FieldNet 2.x Enhancement TUG – September 8, 2003 Andres Marin, Info Tech Inc.
Project Scope Objectives Replace the manual processes used by Michigan DOT to ensure effective synchronization and balance between CAS and FieldManager Minimize user involvement and to automate the actual transfer of data between FieldManager and CAS regardless of geographic distances. This will remove many potential points of failure inherent in the current physical transfer of data. Use new technologies and methodologies to ensure that all data transfers are completed successfully or else completely rolled back with the state of both databases corrected.
Project Scope Objectives (cont) Built on Internet standards allowing the ubiquitous, secure and inexpensive automation of business processes. Implement a scalable and flexible architectural design for future enhancements. Data transfers will be authenticated, authorized, reliable, secure, accurately routed and delivered to the correct destination.
Project Milestones
Project Phases Scope Overview Development PhaseScope Summary Elaboration PhaseFunctional & Architecture Specifications; Macro Design Specifications; GUI Specifications Eng. Build Cycle 1Messaging and FN Server Architecture; Reference Files; Contract Initialization Eng. Build Cycle 2Authorization & Authentication; Pay Estimates; Contract Modification; CAS Interface; Implement New User Roles; Contract Transfer Eng. Build Cycle 3Contract Transfer; FM & FB workflows; Reports; Administrative Console; Activity Logging; CAS & FM Synchronization; Installation Utility
Current Status Project Percent Complete: 40% Overall Project Assessment: On schedule and on budget Build Cycle 1: In progress – Engineering complete – Alpha testing - 9/12/03 – System Design Specification updates - 9/12/03 – MDOT QA/QC Test - 9/17/03
Project Budget MDOT Approved Budget$1,210,000 ITI Approved Budget$439,074 Total Budget$1,649,074
Architecture Overview
Architecture Overview Deployment Model
Project Risks - Summary Key Risk Mitigations – Synchronization with FM – Synchronization with CAS – Synchronization with FM / SM Interface
TRT Questions /Answers FM support of FN Versions – ITI recommends FM 4.X to support FN 2.X FN will be compatible with latest version of CAS – CAS 5.2a7/03 – CAS 5.3a1/04 – CAS 5.3b6/04 Licenses changes will not affect “clients” as a result of using IBM WebSphere MQ FN RDBMS support: Oracle 9.ix