Detector Gas Systems Status Update Ferdi Hahn PH-TA1-GS Detector Steering Meeting November 2004.

Slides:



Advertisements
Similar presentations
Control and IT Systems status and strategy ALBA, Piotr Goryl on behalf of Michał Ostoja-Gajewski, Krzysztof Wawrzyniak, Łukasz Żytniak, Tadeusz.
Advertisements

ALICE TPC Ne/CO2 Gas System. Mixing Rack CO 2 -Removal & (O 2,H 2 O)- Cleaning Rack.
Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
US CMS DOE/NSF Review: May 8-10, US CMS Cost & Schedule Mark Reichanadter US CMS Project Engineer DOE/NSF Review 8 May 2001.
The RPC Closed loop Gas System. Schedule for completion - update Status Supplier: ok Mixer: ok Humidifier: ok Purifiers: installed, but not completely.
Xe leak status C. Garabatos. Leak story The maximum allowable leak rate corresponds to a loss of 10% of the total volume in one year – 0.3 l/h for the.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
LHCC Comprehensive Review – September WLCG Commissioning Schedule Still an ambitious programme ahead Still an ambitious programme ahead Timely testing.
P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety.
Analysis Modules F. Hahn. Goal of todays Meeting Inform about current status and layouts of the analysis modules. (the focus will be on common modules)
GIF++ gas systems 21/01/2014Ernesto, Roberto PH-DT-DI gas service1.
Experimental Beampipes: Status and Outlook Ray Veness / AT-VAC For the beampipe team With many thanks to the experiment’s installation and coordination.
04/02/ FH Plans for 2005 PH-DT1-GS. 04/02/ FH Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans Technicians: Andrea.
Gas Coordination Panel 24/08/2004 Flammable Gas Installation Requirements, Interlocks, etc. F.H.
DT1 Gas Section Debrief of 2005 activities.. The Purpose of the Debrief  Compare plan and achievements.  Analyze how the work is done ? Do we meet the.
The Construction of the LHC Detector Gas Systems ? Ferdi Hahn PH-TA1-GS Detector Steering Meeting 4th of June 2004.
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
Active gas system status. S.Konovalov, K.Zhukov. Active gas system operation. S.Konovalov "Active gas system..."TRT Overview  Good design.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
TOF Gas System Project Overview. Content Prototype for Aging tests done for RPC’s TOF Gas System: parameters and module layouts. Special Technology: channel.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
The RPC Closed loop Gas System Slides from Bianco and Guida.
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
JCOV 24 NOVEMBER 2005 J.Godlewski EP-ATI 1 JCOV NOVEMBER 2005 ATLAS cooling systems installation plans Jan Godlewski CERN EP-ATI The H.Niewodniczanski.
ALICE-TRD gas system 1/4/2015R. Guida PH-DT-DI1. TRD gas system Few numbers:  Total number of modules/racks: 20 (max leak rate certified at construction.
G. Pugliese RPC requests for GIF++ G.Pugliese, N. Zaganidis and I. Pedraza on behalf of the RPC group 1.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Activities and news Last meeting: 2015 CERN budget allocations as expected, now distributed on accounts Annual report done, and MTP (Medium Term Plan)
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
Introduction Straw Working group meeting CERN group 1 NA62 Collaboration meeting, Brussels 7-10/9/2010.
Status of and Installation Plan for DC Gas Control System and Target Work Scheduling Meeting 4 August 2006 PSI W. Molzon, Feng Xiao.
Cable Layouts, Connectors for the LHC GAS SYSTEMS GAS COORDINATION MEETING, OCTOBER 2005 PH / DT1 GS.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed.
Gas System production for LHC detectors Stefan Haider EP / TA1 - Gas.
5 th May 20061M. Battistin CERN LEAF Committee 2/R-030 8h30 - May 5 th 2006 Michele Battistin (TS/CV/DC) TS M&O agreement for Detector Cooling installations.
STATUS REPORT WP7 Facilities and Component Analysis for Detector R&D Activities and Status Resources and Expenditures Work plan Mar CAPEANS 3/11/08 M.C.
R. Boyd 1 February  Dr. M. Saleem  D. Jana  M. R. Meera Labbai  R. Boyd.
October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Atlas Gas Systems - CPC6 Upgrade and Re-Commissioning Infrastructure Meeting – 8th January 2014 Steve Pavis PH-DT-DI/Gas.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
26/03/2014L-Ph. DE MENEZES & F. MERLET CERN/PH-DT-DI New recuperation system for n-Pentane:  Installation of the module in parallel of the first.
25/04/2014R. Guida, A. Wasem PH-DT-DI Gas1 Outline ALICE gas systems meeting Outline Introduction Review usage of ALICE gas M&O 2013 Review achievements.
25/03/2014P. Carrie, R. Guida, S. Pavis PH-DT-DI Gas1 Outline LHCb gas systems meeting Outline Introduction Review usage of LHCb gas M&O 2013 Review achievements.
MERIT review, Dec. 2005CERN AB-ATB1 CERN installation I. Efthymiopoulos, A. Fabich, J. Lettry CERN AB-ATB MERIT review, Dec.
Overview on the Proposal for a new Gamma Irradiation Facility at CERN GIF++ Mar CAPEANS April 29 th, 2009 April 29, 091M.C.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
CMS-GEM gas system GEMs for CMS High Eta Muons - Workshop III, CERN April R.Guida PH-DT-DI.
MUON Project Overview Action Items from September meeting New Action Items Update to the List of Worries Update of plans for the next 6 months.
Gas system for NA62 Straw detector Roberto Guida On behalf of Gas Service Team NA62 Straw working meeting, March 26, 2012 Outline: P&I Drawing Schedule.
Report on database work for INB in ALICE Latchezar Betev (ALICE) Information Session INB – June 8, 2006.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Totem Gas Systems ( T1, T2 ) F. Hahn and S. Haider PH / DT1.
Beampipe Installation Status Ray Veness For the Beampipe team in AT/VAC and TS-MME.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
110 th November 2010EN/CV/DC Detector Cooling Project - advancement status of Work Package N3 Thermosiphon project Michele Battistin 18 May 2011.
TRD Gas System Layouts Production Readiness Review 03 – Nov F. Hahn.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
21 Mar 2007ALICE - Paul Dauncey1 ALICE CR07: Installation and Commissioning Paul Dauncey Material from: L. Leistam: “ALICE Status” W. Riegler: “Commissioning.
Section Meeting News and MARS 22/01/ FH1. General Activity and Staff Organigram for the DI Section 22/01/ FH2 TF+GlassAndre Braem Thomas Schneider.
ELENA installation progress F. Butin / ELENA collaboration.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Detector Gas Systems Status Update Ferdi Hahn PH-DT1-GS 3 rd Detector Steering Meeting on Gas Systems June 2005.
Gas Schedules
Gas system Commissioning procedures and status
Totem Gas Systems ( T1 , T2 ) S. Haider PH / DT1.
Gas System Commissioning
CMS gas systems meeting
Current Status Future Progress Monitoring
Technical Support Activities in PH-ADO-PO
Presentation transcript:

Detector Gas Systems Status Update Ferdi Hahn PH-TA1-GS Detector Steering Meeting November 2004

Physicists: Stefan Haider, Serguei Morozov (PJAS), Ferdi Hahn, Mar Capeans (from January 2005) Technicians: Andrea d’Auria, Patrick Carrie, Daniel Fromm, Steven Pavis, Albin Wasem, Sylvain de Boissieu (since 10/2004) Frederic Merlet (since 11/2004). FSU: Aygun Aydin, Vincent Darras, Leon Muller, Herminio Rama, A. Sari. Protvino Team: Andre Kiver, Vladimir Kosenko, Anatoli Kapitchinkov Our Team

Content Work Package Definition Construction Program Progress since June 2004 Problem Areas –Update on items from June –Other Points Progress Monitoring Schedule Status Summary

Current Work Packages Approved: –WP’s ATLAS and CMS Gas Systems Defined, but not approved: –WP’s for ALICE, LHCb Gas Systems Not included in our Current Work Plan: –ATLAS ID purge systems –TOTEM (no WP) –LHCb GEM (requirements undefined) Okay ! Design and WP ready next Week (…approval should be done)

Baseline Construction Program 34% 27%21%18% Number of Modules (~ Number of Racks) N.B. Auxiliary systems not included.

Progress since June 2004 (1) Ongoing Construction Work: –Mixer Modules (18 units) (85 % completed) (awaiting decision on pressure regulator). –ATLAS Distribution Racks for TRT and Muons (30 Racks) (30% completed) –Pump Module (14 units) (20% completed) In Preparation (for 2005): –Circ.+Exhaust Modules (14 units), –Humidifier Modules (3 units), –Distribution ALICE and LHCb (~ 17 Racks)

Progress since June (2) Successful Test of full Control System (Pilot System) on the ALICE TPC System. Outsourcing of Production of Control Chassis’s is started. In Preparation: –Pilot Commissioning of Multi Channel System (for end 2005)

Re-Enforcements New Staff: –Two new technicians started this autumn –One Physicist will join end of this year Protvino Team: –Will increase from 3 to 5 persons next in New Laboratory in Bldg. 216 (from beg. 2005) The Pace for the construction will still increase.

Update on Problem Areas (since June 2004) Ageing Risk: ↑ Bottlenecks due to component validation, are getting better, but still problematic ↑ Improved component cleaning from 2005 onwards. Schedules: ↑ Acceleration of construction work ↑ Progress monitoring (presented today) ↔ Anticipate “Engorgement” of activities for Installation and Commissioning ↔ Main commissioning of Closed Loop Circuits in Additional Work: ↑ ATLAS ID Purge Systems designs ready WP can be signed very soon ↔ Test activities, Test beam, etc.

New Cleaning Facility PH – TS collaboration (Joint financing between PH and TS) Installation specially tuned to remove Si pollutants. Intensive studies to find the best machine and the best process. ( done by Cedric Petitjean) Installation can be operational by February N.B. Large parts continue to be cleaned in Prevessin For small parts only (not for pipes)

Problem Areas (2) Manpower –Contract (S 108) transition (-> FSU) makes more administrative work.  From 8 OSVS/year to > 70 Jobs/year  Administrative tools today are insufficient Though, work definition will be better on the long run  For us: difficulties with accounting of FSU work for ATLAS. –Protvino Team will need 2 nd Person with English knowledge when going from 3 to 5. Electrical components for flammable gas systems: –There are new European standards: quite strict and not always appropriate for CERN –Induces extra cost for systems concerned. –But, CERN must allow some exceptions, e.g. MFC’s, Valve positioners + ELMB control chassis -> Inquiry (to PH DL) for derogation is ongoing The exceptions will not compromise the safety They will reduce extra cost and work.

Project Monitoring CostSchedule What ? Material Cost balance Manpower balance How ? Monitor remaining work versus time. Manpower (Updated every 6 months)

Material Cost

Material Cost Balance 42% of budget spent No overall cost overrun !

ATLAS Material Cost RPC: extra humidifier module not in the budget 50 % of budget spent

CMS Material Cost 53% of budget spent

LHCb Material Cost 16% of budget spent

ALICE Material Cost 31% of budget spent

Manpower

> Introduction Type A: Engineering manpower (not considered here) Type B: Construction manpower –Currently we have 8 persons; 7 on construction 1 for management + other activities 5 persons in FSU 3 persons from Protvino (to be increased next year) Monitor: Remaining Work (Estimate) versus Total Work (Budget) Work Done (Measured) - =

(Type B) Manpower Balance FSU activity over last 6 months ATLAS work since last 12 months Status Sept Overruns: ATLAS: Delayed start-up. Mixer Module: Component change. FSU partly backlog from previous contract, help for ATLAS Short-term balance since: Start of FSU (6 months) and since start of Protvino Team (12 months) All in men-months

Full Manpower Balance (type B) 26 % of budget spent All in man-years

FSU 4 FTE/y Type B Manpower versus Time Atlas Protvino 3-5 FTE/y Extra Manpower 1 -3 FTE’s Today

Planned and Remaining Work Type B Manpower Integrated Man-power spent Remaining work Current Estimate Overrun 1.4 m-y Today Budget

Schedule (1) Construction

Schedule (1) We plan to complete >90% of the distribution modules by the end –That should enable the experiments to install UX racks according to their schedule. In 2005 we concentrate on Pump Module, Circ. + Exhaust Module, Humidifier Module (RPC’s). US-installation (Pre-Distribution), remaining Purifiers, Membrane Modules are done > Construction completion of all baseline modules (approved WP’s) will not be before Construction

Construction Schedule

Schedule (2) Installation + Commissioning

Installation Schedule 1.Commissioning schedule of Fixed Piping circuits –Availability of neutral gases in the underground. 2.Schedule of –Detector piping –Chamber connections to pipe work –Installation of plastic pipes (pilot pressures for pneumatic valves (ATLAS)) 3.Schedule for cabling: –Freezing of cable parameters –Cabling installation schedule Our needs from Experiments:

Schedule (2) Installation should be organized by Zones: –UX caverns come first, rack connections of multi channel systems are handled by piping contracts of the experiments. –SG and US areas: we will install complete areas where possible Plan: Start with CMS SG and then Plug Alice –Apart from some exceptions commissioning of closed loop systems will be done in –Flushing of Open circuits can be possible before. Installation If the experiments have priorities please let us know.

Proposal Installation Planning (1) ATLAS: UX racks in time in 2005 Main Commiss. in 2007 CMS : UX racks are done Do SG in 2005 Closed Loop Commissioning

Proposal Installation Planning (2) ALICE: TPC in commis. early 2005 Single Pass Syst.’s Mid TRD, TOF in 2007 LHCb: Muon and OT Distribution early 2006 RICH’s pending TRD

Status Summary Construction ATLAS Distribution going fine. Delivery on schedule, or slightly ahead of schedule. Mixer Modules delayed (by 3 months) due to lacking pressure regulator validation. Pump Module is ongoing fine. Construction will accelerate in 2005 due to new staff, new Lab, etc. Focus on Installation and commissioning: –“pilot” commissioning of Multi-channel system 2005/2006