YETS PS&TT2 list of works planned and planning Simon Mataguez EN/MEF-OSS More info about the PS machine? Many thanks to all those who have contributed
Simon Mataguez, 26 November Injector Accelerator Schedule
Simon Mataguez, 26 November 2015 PS&TT2 Year End Technical Stop Access Constraints
Planning YETS EDMS Simon Mataguez, 26 November 2015
YETS – Diagnostic Period Simon Mataguez, 26 November 2015
Simon Mataguez EDMS
YETS – BE-BI Simon Mataguez, 26 November 2015 BPM SS90 are delayed
Simon Mataguez, 26 November 2015 YETS – BE-RF
Simon Mataguez, 26 November 2015 YETS – TE-VSC
Simon Mataguez, 26 November 2015 YETS – TE-VSC
YETS –EN-EL Simon Mataguez, 26 November 2015
2. Copper cabling PS 2/8 12/11/2015P. Lelong Campaign PSREX-YEA1 QFN/QDN: -FZ143 -FZ144 -FZ173 -FZ175 APOLO: -FZ167 -FZ170 REMOTE-RESET: -FZ100 -FZ102 -FZ123 OASIS BLM: -FZ138 RENOV DI Z29: -FZ141 INTERL LEIR: -FZ148 MTG: -FZ156 CTRL CONV: -FZ172 Reprise 4 câbles: -FZ161 CABLAGE BE-CO: -FZ939 (Bat )
2. Copper cabling PS 4/8 12/11/2015P. Lelong Campaign PSRIN-YEA1 Interl. LEIR: -FZ148 WIC Linac3: -FZ150 BTV Hall Est: -FZ159 Porte Secteur Bat352: -FZ180 Jauges (9/17/18/32): -FZ160 Pickup SS90: -FZ162 GSM: -FZ168 BGI (SS82): -FZ146 Attente infos! Tests câble Finemet: -FZ174 -FZ179 Cavités RF: -FZ147
2. Copper cabling PS 5/8 12/11/2015P. Lelong Campaign PSRIN-YEB1 (if possible) This campaign could be started but not surely completed! AffaireLOCALISATIONTitleGroupUserNb. cablesLength (m) FZ177001BAT PSCABLAGE BLM (PS-BLO)BE-BIZAMANTZAS Câbles BLM: -SD14 à SD18 Câbles BLM: -SD40 à SD49 Câbles BLM: -SD71 à SD83
2. Copper cabling PS 6/8 12/11/2015P. Lelong Campaign ADEX-YEA1 (From AD to TT2) AffaireLOCALISATIONTitleGroupUserNb. cablesLength (m) FZ104001BAT 193 – TT2CABLAGE TRANSFO TFA9012BE-BILENARDON2540 Plateforme de racks AD Transfo TFA9012
YETS – EN-HE Simon Mataguez, 26 November 2015
PR40 Replacement Remplacement of PR-40 in B.352 Between weeks 1 et 4 (total immobilization of the crane and constraints to access PS by the B.352) Working area
PR3 long-travel revamping Long travel mechanism replacement of PR-3 in B.151 Scheduled for weeks 6 & 7 Total unavailability of the crane during the works Possibility of using a Mobile crane inside the building
YETS – EN-CV Simon Mataguez, 26 November 2015
YETS – TE-ABT Simon Mataguez, 26 November
Simon Mataguez 18 November 2015 Access Tunnel 350 U0-223
Removal 11/01 – Return 05/02 Simon Mataguez, 26 November 2015 EDMS : "Integration du point d'acces zone SWITCH YARD YEA01.SWY=151
Simon Mataguez, 26 November 2015 ECR. PS-JS-EC-000 : "Shielding in Access Tunnel SWY-151" ex-door Removal 12/01 – Return 04/02
YETS – TE-EPC Simon Mataguez, 26 November 2015 YETS – BE-CO
YETS – TE-MPE,TE-MSC Simon Mataguez, 26 November 2015 YETS – EN-STI
YETS – GS - General infrastructure services Simon Mataguez, 26 November 2015
New Sector PS-Y-EC-0001 – EDMS Simon Mataguez, 26 November 2015
YETS – EN-MEF Survey Simon Mataguez, 26 November 2015
CDS/