YETS 2015-2016 PS&TT2 list of works planned and planning Simon Mataguez EN/MEF-OSS More info about the PS machine? www.cern.ch/pswww.cern.ch/ps Many thanks.

Slides:



Advertisements
Similar presentations
XB YETS PS-TT2 Indico EDMS
Advertisements

BI Outlook for BI Day 2012 Based on latest (last Monday) feedback from EN/EL XXX As foreseen originally Partially ‘As foreseen originally‘ Postponed.
LIU CABLING & OPTICAL FIBRES STRATEGY Georgi Minchev Georgiev EN-EL-CF.
EN-EL Organisation and Needs for LIU project Mar 4, 2015 Daniel RICCI, Jerome PIERLOT Section Leaders Cabling and Low Voltage, on behalf of the EN-EL group.
Session 8 - Long Shutdown 2 Strategy and Preparation LIU Planned Activities Reference : RLIUP Oct.2013 (indico) “Work Effort in the LHC Injector Complex,
Industrial Control Engineering Industrial Controls in the Injectors: "You (will) know that they are here" Hervé Milcent On behalf of EN/ICE IEFC workshop.
HLTC 15 th April 2014 EDMS: Y. Muttoni EN-MEF-INT with the contribution of P. Fessia.
INJECTORS BLM BI-TB on Proton Injector start-up. Summary of actions 2 BLM SystemComments LINAC2 8 movable detectors.
HIE-ISOLDE (High Intensity and Energy) project Protection of superconducting solenoids MPE work shop – December 14, 2010 G.J. Coelingh TE-MPE-CP.
MKE4 Rearrangement -Updated Drawings -Visit to ECA4 -Visit to LSS4 -SPS Safety File -Safety during intervention MKE4 Rearrangement - TCM 25 August
Barriere O, Le Roux P
Injector De-cabling Project Project Team Meeting #
Injector De-cabling Project Enlarged meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
1 st R2E RADIATION SCHOOL & WORKSHOP Some Organisational Issues.
LIU-IONS Linac3 meeting LIU Project – Planning and Installation Julie Coupard EN/MEF-OSS.
LS1 Injectors K. Foraz on behalf of N. Gilbert, S. Mataguez, D. Hay & D. McFarlane LSC 24 th May /05/2013LSC – EN-MEF-OSS1.
Injector De-cabling Project Enlarged meeting # E. HARROUCH, EN-MEF, on behalf of the Injector De-cabling Project Team.
Booster LV Electrical Distribution: Schedule and Quantities Aims: Modernisation of Booster electrical infrastucture To install necessary infrastructure.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
Injector De-cabling Project Enlarged project meeting # S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
Work Effort in the LHC Injector Complex for the Upgrade Scenarios B. Mikulec Thanks to all the valuable input from the LIU project leaders and LIU work-
ISOLDE Activities for LS2 Richard Catherall EN-STI ISOLDE Technical Coordinator.
K. Foraz & Perrot A. L., EN/MEF - R2E Project LMC 25th May 2011 Thanks to EN/EL, EN/HE, EN/MEF, equipment owners the LHC integration team & the R2E team.
BOOSTER ORPHAN CABLES Georgi Minchev Georgiev EN-EL-CF 08/10/2015 General De-cabling Project Meeting #4.
YETS COMPLEX PS 2015/2016 Travaux EN/EL/CF P. LELONG, J-M. LASSAUCE & G. GEORGIEV 12 Novembre 2015.
Consolidation activities for GS-SE Luigi Scibile GS-SE Accelerator Consolidation Workshop, EDMS:
12th February 2010David Mcfarlane EN-MEF-ABA1. History of Booster The accelerator was built in The Proton Synchrotron Booster is the first, in the.
2. Linac Systems 3. Booster Systems 4. Installation commiss. 5. Building, Infrastruct. 2.1 Ion Source and LEBT, R. Scrivens, BE/ABP 2.2 Radio Frequency.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
Booster identification/disconnections Follow-up Enlarged project meeting, E. HARROUCH, EN-MEF, on behalf of the Injector De-cabling Project.
HIE-ISOLDE Project: Planning & Resources Y. Kadi (EN-HDO) and the HIE-ISOLDE Project team.
SPS YETS 2015/2016 Planning meeting for BE-BI 09/12/15 David Mcfarlane EN-MEF D.Mcfarlane1.
Injector De-cabling Project Project meeting # 7, S. EVRARD, EN-MEF, on behalf of the Injector De-cabling Project Team.
SPS YETS 2015/2016 Planning meeting (No.3) 07/10/15 David Mcfarlane EN-MEF D.Mcfarlane1.
Injectors & LHC report K. Foraz on behalf of OSS members 01/11/13LSC - EN-MEF-OSS1.
EN-EL Activities for LS2 LIU, Consolidation, Maintenance, Operation Nicolas Bellegarde on behalf of EN-EL.
Mid Term Review Meeting, 26 September * Research project supported by a Marie Curie Early Initial Training Network of the European Community’s Seventh.
European Organization for Nuclear Research Industrial Controls Engineering Department GUAPI working group meeting May the 6th 2015.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
R2E relocation & shielding LS1 preparation Anne Laure Perrot EN/MEF- LE Discussion with OP colleagues, 5 th July 2012.
Each converter 3 racks (fighting for 2?) Access from front and rear of each rack! 56 racks total + 6 racks Ethernet/control Existing RF equipment to be.
Activities related to BE-BI during LHC-YETS 7 th December, 2015 Maria Barberan, Marzia Bernardini.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
PSB HW Commissioning Meeting 8 February 2016 A. Akroh, B. Mikulec.
R2E relocation & shielding activities: status report Anne Laure Perrot EN/MEF- LE On behalf of the R2E coordination team LS1 Committee – meeting #48, 27.
LIU–PLI report LIU Project Team meeting. Follow-up on the Engineering Change Requests Engineering Change Requests for the YETS PSB PS.
Electrical Group Inputs for LIU-Ions J. Devine, on behalf of EN/EL.
Controls Activities & Organisation during LS1 Eugenia Hatziangeli BE/CO LS1 Day – 12 th June 2012 Input from Machine Controls Coordinators (S. Jensen,
LIU Critical Key activities in Long Shutdown 1 (2013) LIU-PSB: assuming LINAC4 connection in LS2 –Beam dump consolidation If not done: operation will be.
ELENA installation progress F. Butin / ELENA collaboration.
LS1 Day: The Injectors S. Baird EN/MEF Thanks to R Brown, N Gilbert, D McFarlane & V Chohan, IEFC workshop…. LS1 Day: The Injectors 1.
SPS Personnel Protection System Renovation Project
BE-BI Activities and Status: LHC and Injectors
Injector De-cabling Project
LIU – EVM status and next steps
EYETS16-17 ACTIVITIES EN-EL-CF
Planning and Installation
Julie Coupard Schedule and Coordination
C.Carli Budget and Planning ELENA Project Review, 15th October 2013
TE/EPC activities for YETS & LS2 LINAC 2-3, PSB, PS & TT2
PSB/PS/TT2/Linac2-3 YETS 2017–2018 & LS2 preparation meeting
SPS Planning for the EYETS Meeting 9 (14/12/2016)
Update on the Ethernet Network Installation Campaign
Summary of ECRs for the YETS Booster, PS, ISOLDE and associated transfer lines (LIU + Consolidation) T. Birtwistle (EN-MEF-DC)
YETS PS + PS SWY + TT2 Facility Coordinator:
Linac4-PSB 160 MeV connection readiness review ( TE/VSC )
HIE-ISOLDE Project: Planning & Resources
LINAC 3 Meeting ICL machines Injectors
Linac4 Connection Broken Line 07/08/19
LIU EL-FC ACTIVITIES Updated on 28/11/2017
Presentation transcript:

YETS PS&TT2 list of works planned and planning Simon Mataguez EN/MEF-OSS More info about the PS machine? Many thanks to all those who have contributed

Simon Mataguez, 26 November Injector Accelerator Schedule

Simon Mataguez, 26 November 2015 PS&TT2 Year End Technical Stop Access Constraints

Planning YETS EDMS Simon Mataguez, 26 November 2015

YETS – Diagnostic Period Simon Mataguez, 26 November 2015

Simon Mataguez EDMS

YETS – BE-BI Simon Mataguez, 26 November 2015 BPM SS90 are delayed

Simon Mataguez, 26 November 2015 YETS – BE-RF

Simon Mataguez, 26 November 2015 YETS – TE-VSC

Simon Mataguez, 26 November 2015 YETS – TE-VSC

YETS –EN-EL Simon Mataguez, 26 November 2015

2. Copper cabling PS 2/8 12/11/2015P. Lelong Campaign PSREX-YEA1 QFN/QDN: -FZ143 -FZ144 -FZ173 -FZ175 APOLO: -FZ167 -FZ170 REMOTE-RESET: -FZ100 -FZ102 -FZ123 OASIS BLM: -FZ138 RENOV DI Z29: -FZ141 INTERL LEIR: -FZ148 MTG: -FZ156 CTRL CONV: -FZ172 Reprise 4 câbles: -FZ161 CABLAGE BE-CO: -FZ939 (Bat )

2. Copper cabling PS 4/8 12/11/2015P. Lelong Campaign PSRIN-YEA1 Interl. LEIR: -FZ148 WIC Linac3: -FZ150 BTV Hall Est: -FZ159 Porte Secteur Bat352: -FZ180 Jauges (9/17/18/32): -FZ160 Pickup SS90: -FZ162 GSM: -FZ168 BGI (SS82): -FZ146 Attente infos! Tests câble Finemet: -FZ174 -FZ179 Cavités RF: -FZ147

2. Copper cabling PS 5/8 12/11/2015P. Lelong Campaign PSRIN-YEB1 (if possible) This campaign could be started but not surely completed! AffaireLOCALISATIONTitleGroupUserNb. cablesLength (m) FZ177001BAT PSCABLAGE BLM (PS-BLO)BE-BIZAMANTZAS Câbles BLM: -SD14 à SD18 Câbles BLM: -SD40 à SD49 Câbles BLM: -SD71 à SD83

2. Copper cabling PS 6/8 12/11/2015P. Lelong Campaign ADEX-YEA1 (From AD to TT2) AffaireLOCALISATIONTitleGroupUserNb. cablesLength (m) FZ104001BAT 193 – TT2CABLAGE TRANSFO TFA9012BE-BILENARDON2540 Plateforme de racks AD Transfo TFA9012

YETS – EN-HE Simon Mataguez, 26 November 2015

PR40 Replacement Remplacement of PR-40 in B.352 Between weeks 1 et 4 (total immobilization of the crane and constraints to access PS by the B.352) Working area

PR3 long-travel revamping Long travel mechanism replacement of PR-3 in B.151 Scheduled for weeks 6 & 7 Total unavailability of the crane during the works Possibility of using a Mobile crane inside the building

YETS – EN-CV Simon Mataguez, 26 November 2015

YETS – TE-ABT Simon Mataguez, 26 November

Simon Mataguez 18 November 2015 Access Tunnel 350 U0-223

Removal 11/01 – Return 05/02 Simon Mataguez, 26 November 2015 EDMS : "Integration du point d'acces zone SWITCH YARD YEA01.SWY=151

Simon Mataguez, 26 November 2015 ECR. PS-JS-EC-000 : "Shielding in Access Tunnel SWY-151" ex-door Removal 12/01 – Return 04/02

YETS – TE-EPC Simon Mataguez, 26 November 2015 YETS – BE-CO

YETS – TE-MPE,TE-MSC Simon Mataguez, 26 November 2015 YETS – EN-STI

YETS – GS - General infrastructure services Simon Mataguez, 26 November 2015

New Sector PS-Y-EC-0001 – EDMS Simon Mataguez, 26 November 2015

YETS – EN-MEF Survey Simon Mataguez, 26 November 2015

CDS/