will be installed by the end of 2006

L. Pontecorvo INFN Roma 5 Barrel Side C: Now Not all the chambers are in final position

L. Pontecorvo INFN Roma 6 Barrel Side A: Now USA 8 US Blue not installed Red installed Violet Partly installed

L. Pontecorvo INFN Roma 7 Barrel Side C: Beg. Oct Side C installation is stopped when moving the TGC big wheel towards Barrel C

L. Pontecorvo INFN Roma 8 Side A: End of 2006 End of the installation: Dec 2006, from our present installation rate Few chambers (about 40-50) still to be installed on side C after removing TGC big wheel: Only BML and BIL Editare dati

L. Pontecorvo INFN Roma 9 Manpower for Installation Chamber installation is a TC duty 2 teams of CERN technicians take care of inserting chambers in the spectrometer. Muon Community takes care of: Final chamber positioning Connections and cabling of all the available services Chambers testing Large participation of all the Muon collaboration: Dubna, MPI/LMU, NIKHEF, NTUA/Thessaloniki, INFN. L.Pontecorvo (INFN Roma) and F. Cerutti(INFN-LNF) coordinate all the installation and commissioning activities

L. Pontecorvo INFN Roma 10 Service Installation Service installation and routing is responsibility of TC Large cabling Team is now becoming available and is starting to work on: HV, LV, Control Cables, Alignment cables, Read-out Fibers Gas Piping (from Rack to Manifold and valves) A. Lanza (INFN PV) is the coordinator of this activities Muon Collaboration is responsible for providing cables and for final connections to the chambers including gas piping (lengthy operation) Chamber testing and commissioning can be done only after connection to final services will be completed

L. Pontecorvo INFN Roma 11 Service installation status: MDT MDT HV-LV cables installed for all outer chambers Production and installation under way MDT Alignment cables Installed for most of the chambers MDT DCS daisy chains cable produced for most of the chambers and installed on upper sectors (2,4,5,6) MDT RO/TTC fibers: Installed on most of the upper sectors but not yet connected to chambers Gas connections Chambers to Manifold started in many sectors (BOL, BOS, BIL, BIS) Installed Under installation Installed Length to be evaluated Partly installed Installed Bundles installed and connected Bundles installed and not connected Patch-cords installed Patch-cords installed and not connected

L. Pontecorvo INFN Roma 12 Service installation status: RPC RPC services less advanced than MDT HV cables installed only in sector 13, other sectors in production RPC LV and DCS in production only for sector 13 LVL1 LV cables installed in sector 13 and in production for other sectors LVL1 RO and Timing fibers installed on most of the sectors, patch cords installed only in sector 13. Hpt-Lpt cables installed on most of the sectors LVL1 CAN-cables installed (daisy chain to be produced) Gas connections to manifold well advanced.

L. Pontecorvo INFN Roma 13 Power system status MDT: Most of the crates, branch controllers and AC/DC generators are delivered or under delivery Preseries of the LV distributors is delivered and used in sector 13. First series delivery will take place in October 2006 Preseries of HV distributors is delivered and used in sector 13.. First delivery is foreseen in March 2007 RPC and LVL1: Noise problem discovered when using the prototype version of the HV distributor A3512. The problem is under investigation First delivery of some LV/HV modules is expected before the end of 2006 REMINDER: delivery schedule will be agreed on 25 Sept. taking into account all the requests (ATLAS, CMS, etc.)

L. Pontecorvo INFN Roma 14 Chamber commissioning Muon stations are tested before and after installation SURFACE TEST. Check of the functionality of the detectors prior to the installation, to find any problem occurred during transport/storage and components added just before installation PIT TEST. Check of the functionality of the detectors, of the services and of the correctness of the cabling after installation

L. Pontecorvo INFN Roma 15 Test sequence MDT: Leak : measure MDT pressure before and after transport. HV (2000V): check for broken wires and high currents. LV test: check for LV shorts DCS and alignment test: check for disconnected/not working sensors. Noise and Test Pulse Run : check of the full Read-out chain Test Sequence RPC: Install and cable the Trigger PADS Leak: check the gas tightness of the RPC gaps Test of the Electronics noise: read-out the Pool Down Current Test Pulse run: check full read-out chain and cabling. About 450 chambers have been tested up to now Many small problems solved on the spot About 4% of chambers have been sent back to certification phase Surface test station

L. Pontecorvo INFN Roma 16 Pit Testing Up to now only very basic test have been performed both on MDT and RPC : HV and leak tightness Now the possibility of more refined test is approaching due to the installation of final services. MDT Gas tightness after connection to gas manifolds DCS tests and JTAG initializations Functionality of the alignment sensors Noise tests RPC RPC gas tightness RPC pull-down currents Complete test (no noise runs) Partial tests (HV and Pressure)

L. Pontecorvo INFN Roma 17 MDT DCS and Alignment All DCS computers Installed in USA15 CANbus Power crates installed Read-out of DCS chains in many sectors is performed with final system. All Alignment Computer Installed in USA15 Many sectors cabled and tested with final system First 4 projective alignment lines read-out in sector 13 P. Valente (INFN-Roma) is the new MDT DCS coordinator Alignment PCs DCS PCs and Power crates

L. Pontecorvo INFN Roma 18 Cosmic Ray Test: Sector 13

L. Pontecorvo INFN Roma 19 Sector 13 : Set up Experimental setup: 3 BML and 3 BOL installed and temporarily cabled HV-LV from CAEN pre-series Temporary gas systems used for both RPC and MDT Scintillator trigger installed DAQ DAQ system based on ATLAS RCD (Coordinator E. Pasqualucci INFN Roma) Test of the final MDT MRODX Test of final LVL1 Sector Logic Trigger : RPC LVL1 trigger: 40 Hz(Coordinator S. Veneziano INFN Roma) Scintillator trigger: <1 Hz Stable combined runs (RPC + MDT + CTP with RPC trigger) Trigger distributed to Tile calorimeter via CTP, combined runs Muon+Tile

L. Pontecorvo INFN Roma 20 Sector 13: First MDT results Typical MDT spectrum: Time Spectrum shape as expected Low noise out of the trigger window. Hits per event: Large peak close to 12 hits as expected Very clean hits/track distribution Reconstructed track angle: Cosmic muons points mainly to the large shaft on side A. Hits per event Hits per track Track angle Large shaft Small shaft

L. Pontecorvo INFN Roma 21 Sector 13: MDT-RPC correlation Very good Correlation between RPC Z measurement (  strips) and MDT Z measurement (tube number). Correlation is kept all along the run: no desyncronization during the run. MDT Z measurement RPC Z measurement Difference Zrpc-Zmdt vs event Event number

L. Pontecorvo INFN Roma 22 Goals for thoroid test Experimental set up: 3 BIL-BML-BOL+3BOF/BOG B-field measurement : extensive use of MDT DCS Alignment : Measurement of toroid displacements with reference system Commissioning of first projective lines Alignment with tracks vs alignment system (BOL-BOF) MDT: Detailed NOISE studies: dependence on I tor, Threshold, RPC running conditions, grounding schemes Running parameter optimization Detailed studies of calibrations (r(t), t0, …) vs B-field RPC/LVL1: First running parameter optimization Verify trigger efficiencies vs Pt of cosmics

L. Pontecorvo INFN Roma 23 Conclusions 66% of the barrel chambers have been installed End side A by Dec 2006 End side C (BML-BIM/BIR chambers) by Feb 2007 First TGC big wheel installed Services installation on-going : end by November Chamber commissioning starting with inner layer chambers Power system: first deliveries of LV boards during Oct, HV boards by March 2007 Sector 13 as a benchmark of the phase II commissioning: good results from cosmic ray combined runs with MDT- RPC-LVL1-CTP and Tile Calorimeter.

L. Pontecorvo INFN Roma 24

L. Pontecorvo INFN Roma 25