Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.1 LCLS Ultrafast Science Instruments (LUSI) T. Fornek – Project.

Slides:



Advertisements
Similar presentations
Cost, Schedule & Funding Closeout Jan Joint DOE/NSF CD2/3a Review 1 DOE/NSF Review of the Dark Energy Survey (DES) Project SC 6/7 Cost, Schedule.
Advertisements

DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science OECM Limited-External Independent.
Tom Fornek LUSI 12 November 2008 SLAC National Accelerator Laboratory 1 LUSI Status Update Tom Fornek Project Manager.
Tom Fornek LUSI June 17, LUSI UPDATE – June, 2008.
J. B. Hastings LUSI Overview LCLS FAC March 20, 2007 LUSI Overview J. B. Hastings January 2007 Lehman Review Response to Lehman Review.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
M. Reichanadter LCLS Project June 2008 FAC Meeting Report to the LCLS Facilities Advisory Committee Project Management.
John Arthur Photon April 20, 2006 Photon Systems Update John Arthur SLAC Photon Systems Manager.
1 T. Fornek 1 LUSI CXI FIDR June 3, 2009 Thomas Fornek Project Manager June 3, 2009 LUSI Coherent X-Ray Imaging Instrument Final.
John Arthur PIXEL Project April 7, 2005 Status of the Proposed PIXEL Project John Arthur SSRL/SLAC Photon Instrumentation.
1 T. Fornek 1 LUSI XCS FIDR June 17, 2009 Thomas Fornek Project Manager June 17, 2009 LUSI X-Ray Correlation Spectroscopy Instrument.
FRA’s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight.
Mark Reichanadter LCLS FAC Oct12-13, 2004 Meeting of the LCLS Facilities Advisory Committee LCLS Organization & Execution.
David Pindroh Procurement Overview LUSI DOE Review 8/19/08 – 8/21/08 p.1 LCLS Ultrafast Science Instruments (LUSI) David Pindroh – LCLS Procurement Manager.
Trish Mast External Independent October 9, 2007 Linac Coherent Light Source (LCLS) The Rebaseline Process Trish Mast October.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Marty Fallier Director for Conventional Facilities CD-2 Planning May 8, 2007.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
OFFICE OF SCIENCE 1 3. Cost Estimate Gines, Fisher 2.Are the estimated cost and proposed schedule ranges realistic, consistent with the technical and budgetary.
7/26/2006 Wyatt Merritt 1 DECam Preparations for Critical Decision 2/3a Preparations for CD2 Preparations for CD3a DECam MOUs.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Executive Session Director’s CD-3b Review of the MicroBooNE Project January 18, 2012 Dean Hoffer.
1 E. Bong 1 XCS Final Instrument Design Review Engineering Status April 21, 2009 LUSI WBS 1.4 X-Ray Correlation Spectroscopy Final.
July LEReC Review July 2014 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.
LBNE Working Group Meeting December 20, :00– 5:00 PM Snake Pit.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
W.J. Foyt LUSI DOE Review July 23, 2007 Project Management 1 Project Management W. J. Foyt Project Scope Timeline Cost Estimate.
DOE Order 413.3A Program and Project Management for the Acquisition of Capital Assets Catherine Santana Deputy Director, Project Management Systems, OECM.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
7/26/2006 Wyatt Merritt 1 DECam CD1 Documentation DOE Critical Decision Process Documentation Requirements.
Fermilab Presentation Greg Bock, Pepin Carolan, Mike Lindgren, Elaine McCluskey 2014 SC PM Workshop July 2014.
Felix B. Fernandez LUSI DOE Review August 20, 2008 PMCS Overview p. 1 LCLS Ultrafast Science Instruments (LUSI) Felix B. Fernandez.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
LHC CMS Upgrade Project CD-1 Alternative Selection and Cost Range Steve Webster Federal Project Director August 26, 2013 CD-1 Executive Session.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Strykowsky 1Project Review November 2, 2005 NCSX Project Review November 2, 2005 Cost and Schedule Ron Strykowsky.
September 10, FY 2003 Plans Bob Simmons. September 10, Introduction Overview of Project and Engineering Plans Project Plans Engineering Plans.
Nadine Kurita LUSI DOE Review July 23, 2007 PMCS 1 Project Management Cost and Schedule Nadine Kurita ANSI/EIA-748-A Standard.
6/6/ SOFTWARE LIFE CYCLE OVERVIEW Professor Ron Kenett Tel Aviv University School of Engineering.
DOE Review of LARP – Feb 17-18, 2014 DOE Critical Decision Process Ruben Carcagno February 17,
Cost and Schedule Breakout Session Paul Weinman Pacific Northwest National Laboratory.
IV&V Facility 7/28/20041 IV&V in NASA Pre-Solicitation Conference/ Industry Day NASA IV&V FACILITY July 28, 2004.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Office of Project Management Oversight and Assessments Office of Critical Decision-3 Approve Start of Construction or Brief Presented by:
Camera PDR/CD1 Planning 19 September 2008
Nadine Kurita - LUSI Chief Engineer
Project Management W. J. Foyt
X-ray Pump-Probe Instrument
Linac Ops Budget Review LCLS Overview / Org Structure / Legacies
Linac Ops Budget Structure & Approach WBS 1 – LCLS Mgmt & Admin
Development of LCLS Far Experimental Hall Hutches
Linac Coherent Light Source (LCLS)
Thomas Fornek Project Manager July 15, 2009
Tom Fornek Project Manager April 20-22, 2009
Details supporting the increase
LUSI MANAGEMENT OVERVIEW
Project Management Issues John N. Galayda, SLAC April 24, 2002
DOE Review of the LCLS Project
PIXEL Project Status John Arthur Photon Instrumentation for
Linac Coherent Light Source (LCLS)
Preliminary Project Execution Plan
LCLS Instrument MIE Project: Staffing, Schedule
Presentation transcript:

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.1 LCLS Ultrafast Science Instruments (LUSI) T. Fornek – Project Manager August 19, 2008 Management Overview

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.2 Outline Project Management Overview Scope & WBS Organization Baseline Development Funding Profile Project Schedule Contingency Staffing Procurements Risk Management CD-2 Requirements Summary

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.3 LUSI Project Philosophy LUSI is a “Major Item of Equipment “ (MIE) Project delivering three LCLS scientific instruments Utilizes Integrated Project Teams and matrixed engineering LUSI team “owns the plan” The P3/COBRA database is the sole source of the approved LUSI scope, cost and schedule work plan Plan the work … Work the plan”. Emphasis on meeting schedules/milestones Changes to the “plan” are approved through change control LUSI Project is integrated with the LCLS Directorate. Transparent organizational structure and configuration management Matrix supporting infrastructure from LCLS Directorate LUSI seeking industrial solutions LUSI utilizes MOUs with BNL (Detectors) and DESY (Split and Delay) LUSI identifies risks up-front (continuous over the project life)

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.4 LUSI Scope LUSI will deliver: Three X-ray scattering instruments XPP - X-ray Pump Probe CXI - Coherent X-ray Imaging XCS - X-ray Correlation Spectroscopy The instruments will be assembled entirely at SLAC using SLAC technical staff Project detailed scope is based on Value-managed decisions Advice from instrument teams LUSI will provide instruments producing groundbreaking science

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p LCLS LUSI HEDS Offset Monochromator Exp. Chamber Detector Beam Transport Near Experimental Hall Far Experimental Hall XPP XCSCXI AMO HEDS Part of LCLS Proposed External Funds SXR Proposed External Funds Project description (1) Mono X-ray Transport SXR

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.6 Project description (2) XPP WBS 1.2 LCLS AMO XCS Offset Monochromator WBS 1.5 X-ray transport tunnel (200 m) XCS WBS 1.4 HEDS CXI WBS 1.3 SXR imaging

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.7 Purpose of this review Baseline (CD-2) status review for: WBS 1.1 – Project Management WBS 1.2 – X-ray Pump Probe (XPP) instrument WBS 1.3 – Coherent X-ray Imaging (CXI) instrument WBS 1.4 – X-ray Correlation Spectroscopy (XCS) instrument WBS 1.5 – Diagnostics and Common Optics WBS 1.6 – Controls and Data Acquisition WBS 2.0 – Other Project Costs (Spent) Independent Cost Review per DOE O (Part of this review)

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.8 LUSI WBS Organization WBSTITLE 1.1PROJECT MANAGEMENT ES&H Project Management Technical Support WBSTITLE 1.2X-RAY PUMP PROBE (XPP) XPP System Integration & Design XPP X-ray Optics & Support Table XPP Laser System XPP Detector System (BNL) XPP Sample Environment & Diffractometer System XPP Facilities XPP Vacuum System XPP Installation Product-based Components Coordination & Integration Installation Typical Instrument WBS

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.9 DOE-HQ H. Kung, Acquisition Executive T.E. Kiess, Program Manager DOE-SSO H. Joma DOE Federal Project Director SLAC T. Fornek LUSI Project Manager Deputy - TBD WBS 1.2 XPP IIT D. Fritz (Instr. Scientist) J. Langton ( Lead Eng) WBS 1.3 CXI IIT S. Boutet (Instr. Scientist) P. Montanez ( Lead Eng) WBS 1.4 XCS IIT A. Robert (Instr. Scientist) E. Bong - Acting (Lead Eng) WBS 1.5 Diagnostics & Common Optics Y. Feng (Lead Scientist) E. Ortiz (Lead Eng ) Instrument Team Leaders (Advisory) DOE-SSO Support WBS 1.6 Data Acquisition & Controls G. Haller (Lead) LCLS Directorate Support ES&H, QA, Finance, EVMS, Procurement… Engineering N. Kurita - Chief Engineer Technical Configuration Control Committee (Scope Decisions) LUSI Integrated Project Team

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.10 Typical Integrated Instrument Team WBS 1.2 X-ray Pump Probe Instrument Scientist – D. Fritz Lead Engineer (CAM) - J. Langton Eng/Design Support –J. DeLor J. Defever Detectors-N. van Bakel Diag./Common Optics – Y. Feng Controls & DAQ – G. Haller ES&H – M. Scharfenstein QA – D. Marsh Instrument Team Leaders Sign Off on Instrument Physics Requirements Document Instrument Team Leaders K. Gaffney, D. Reis, T. Tschentscher, J. Larsson

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.11 LCLS Directorate Support Business Services – C. Lowe (mgr), W. Sisson (Finance), F. Fernandez, (Project Controls), D. Pindroh, (Procurement) Michael Scharfenstein, ES&H Representative Darren Marsh, QA Representative Helen O’Donnell, Office Management Siony Matni, Administrative and Finance Mechanical Engineering Niels van Bakel – Detectors

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.12 Baseline Development Process Define initial schedule and budget assumptions Initial scope assumptions, WBS, WBS dictionary Responsibility assignment and organization Generate the schedule baseline estimate Finalize the Milestone Hierarchy and Dictionary, schedule activities, links, etc. Load resources Generate the resource loaded schedule Compare to funding profile Iterate until scope, schedule, costs match yearly funding, stakeholder requirements and good management practice Major driver is early science for the instruments

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.13 LUSI Cost Baseline Base Cost (BCWS)$42.13 M Contingency$12.97 M TEC$55.10 M OPC$4.90 M TPC$60.00 M

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.14 LUSI Project Funding Profile LUSI Funding Profile (AYM$) Prior Yrs FY07FY08FY09FY10FY11FY12Total MIE OPC Total

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.15 BA Plan & Obligation Profile Assumed BA Profile 08 Q1 08 Q2 08 Q3 08 Q4 09 Q1 09 Q2 09 Q3 09 Q4 10 Q1 10 Q2 10 Q3 10 Q4 11 Q1 11 Q2 11 Q3 11 Q4 12 Q1 12 Q2 12 Q3 12 Q4.5M6.5 M 8.0 M 9.5 M 21. 5M 40. 5M 50. 5M 55. 1M LUSI is funding- limited in Q1,Q2 of FY09.

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.16 LUSI Resource Loaded Schedule The LUSI resource-loaded schedule comprises ~3,900 tasks. 64 Control Accounts LUSI uses Primavera (P3) as its scheduling tool with COBRA as the cost processor. SLAC has successfully delivered with P3/COBRA (PEP-II, GLAST, SPEAR-III, LCLS). Significant supporting documentation for LUSI base costs.. A WBS Dictionary defines the scope of work at the lowest WBS level (typically Level 4/5). Contingency is assessed at the lowest WBS. Design Maturity & Judgment Factor (risk-based) Work schedule, commitments and resource profiles are derived from the resource-loaded schedule.

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.17 Critical Decision Milestones CD-0 - Mission Need - Approved Aug 2005 CD-1 - Alternative Selection and Cost Range – App’d Sep 2007 CD-2 - Approve Performance Baseline - planned Oct 2008 Utilize Phased CD-3 and CD-4 Milestones CD-3 - Approve Start of Construction CD-3A – XPP - scheduled Jul 2009 CD-3B – CXI - scheduled Apr 2010 CD-3C – XCS - scheduled Oct 2010 CD-4 - Approve Start of Operations CD-4A – XPP - scheduled Dec 2010 CD-4B – CXI - scheduled Sep 2011 CD-4C – XCS - scheduled Aug 2012 Baseline assumes long lead procurement approval for XPP and CXI received by November, 2008 These are baseline dates. Funding profile prevents combining CD-3s – We are trying to obtain earlier funding Early science begins with separate CD-4A, CD-4B

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.18 Key Cost/Schedule Assumptions Schedule Six month Continuing Resolution in FY 2009 Staffing can be secured to meet schedule requirements LCLS milestone dates for LUSI tie-ins are met Cost Six month continuing resolution in FY 2009 Three month continuing resolution in succeeding years Escalation rates used are 2.3% non-labor and 4% labor.

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.19 LUSI Project Summary Schedule

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.20 Schedule Contingency Float XPP – 75 working days to CD-4A CXI – 95 working days to CD-4B XCS – 80 working days to CD-4C (No funding constraints days) Critical Path XPP Diffractometer design, fabrication & installation CXI 1 micron K-B mirror system XCS Delayed design effort due to funding Diagnostic and common optics components delayed procurements Component assembly and installation

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.21 Project Contingency “Bottoms-up” contingency estimate $11.3M on $39.22M ETC Available contingency in proposed baseline is $12.8 Contingency is managed at the project level Annual comprehensive ETC and contingency update

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.22 Staffing (FTE) Plan for staffing ramp-up 1.AMO & other LCLS Engineers available to LUSI in September (~5 FTE) 2.Seeking Deputy Project Manager

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.23 Control Account Managers WBSControl Account MgrCntrl Accts Work Pkgs Budget 1.1 PMT. Fornek (Acting)612$5.5M 1.2 XPPJ. Langton (WO Detect)1044$4.5M 1.3 CXIP. Montanez1145$9.5M 1.4 XCSE. Bong (WO Detect)1241$5.7M 1.5 D&COE. Ortiz1039$6.4M 1.6 Cntrls & DAQ G. Haller20289$7.2M Detectors N. Van Bakel89$3.5M

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.24 LUSI Procurement Planning LUSI employs established SLAC procurement procedures LUSI uses the LCLS procurement cell Weekly LCLS/LUSI procurement status meeting with David Pindroh, LCLS Procurement LUSI Advanced Procurement Plans exist

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.25 Procurements

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.26 Long Lead & Major Procurements Long Lead Procurements XPP Diffractometer/Detector Mover Components $ 730K CXI 1.0 Micron KB Mirror System $ 970K Other Major Procurements CXI 0.1 Micron KB Mirror System $ 970K XCS Diffractometer System $ 517K XCS Detector Mover $ 689K Large Offset Monochromator $1,160K XPP Ti-Sapphire Power Amplifier $ 245K

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.27 LUSI MOUs Brookhaven National Laboratory – Detector Systems for XPP and XCS Instruments ETC - $1.1M XPP Detector System: Estimated Delivery – January, 2010 Cost to date $1.8M (OPC) XCS Detector System: Estimated Delivery – September, 2011 Estimated Cost – $1.8M DESY Split and Delay System Long-Term Loan arrangement

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.28 Risk Management LUSI Follows the LCLS Risk Management Plan and uses the LCLS Risk Registry LCLS Project Management Document Risk is considered in cost contingency Risk identification, assessment and mitigation First risk registry update meeting July 31, 2008 Major Risks Annual funding - Continuing Resolutions Foreign procurements – Dollar fluctuation, sole source Loss and/or availability of critical personnel CXI mirror delivery, performance XCS Monochromator performance

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.29 DOE 413.3A CD2 Requirements Established Perfomance Baseline Completed – Includes Key Performance Parameters Updated Project Execution Plan Ready for signature pending CD-2 Comments ANSI/EIA-748-A-1998 Compliant EVMS SLAC EVMS certified Independent Project Review/Cost Review EIR lines of inquiry will be addressed by this CD-2 Review The Quality Assurance Program must fully address all applicable Quality Assurance Criteria as defined in 10 CFR 830 Subpart A and DOE O 414.1C. SLAC Document PM R0 released in July ’07. Consistent with DOE Order 414.1C and the SLAC Office of Assurance “Quality Implemention Procedure Requirements “SLAC-I-770-0A17S-001-R000”

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.30 DOE 413.3A CD2 Requirements Prepare a Preliminary Design Completed Conduct a Preliminary Design Review Completed for XPP, CXI and XCS Hazards Analysis Report Completed (PM R0) Update the Preliminary Security Vulnerability Assessment Report. CD-1 report still valid

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.31 EIR Lines of Inquiry EIR ELEMENTCOMMENTCD2 Ready 1. Work Breakdown StructurePM (Structure) 2. Project Cost & Res Loaded SchedThis presentation & Project Controls/EVMS presentation 3. Key Proj Cost & Sched AssumpThis presentation 4. Critical PathProject Controls/EVMS presentation 5. Risk ManagementThis presentation and Management breakout 6. Funding ProfileThis presentation 7. Project Controls/EVMSProject Controls/EVMS presentation 8. Basis of DesignEngineering presentation 9. Design ReviewEngineering presentation 10. System Functions & ReqsEngineering presentation 11. SustainabilityNot applicable 12. Hazards AnalysisPM Value Management/EngineeringLUSI Value Management Plan (Doc No. PM ) 14. Start-up Test PlanSP , -16, -17 (XPP, CXI, XCS) 15. Project Execution PlanDraft ready for signature pending CD-2 review changes 16. Acquisition StrategyApproved September, Integrated Project TeamThis presentation & the PEP

Tom Fornek LUSI DOE Review August 19, 2008 Management Overview p.32 In Conclusion Project Cost, Schedule and Scope Baselines are in Place and Fit the Funding Profile Integrated Project Team is in Place Risks are Identified and Steps Have Been Taken to Reduce Risk Where Possible Contingency is Reasonable LUSI is ready for CD-2