Hospital Revitalisation Grant: 2010/11 Financial Year Presentation to the Select Committee on Finance October 2010.

Slides:



Advertisements
Similar presentations
STANDING COMMITTEE ON APPROPRIATIONS NATIONAL HEALTH GRANT PREPAREDNESS 8 March
Advertisements

PRESENTATION TO THE SELECT COMMITTEE ON APPROPRIATION 19 OCTOBER 2010.
1 Portfolio Committee on Home Affairs Compliance monitoring in the Department of Home Affairs 30 April 2013.
1 COMMUNITY LIBRARY CONDITIONAL GRANT 4 th Quarter Performance: 2011/12 Financial year.
1. PRESENTATION TO THE SELECT COMMITTEE ON FINANCE 03 September 2008.
Guided by the decisions of the National Health Council (NHC) In financial year 2010/2011, the National Department of Health rationalized and reformed its.
1 Outcome of Conditional Grants & Capital Expenditure as at 30 November 2005 [Section 40(4) of PFMA] Select Committee on Finance National Council of Provinces.
IN YEAR MONITORING & BUDGET PREPARATION WORKSHOP PREPARED BY BUDGET OFFICE MAY
Presented by Themba P Wakashe Director-General REPORT ON THE UNSPENT BUDGET 2009/10 TO STANDING COMMITTEE ON APPROPRIATIONS.
INTEGRATED SUSTAINABLE RURAL DEVELOPMENT AND URBAN RENEWAL PROGRAMMES 26 FEBRUARY 2002.
REPORT TO THE SELECT COMMITTEE ON APPROPRIATIONS ON HOSPITAL REVITALISATION GRANT PERFORMANCE DR SIBONGISENI DHLOMO MEC FOR HEALTH KWAZULU NATAL.
REPORTING, MONITORING AND PERFORMANCE EVALUATION PROVISIONS ON NON-FINANCIALS – 2013/14 1 MIG Quarterly Workshop 3 – 4 September 2013.
1 Water Services to Schools and Clinics Programme 20 June 2007 Presentation to Select Committee on Education and Recreation By DWAF.
Limpopo - Health1 Report to the Select Committee on Finance on the Provincial Budgets and Expenditure Review 2001/ /08 and Conditional Grants and.
Report on the Challenges in the Planning and Procurement of Services for the Ceres and van Rhynsdorp Correctional Facilities Portfolio Committee on Correctional.
Public Hearing on Performance of Hospital Revitalisation Programme Grant April – September 2010 Department of Health Western Cape 20 October 2010.
PRESENTATION: PORTFOLIO COMMITTEES ON CORRECTIONAL SERVICES AND HEALTH PROVISION OF HEALTH CARE WITHIN CORRECTIONAL CENTRES 1.
CIVILIAN SECRETARIAT FOR POLICE STATUS REPORT ON IMPLEMENTATION OF THE CIVILIAN SECRETARIAT FOR POLICE SERVICE ACT 2 OF 2011 PORTFOLIO COMMITTEE ON POLICE.
DEPARTMENT OF HEALTH HEALTH PORTFOLIO COMMITTEE BRIEFING: HOSPITAL REVITALISATION PROGRAM Infrastructure Management 5 September 2012.
1 PROGRESS MADE AND RECOMMENDATIONS OF THE PORTFOLIO COMMITTEE ON THE RURAL HOUSING IINFRASTRUCTURE PROGRAMME 09 NOVEMBER 2011.
DEPARTMENT OF CULTURE, SPORT AND RECREATION MPUMALANGA PROVINCE COMMUNITY LIBRARY CONDITIONAL GRANT 2011/12 FINANCIAL YEAR 1.
PORTFOLIO COMMITTEE on HEALTH
1 PRESENTATION TO THE PORTFOLIO COMMITTEE ON THE OVERVIEW OF THE NDPW PRESENTED BY THE TOP MANAGEMENT COMMITTEE 26 MAY 2004.
Sport Infrastructure Grant. Pre-2004 there was a national grant for municipal sports infrastructure managed by SRSA This funding was incorporated into.
1 SELECT COMMITTEE ON FINANCE PUBLIC HEARINGS 13 FEBRUARY 2007.
Province of the EASTERN CAPE DEPARTMENT OF PUBLIC WORKS DOH REVITALISATION PROGRAM EASTERN CAPE PROVINCE PRESENTATION TO SELECT COMMITTEE ON APPROPRIATIONS.
Hospital Revitalization Grant Infrastructure Performance Review : Western Cape April-September 2010 Presentation to Select Committee on Appropriations.
1 Northern Cape Department of Health HOSPITAL REVITALISATION PROGRAMME January 24 th 2012.
NORTHERN CAPE EDUCATION DEPARTMENT – CONDITIONAL GRANTS EXPENDITURE AND PERFORMANCE 16 September 2009.
11 PUBLIC HEARINGS ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 2008/2009 PARLIAMENT 27 AUGUST 2008.
Hospital Revitalisation Joint Budget Committee 23 May 2005.
Joint Report to Select Committee on Appropriations by Northern Cape Department of Health Northern Cape Department of Roads & Public Works supported by.
2016/02/17STANDING COMMITTEE ON APPROPRIATIONS 1 NATIONAL DEPARTMENT OF HEALTH PRESENTATION TO STANDING COMMITTEE : APPROPRIATIONS 12 AUGUST 2009.
NATIONAL DEPARTMENT OF HEALTH National Health Insurance Grant Select Committee on Appropriations Hearing on 3 rd and 4 th Quarter Expenditure 4 th June.
PROVINCIAL INFRASTRUCTURE GRANT NCOP 06 March 2006.
PRESENTATION ON CONDITIONAL GRANTS TO THE SELECT COMMITTEE ON APPROPRIATIONS NORTH WEST DEPARTMENT OF HEALTH 08 AUGUST
FREE STATE DEPARTMENT OF HEALTH Presentation on the Status of Conditional Grants Public Hearings on Conditional Grants 03 May 2006.
NCOP PRESENTATION ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE – NORTH WEST. FOURTH QUARTER ENDING 31 MARCH
ILIMA/LETSEMA PROJECT GRANT PRESENTATION TO SELECT COMMITTEE ON APPROPRIATION KZN AGRICULTURE & ENVIRONMENTAL AFFAIRS 21 MAY 2013.
1 Hospital Revitalization Grant Performance Report: Free State.
STRENGTHENING HEALTH SECTOR PREPAREDNESS OF DISASTER THROUGH HRP 14 October 2009 Mr Ndinannyi Mphaphuli Director: Hospital Revitalisation Programme NDOH.
1 Provincial Budget Outcome of Conditional Grants and CAPEX As at 31 March 2006 Select Committee on Finance Presentation by Northern Cape Provincial Treasury.
2013/14 Annual Report Briefing for the Portfolio Committee On Higher Education and Training 5 November 2014.
REPORT TO THE NCOP ON HOSPITAL REVITALISATION GRANT PERFORMANCE AS AT END OF 2010/11 QUARTER 2 DR S DHLOMO MEC FOR HEALTH- KWAZULU NATAL AND Ms M GOVENDER.
Presentation to the Select Committee on Finance: 1 st Quarter 2006/07: Conditional Grant Hearings Housing Delivery Status Department of Local Government.
PRESENTATION TO THE PORTFOLIO COMMITTEE WORKSHOP ESTIMATES OF NATIONAL EXPENDITURE (ENE) 2016/17 Date: 12 – 13 April 2016 e: 13 October
PRESENTATION TO THE NCOP TRANSPORT, ROADS & PUBLIC WORKS
National Department of Health Presentation to the Standing Committee on Appropriations Public Hearings on the Adjustments Appropriation Bill 05 November.
National Council of Provinces Select Committee on Finance
North West provincial Treasury presentation on Conditional Grants and Capital Expenditure as at 30 June 2008.
REVIEW AND IMPROVEMENT OF PED REPORTING SYSTEMS
Select Committee on Finance Presentation by
1. Data on trends in allocations, transfers and expenditure.
PRESENTATION TO PARLIAMENT CONDITIONAL GRANTS AND CAPITAL EXPENDITURE
03 SEPTEMBER /09 FINANCIAL YEAR
24 JANUARY 2019 NORTHERN CAPE PROVINCE
LIMPOPO DEPARTMENT OF PUBLIC WORKS PRESENTS
Select Committee on Finance Presentation by
Select Committee on Finance Presentation by
13 NOVEMBER 2007 DEPARTMENT OF HEALTH AND SOCIAL DEVELOPMENT
PUBLIC HEARING ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE
Report to the Select Committee on Finance on the 4th Quarter Provincial Budget Report for the 2005 / 2006 financial year Conditional Grants and Capital.
Provincial Treasury Western Cape
Report on Conditional Grants
MPUMALANGA 4TH QUARTER EIG PERFOMANCE
HOSPITAL REVITALISATION PROJECTS REPORT TO THE SELECT COMMITTEE ON APPROPRIATIONS AUGUST 2012 Northern Cape Department of Health & Department of Roads.
Future budget trends:MTEF
PRESENTATION ON THE CONDITIONAL GRANT TO THE SELECT COMMITTEE
Briefing to the Portfolio Committee on Health, Parliament The State of Mental Health Services in the Northern Cape June 7th 2017.
What is an audit of predetermined objectives?
Presentation transcript:

Hospital Revitalisation Grant: 2010/11 Financial Year Presentation to the Select Committee on Finance October 2010

.. Background The Hospital Revitilisation Grant is utilised to replace and revitalise current hospitals in the Province. Prioritization of the projects is done as per the Departmental Service Transformation Plan. The following projects have been prioritised in the allocation: – –Mental Health Hospital; – –Upington Hospital; – –De Aar Hospital; – –Prof ZK Matthews Hospital; – –Kimberley Hospital; – –Kuruman Hospital – –Postmasburg Hospital The Department of Roads and Public Works serves as the implementing agent on all infrastructure development projects;

.. Financial Information

.. Mental Health Hospital PurposeProvision of Mental Health Services Commencement Date2006 Projected Completion Date2008 Initial Project CostsR290 million Expenditure to dateR360 million Cause of delaySlow delivery by the contractor on site Current StatusMatter with the Court of Law Remedial measuresAppointment of CIDB graded contractors Additional costs to complete project R380 million Total estimated costR740 million

.. Upington Hospital PurposeProvision of Level Two Services Commencement Date2009 Completion Date2012 Initial Project CostsR836 million (construction, organizational development, health technology & quality assurance, excluding escalations) Expenditure to dateR278 million Cause of delayNone Current Status50% Total project costsR836 million

.. De Aar Hospital PurposeProvision of Level Two Services Commencement Date2010 (Phase 1) Completion Date2012 Initial Project CostsR400 million (construction, organizational development, health technology & quality assurance, excluding escalations) Expenditure to dateR25 million (earth works) Causes of DelayChange of services package Current StatusSite establishment for staff accommodation, reservoir & fencing Projected project costsR400 million

.. Prof ZK Matthews PurposeProvision of Level One Services Commencement Date2006 Completion Date2008 (additional work commenced in 2009) Initial Project CostsR80 million Expenditure to date Causes of DelayNone Current Status98% additional work complete Projected project costs

.. Kimberley Hospital PurposeProvision of Tertiary Services Commencement Date2013 Completion Date2018 Initial Project CostsR1,600 billion Expenditure to dateNone Causes of DelayNone Current StatusDevelopment of business case Projected project costsR1,600

.. Kuruman Hospital PurposeProvision of Level Two Services Commencement Date2013 Completion Date2016 Initial Project CostsR900 million Expenditure to dateNone Causes of DelayNone Current StatusDevelopment of business case Projected project costsR900 million

.. Postmasburg Hospital PurposeProvision of Level One Services Commencement Date2011 Completion Date2013 Initial Project CostsR200 million Expenditure to dateR0 Causes of DelayApproval of the business case by the NDoH Current StatusDevelopment of Project Brief Projected project costsR200 million

.. Performance & Monitoring (DoH & Public Works) Each project has the initial Project Implementation Plan to outline the activities and time frames; The project deliverables are measured on quarterly basis; The Project Implementation Plan is developed on annual basis but with quarterly targets for reviews; Monthly financial reports are submitted to NDoH; A representative of PDoH participate in the site meetings; Monthly progress meetings between the implementing agent and the client take place; The National Treasury Infrastructure Reporting Model and In Year Monitoring report are used to monitor expenditure; Reports are also presented to the Project Management Forums.

.. Co-ordination of the HRP Project Prioritisation was done through the Service Transformation Plan The following table presents the HRP projects implementation plan up to 2016/17 financial year:

.. Co-ordination of HRP Project (cont) HOSPITAL REVITALIZATION PROGRAMME 2010 UP TO 2016 BUDGET BID Project2009/ / / / / / / /2017 Barkly West HospitalR 9,000R 1,000R 0 Mental Health FacilityR 155,967R 69,800R 10,000R 0 Upington HospitalR 140,000R 220,000R 240,000R 197,000R 20,000R 0 De Aar HospitalR 18,307R 103,068R 130,000R 120,000R 10,000R 0 Postmasburg HospitalR 6,000R 20,000 R 107,572R 65,436R 0 Kuruman HospitalR 0R 150R 2,500R 0R 140,000R 200,000 R 250,000 Kimberley HospitalR 6,000R 200R 2,392R 1,482R 170,000R 250,000 Hartswater HospitalR 0 R 500R 200R 49,243R 30,379R 15,742 Kakamas HospitalR 0 R 500R 1,500R 47,000R 28,124 Springbok HospitalR 0 R 500R 1,500R 0 Grand ManagementR 5,000R 6,000R 5,500 R 6,000 Total AllocationR 340,274R 420,218R 410,892R 431,754R 461,679R 489,379R 518,742R 549,866

.. Performance of Contractors and Consultants Contractors are unable to meet the monthly deliverables as per their set programmes due to insufficient capacity in their companies; Their respective under- performance subsequently leads to underspending on the project; Poor coordination between the Contractors/Consultants and implementing agent leads to further delays on the project.

.. Capacity to implement the Hospital Revitilisation Programme The Dept of Public Works is responsible for the implementation of the programme; The Department of Health is only responsible for planning(development of business case, project brief and supervision of designs), reporting and monitoring of projects; Due to limited capacity at Public Works, there is no proper monitoring on projects, hence mental health hospital.

Conclusion Projects are planned timeously, with the necessary inputs from all stakeholders;Projects are planned timeously, with the necessary inputs from all stakeholders; Challenges are often experiences, with the service providers either not meeting their deadlines, or not being able to complete the project;Challenges are often experiences, with the service providers either not meeting their deadlines, or not being able to complete the project; Remedial measures include:Remedial measures include:  Termination at the earliest confirmed inability to complete the contract;  Regular monitoring meetings are held, in order to assess progress;  Regular report-backs to management and recommendations on how to prepare for the take-over of the project, once completed;  Ensuring that there is value-for-money is attained. THANK YOU