Beam Rotatable Collimators as a Possible US Contribution to the LHC Luminosity Upgrade Project 24 April 2008 LARP CM#10 Tom Markiewicz/SLAC BNL - FNAL-

Slides:



Advertisements
Similar presentations
Coll Eng E Doyle 1/18 LARP Phase II Secondary Collimator RC1 Prototype Engineering Status 6/21/06 Jaw-hub-shaft concept - continued Permanent.
Advertisements

Status of the LARP Phase II Secondary Collimator Prototype 30 September 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US.
CLIC collimator survival IWLC 2010 J.L. Fernández-Hernando – ASTeC/Cockcroft Institute (Daresbury Lab.) 21/10/2010 J.L. Fernández-HernandoASTeC/CI21/10/2010.
Status of the LARP Phase II Secondary Collimator Prototype 14 October 2013 LHC Collimation WG Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
SLAC rotating collimator for HiRadMat beam tests 14 March 2014 S. Redaelli, A. Bertarelli, CERN T. Markiewicz, SLAC US LHC Accelerator Research Program.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes now twist, under vacuum, as jaws turn, with R~1.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes twist, under vacuum, as jaws turn, with R~1 m.
Beam LARP Contributions to LHC Phase II Collimation 07 November 2007 ATLAS Forum Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research.
LARP Rotatable Collimator Prototype Assembly completed and all mechanical tests successful: Cooling tubes now twist, under vacuum, as jaws turn, with R~1.
Beam LARP Rotatable Collimator Mechanical Engineering Discussion 03 October 2008 Phase II CERN ME Video Mtg. Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC.
Summary of Accelerator Systems Collimation Parallel Session 19 October 2007 LARP CM#9 - SLAC Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator.
LHC Phase II Collimator teleconference - 4 March 2008LHC Rotatable Phase II Collimators 1 beam LARP Phase II collimator Progress and Plans 4 March 2008.
Introduction to collimators Integration of BPM Mechanical design Electrical design Processing Simulations Results Conclusions & Outlook.
1 LARP Phase II Secondary Rotatable Collimator Evolution of design changes 3 rd March, 2010.
LHC Phase II Collimator Compact jaw simulations New FLUKA => ANSYS mapping scheme New 136mm x 950mm jaw –60cm primary collimator –Helical cooling channel.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 06 June 2006 No 1 /17 LARP Phase II Secondary Collimator RC1 Collimator Test Program Plan Forward Revised.
1 Status of the CLIC two-beam module program A. Samochkine, G. Riddone Acknowledgements to the Module WG members 4 February 2014 CLIC Workshop 2014 (3-7.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 16 May 2006 No 1 /22 LARP Phase II Secondary Collimator RC1 Collimator Test Program Revised 5/15/06.
The SLAC Phase II Collimator Program 15 June 2005 CERN Team Visit Tom Markiewicz SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
Preparation of Review R. Assmann et al CWG, CWG R. Assmann.
SLAC R&D Mtg November 2007LHC Rotatable Phase II CollimatorsSlide # / 17 beam LARP Rotatable Collimators for LHC Phase II Collimation 12 November.
CERN Phase II Collimation Conceptual Review Summary 09 April 2009 LARP CM12 Napa, CA Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research.
LARP Rotatable Collimators for LHC Phase II Collimation 18 April 2007 LARP Collaboration Meeting – Fermilab Tom Markiewicz/SLAC Representing Gene Anzalone,
Design Review of the 1 st Rotatable Collimator (RC1) Prototype Project Overview 15 December 2005 Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator.
1 LARP Collimator Engineering E. Doyle 2/3/05. 2 Review: SS Thermal Simulation 150mm OD 25mm wall Simply supported Heat: 1hr beam life, FLUKA results,
Main features of PETS tank J. Calero, D. Carrillo, J.L. Gutiérrez, E. Rodríguez, F. Toral CERN, 17/10/2007 (I will review the present status of the PETS.
Beam Rotatable Collimators as a Possible US Contribution to the LHC Luminosity Upgrade Project 20 June 2008 LARP DOE Review Tom Markiewicz/SLAC BNL - FNAL-
A. Bertarelli, A. DallocchioEuCARD/ColMat Kick-off Meeting 17/06/2009 EuCARD/ColMat Kick-off Meeting EuCARD/ColMat Kick-off Meeting 17 th June, 2009 A.Bertarelli,
Task List for Phase II Rotatable Collimator Project at SLAC 30 January 2007 CERN/LARP Video Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC.
Collimation Overview 28 October 2008 LARP CM11, Fermilab Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program 1)Short Status.
LARP LHC PHASE II SECONDARY COLLIMATOR CD1 REVIEW. - E. Doyle 15 Dec /25 LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 Prototype Engineering.
LARP Coll. Video-conf. May 12, '05Phase II Collimator Engineering - E. Doyle1/20 Adapting the NLC Consumable Collimator to LHC Phase II Secondary Collimation.
LARP Rotatable Collimators for LHC Phase II Collimation 09 July 2007 SLAC R&D Status Meeting Gene Anzalone, Eric Doyle, Lew Keller, Steve Lundgren, & Tom.
Phase II Collimators for LHC Upgrade at SLAC - Material Issues E. Doyle 03 Sept /25 Workshop on Materials for Collimators CERN 2007/09/03 Phase.
A. Bertarelli – A. DallocchioWorkshop on Materials for Collimators and Beam absorbers, 4 th Sept 2007 LHC Collimators (Phase II): What is an ideal material.
LARP Rotatable Collimators 19 June 2006 ILC R&D Status Meeting Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 30 Jan 2007 No 1 /13 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
LARP LHC PHASE II COLL RC1 TESTS - S. Lundgren 10 Dec 2007 No 1 /12 LARP Phase II Secondary Collimator RC1 Collimator Development and Test Program Status.
LARP LHC PHASE II COLL RC1 - S. Lundgren 21 Sep 2009 No 1/17 LARP Phase II Secondary Collimator RC-1 Collimator Development Status and Outlook Revised.
Summary Session Advanced Collimation CARE-HHH-APD BEAM'07 R. Assmann.
accident deformation – doyle 1/12 Phase II Collimator - Accident Deformation Simulation December 11, 2006.
SPS High Energy LSS5 Thermal contact & cooling aspects
LARP Phase II Secondary Collimator Status Report SLAC ILC R&D Summary Meeting 24 April 2006 T. Markiewicz/SLAC.
News and Introduction from CERN June 15th, 2005
LARP Contributions to LHC Phase II Collimation
LARP Phase II Secondary Collimator RC1, ETC - Status 4/10/06
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1
LARP Phase II Secondary Collimator RC1
Problem: A kicker failure can deposit 9 x 1011 protons on any metallic
LARP Phase II Secondary Collimator RC1 Review SLAC 12/15/05 RC1 Construction and Test Plan LARP LHC PHASE II COLL REVIEW – RC1.
Dump Core Studied Design Solutions
Joint Meeting SPS Upgrade Study Group and SPS Task Force
2th EuCard Col/Mat WP Meeting
Recommendations of 12/16/05 review committee & SLAC response
LARP Collimation – Engineering & Analysis
23 April 2012 Tom Markiewicz/SLAC
LARP Phase II Secondary Collimator RC1
accident deformation – doyle (rev1) 1/8
Phase II Collimators : design status
LARP Phase II Secondary Collimator RC-0 and RC-1
LARP Rotatable Collimators for LHC Phase II Collimation
LARP Phase II Secondary Collimator RC-1
US LHC Accelerator Research Program
Micro Status Report of SLAC Phase II Plan Tom Markiewicz SLAC
RC1 Prototype Conceptual Design Review 15 December, 2005
LARP Phase II Secondary Collimator RC-0 and RC-1
US LHC Accelerator Research Program
accident deformation – doyle 1/8
Presentation transcript:

beam Rotatable Collimators as a Possible US Contribution to the LHC Luminosity Upgrade Project 24 April 2008 LARP CM#10 Tom Markiewicz/SLAC BNL - FNAL- LBNL - SLAC US LHC Accelerator Research Program

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 2 / 34 Vision DOE/LARP management perception is that rotatable copper collimators are relatively simple mechanical devices that could be offered as a low risk component of a US LHC Luminosity Upgrade Project, offsetting risk of not delivering Nb 3 Sn magnets, their main interest.

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 3 / 34 The Problem Suggesting that the US manufactures 36 of these devices for the 30 reserved Phase II secondary collimator lattice slots (plus 6 spares) Soft peddles fact that – 1 st single jaw has only now been brazed and still needs some weeks of work before thermal-mechanical tests can begin –SLAC has not begun, the “almost” fully defined, process of building the 1 st full beam testable double jaw collimator Ignores the CERN collimation “White Paper” plan calling for construction and mechanical, vacuum & beam testing of three “complementary” designs that can bring LHC luminosity from to before a production decision is made –The Cu secondary RCs do not give x10 improvement in luminosity –Destructive testing of the by-design damageable Copper may be prove extensive enough to remove RC from consideration Does not address adequately the quality control issues seen in CERN’s Phase I collimator production nor has there yet been any talk or agreement with CERN on interface, installation, or engineering support issues.

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 4 / 34 My Opinion LARP, through SLAC, is participating fully in the Phase II Collimation project as outlined in the CERN “White Paper” plan and any action on LARP’s part that looks, as this does, like it is circumventing the agreed to schedule damages our relationship with our colleagues and is doomed to failure. If, after the R&D process concludes in October 2010, a decision is made to produce some number of rotatable copper collimators, SLAC is ready to participate. This exercise should only be taken at the “CD-0” level: mission need and ballpark cost estimate, and is hopefully, laying the bureaucratic groundwork for eventual US participation in construction of collimators

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 5 / 34 References Executive Summary Second Phase LHC Collimators R. Assmann Description Phase 2 Collimator Project R. Assmann Collimation Issues for the Two LHC+ Scenarios and Future Plans R. Assmann Beam’

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 6 / 34 White Paper Plan 1.The R&D and prototyping of at least three different concepts for advanced collimation designs, each addressing different possible limitations to LHC luminosity. 2.Operational experience of the LHC with the Phase I collimation system to understand the nature of any luminosity limit and the best ways to ameliorate deleterious effects with already installed systems. 3.Testing of prototypes at CERN to their technological limits before any installation in the LHC 4.Installation and testing of qualified Phase II prototypes in the LHC during the second full year of LHC operation with a decision on phase II design and production, which may require more than one technology, at the end of the year. 5.Production of the collimators during years 3-4 of LHC operation, installation during regularly scheduled shutdowns and use beginning with year 5 of LHC operation.

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 7 / 34 White Paper Schedule

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 8 / 34 CERN Phase II R&D Budget

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 9 / 34 CERN Pre-Production Manpower vs. Time

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 10 / 34 Production Estimated at 8M CHF

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 11 / 34 NLC Consumable Collimator rotatable jaws – 500 to 1000 hits 6.0 Note short high-Z material. radiative cooling! Aperture control mechanism – 5  m accuracy & stability Alignment BPMs upbeam & down Movers align chamber to beam based on BPMs

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 12 / 34 LHC Phase II Base Concept physical constraints current jaw design beam beam spacing: geometrical constraint Length available 1.47 m flange - flange Jaw translation mechanism and collimator support base: LHC Phase I >10 kW per jaw Steady State heat dissipation (material dependent) Cu coolant supply tubes twist to allow jaw rotation Hub area Glidcop Cu Mo Cantilever Mo both ends Helical cooling channels 25mm below surface 20 facets

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 13 / 34 Cu Jaw-Cu Hub-Mo Shaft Design 2mm shaft-jaw gap gives x5 improvement in thermal deformation over solid shaft-jaw design 1260 um  236 um (60kW/jaw,  12min) 426 um  84 um (12kW/jaw, t=60min) Rather than Cu, Moly shaft improves Gravity sag x3: 200 um  67 um Thermal bulge 30%: 339 um  236 um

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 14 / 34 Brazing Each Moly Shaft End to a Central Copper Hub After much R&D, developed method to braze Molybdenum to Copper for inner shaft

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 15 / 34 Three Braze Cycles Three main brazing steps. Brazing materials set to melt at gradually lower temperature. 1.) Braze each shaft end to a central half-hub 2.) In one go: Braze shaft hubs to Mandrel 25% Gold, 75% Copper Braze copper cooling coil to Mandrel 35% Gold, 65% Copper 3.) Braze jaw quadrants to mandrel surface 50% Gold, 50% Copper

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 16 / 34 Inserting Molybdenum Shaft Ends into Mandrel then Wind Coil Around Mandrel with Ends of Coil Protruding Out Each End

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 17 / 34 Braze Step#1 Shaft Assembly & Coil to Mandrel On support stand and ready for insertion in baking oven Carbon block used to hold thermally expanding copper against central hub and shaft (moly and copper) Next time may use carbon block full length of mandrel

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 18 / 34 Filling Coil-Mandrel Keystone Gaps Three brazing cycles needed before coil- mandrel ‘keystone’ gaps filled adequately On 3 rd cycle excess braze material attaches support stand to mandrel, which warps Pix of 2nd braze cycle

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 19 / 34 Recovery after Excess Braze Material Attaches Mandrel & Shaft to Inox & Inconel Braze Supports

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 20 / 34 Measure & Machine Quadrants to Mandrel. Assemble & Braze Using Au-Cu brazing material ($$)

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 21 / 34 Results of Jaw Brazing 22 April 2008 Looks good! QA measurements will be done 23-Apr Next step is machine flat facets and grooves for heater tests and thermocouple holes.

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 22 / 34 Internally actuated drive and jaw mount for rotating after beam abort damages surface Completed 27 May 2007 Rotation drive with “Geneva Mechanism” Universal Joint Drive Axle Assembly Thermal expansion Gravity sag Differential transverse displacement

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 23 / 34 Up Beam end detail beam side view of Current Idea for RF Transition to Beam Pipe LCR meter, Contact Resistance, Trapped Mode Calculations Spiral style backing springs reside inside “Sheath” (sheath not shown) Round to Square Transition Thin sheet metal RF “Curtain”

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 24 / 34 Summary of Mechanical Design Complete braze procedure developed, but want to look at… Full length graphite choke when brazing coil to mandrel Keystone reduction –Blowing up coil with compressed air –Wedging copper between mandrel between coil slots to drive it towards coil Using 360 quarter length jaws with braze wire rings cut on ID rather than 90 quarter length jaws Anything to reduce number surface prep requirements for brazes Support & rotation done Well developed ideas on RF features that (in principle) are far from critical path

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 25 / 34 Performance Risks Will thermal-mechanical testing of the first jaw validate the shaft-hub- jaw design that should limit maximum jaw deflection into the beam area to 230 microns for 10 second bursts of 60kW beam absorption Will the mechanical accuracy of the device be adequate (40 um) Will the basic jaw-adjustment and jaw-rotation work as planned Will the effective impedance and RF characteristics of the jaw and the transition to the vacuum tank aperture be adequate Will the device vacuum be sufficiently low When damaged by an aborted beam, will the extent of damage be sufficiently localized to allow rotation to a clean surface, as planned

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 26 / 34 Exact Nature & Extent of Damaged Region Thin Cu sample in FFTB electron beam at SLAC Hole = Beam Size 2000um 500 kW 20 GeV e- beam hitting a 30cm Cu block a few mm from edge for 1.3 sec (0.65 MJ) FNAL Collimator with.5 MJ

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 27 / 34 Accident Case: Permanent deformation AND Molten copper Case: beam abort system fires asynchronously, 8 full intensity bunches into jaw Model: - increased resolution 3-D ANSYS & FLUKA models - Thermal heating/cooling analysis followed by quasi-static stress analysis - Jaw ends constrained in z during 200 ns, released for 60 sec cool-down MJ deposited in 200 ns - Molten material removed from model after 200 ns Result: - 57e3 peak temperature (ultra fine model) - 54  m permanent deformation (concave) 5mm melt 2.5mm x 2.5mm elements T max = 57 e3 Shower max – extent of melted zone 3.3mm Cooling tubes Shaft Jaw facets

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 28 / 34 Braze Test #3: Vacuum tests: No improvement 3rd Jaw Braze Test Assembly has been vacuum baked at 300 degrees C for 32 hours. Results in slightly lower pressure. Inclusion of longitudinal grooves in the inner length of jaws for better outgasing Test Chamber setup similar to previous test. OldNew Baseline3.2E-9 Torr2.4E-9 Torr?? w/ jaw assy.3.7E-9 Torr3.4E-9 Torr Presumed jaw assy. pressure 4.5E-10 Torr10E-10 Torr?? LHC requirement 7.5E-10 Torr

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 29 / 34 Efficiency Studies Chiara Bracco (CERN) Performance (Efficiency) of collimation system depends on # particles getting into the cold aperture (>10  ) per unit length as a function of location around the LHC given the optics model AND an aperture model 500E6 Halo protons tracked over 200 turns in 10cm steps by Bracco et al to get loss maps for each magnet Beam intensity limitations are due to losses in the dispersion suppressor above the quench limit. Phase I to II Global Improvement Phase I Beam Intensity Limit

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 30 / 34 Intensity Limit at “Dispersion Suppressor” with Phase II at Nominal Collimation Settings Losses due to particles that hit primaries but that do not see the secondaries While philosophy is every bit helps (take the x3.6) “ultimate” luminosity may require different collimation settings or completely different collimators (crystals as primaries?)

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 31 / 34 Graphite -> Copper Switching to copper will decrease the imaginary part of the impedance but increase the real part This is either good or bad depending on how you want to damp beam instabilities (Landau Damping versus Feedback) So, impedance still dominated by copper collimators

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 32 / 34 Unscrubbed Unit Cost Based on work done to date: $250k

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 33 / 34 Project Cost “x2 Estimate” Unit Cost for Tank, 2 jaws, rotation & support, RF$250k Unit Cost for Rack & pinion, motors, LVDTs$50k These are probably underestimates: Assembly, test & qualification at SLAC4 FTEs 36 units over 2 years$200k EDI&A6 FTE Lab overhead42%

LARP CM# April 2008Rotatable Collimator CP Proposal - T. MarkiewiczSlide n° 34 / 34 Project Schedule Sure to be dominated by braze operations and braze oven cycles 72 jaws with 3 braze cycles per jaw –imply that while not excluded 2 years of production is aggressive –1 year construction seems impossible