Mitglied der Helmholtz-Gemeinschaft ESS cold and thermal Moderators Moderator & Reflector System Project Introduction Meeting 2015-08-19 | Yannick Beßler,

Slides:



Advertisements
Similar presentations
19th – 20th of September 2007Cryogenic Expert Meeting at GSI, Jan Patrick Meier1/11 Cryogenic Experts Meeting at GSI, 2007 The SIS 100 Cryogenic Jumper.
Advertisements

Manchester 09/sept/2008A.Falou & P.Cornebise {LAL-Orsay}1 CALICE Meeting/ Manchester Sept 2008 SLAB Integration & Thermal Measurements.
ATD Assembly. ATD Assembly #1 Dewar Assembly #1 Status: Dewar has been completely assembled and vacuum tested. No vacuum leaks were detected on the outer.
The Current T2K Beam Window Design and Upgrade Potential Oxford-Princeton Targetry Workshop Princeton, Nov 2008 Matt Rooney.
N. Dhanaraj, Y. Orlov, R. Wands Thermal-Stress Analysis of CC1 Space Frame.
AMS-02 Cryosystem Phase III Flight Safety Review January 12, 2010 Phil Mott.
SSRF1 ALUMINUM ALLOY VACUUM CHAMBERS FOR SSRF L.X. Yin, D.K. Jiang, H.W. Du, X.L. Jiang SSRF Vacuum Group Shanghai National Synchrotron Radiation Center.
Michael Butzek, Jörg Wolters, Bernhard Laatsch Mitglied der Helmholtz-Gemeinschaft Proton beam window for High Power Target Application 4th.
Background to the current problem 1. As a result of the high stresses in the bobbin due to the magnet load, the bobbin end plate needs to be increased.
MICE Hydrogen System Implementation Tom Bradshaw Elwyn Baynham Iouri Ivaniouchenkov Jim Rochford.
CRYO PIPING & INTER-MODULE CONNECTIONS Yun He, Daniel Sabol, Joe Conway External Review of MLC Daniel Sabol, MLC External Review 10/3/2012.
1 RF-Structures Mock-Up FEA Assembly Tooling V. Soldatov, F. Rossi, R. Raatikainen
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe MLC external review October 03, 2012.
1 Cryostat assembly, integration and commissioning procedures M.Olcese Version: 07 May 2008.
INTRODUCTION Definition:
Dec. 4, 2001 CERN-1 Hans de Vries VELO Mechanics  RF/vacuum foil  Rectangular bellow  Wake field suppressors  Cabling Summary & Outlook VELO mechanical.
Pixel Support Tube Requirements and Interfaces M.Olcese PST CDR: CERN Oct. 17th 2001.
Calorimeter Analysis Tasks, July 2014 Revision B January 22, 2015.
24 January 2014 LARP VTF Follow-up Meeting P. Kovach VTF 1 LARP Vertical Test Facility Vertical Dewar Design, Magnet Prep And Installation Paul Kovach.
Mitglied der Helmholtz-Gemeinschaft TIK 3.1 Moderator & Reflector System TAC Meeting 15. October 2015 | Yannick Beßler (FZJ), Daniel Lyngh (ESSS)
Brookhaven - fermilab - berkeley US LHC ACCELERATOR PROJECT LHC IRQ Inner Triplet Review Q1, Q2, and Q3 Mechanics T. Nicol April 24-25, 2007.
WP 12.3 Moderator & Reflector Systems D. Lyngh, M. Kickulies, J. Ringnér, J. Jurns, Y. Bessler (FZJ), M. Klaus (TUD), H. Quack (TUD) TAC12 Presenters:
56 MHz SRF Cavity Cryostat support system and Shielding C. Pai
56 MHz SRF Cavity Thermal Analysis and Vacuum Chamber Strength C. Pai
Progress on Remote Handling Systems TAC 12 Magnus Göhran – WPM 15 th October 2015.
SCH Controls Readiness Review- Cryostat Nov 4-5, 2015 Kurt Cantrell.
TIK 3.1 Moderator & Reflector System
Mitglied der Helmholtz-Gemeinschaft Twister 15. Januar Shaft Moderators & Reflectors Radial Bearing Axial Bearing Target Rotation and lifting device.
Update on Micro Channel Cooling Collaboration Meeting , G. Nüßle.
Mitglied der Helmholtz-Gemeinschaft Jörg Wolters, Michael Butzek Focused Cross Flow LBE Target for ESS 4th HPTW, Malmö, 3 May 2011.
Cavity support scheme options Thomas Jones 25/06/15 1.
Alignment and assembling of the cryomodule Yun He, James Sears, Matthias Liepe.
DON LYNCH NOVEMBER 6, AGENDA November 4, BABAR Magnet Update Global Design Concept – Update Outer HCal Structural Analysis (2 nd pass) sPHENIX.
EMC BWE Proto18 - Orsay Meeting 1 PANDA EMC BWE Proto18 Mikel Catania Goikoetxea, Javier Navarro Medrano, David Rodríguez Piñeiro, Yue Ma, Frank.
CDR2 – Coupler Mechanical Design NICOLAS MISIARA.
Cooling Circuit Design Steve Virostek Lawrence Berkeley National Lab February 29, 2012 MICE Coupling Coil Cryostat Design Review Lawrence Berkeley National.
Rapid Change Technology The following is a presentation to aid Technicians in the replacement of the Rapid Change Technology Block.
Origami and Cooling 24th September 2012 C. Irmler (HEPHY Vienna) Joint PXD and SVD Meeting Göttingen.
Update on the ESS monolith design Rikard Linander Monolith and Handling Group ESS Target Division TAC 10, Lund, Nov 5,
Thermal screen of the cryostat Presented by Evgeny Koshurnikov, GSI, Darmstadt September 8, 2015 Joint Institute for Nuclear Research (Dubna)
High Energy Dump of the Super Proton Synchrotron at CERN – Present and Future designs A. Perillo-Marcone (EN-STI) Contributions from several colleagues.
Target Systems and Monolith Design Update Rikard Linander Group Leader Monolith and Handling April 2, 2014.
Engineering of the power prototype of the ESRF HOM damped cavity* V. Serrière, J. Jacob, A. Triantafyllou, A.K. Bandyopadhyay, L. Goirand, B. Ogier * This.
ROLLING Rolling is a process of reduction of the cross-sectional area or shaping a metal piece through the deformation caused by a pair of metal rolls.
SPS High Energy LSS5 Thermal contact & cooling aspects
The ESS Target Station Eric Pitcher Head of Target Division February 19, 2016.
WP 12.3 Moderator & Reflector Systems D. Lyngh, M. Kickulies, J. Ringnér, J. Jurns, M. Andersson, M. Pucilowski, T. Hedlund, A. Olsson TAC11 Lund, 1 st.
The ESS Target Station F. Mezei ESS target division NPPatLPS, 2013.
First Wall Panel - Overview
Panda Solenoid Content Interface Box Cold Mass Layout Cooling Lines
Ti/SS transitions A.Basti INFN-PISA*
Status of design and production of LEP connection cryostat
A. Vande Craen, C. Eymin, M. Moretti, D. Ramos CERN
PANDA Yoke of the Magnet
LARP Vertical Test Facility
Tracker Outer Barrel COOLING Antti Onnela, CERN.
rd IFHTSE Conference Hot Hydroforging of Lightweight Bimaterial Gears and Hollow Products Bulent Chavdar1, Robert Goldstein2, Lynn Ferguson3 1Eaton,
Design of Distribution Feedbox at LHC P7
ESS Target Cryogenic System European Cryogenic Days CERN
iSHELL Design Review Cryostat & Optics Bench
Welds in the magnet system
Target collaboratin Board Meeting
Cryomodule Assembly Plan
Neutron guide Shielding Concept
APTM and GRID interface requirement PBIP and PBW
Bunker Wall Design Wall ESS
UPPSALA UNIVERSITY_GERSEMI PROJECT
Work Unit AIK 11.2 CDR of the CDS-SL Mechanics
SNS PPU Cryomodule Space Frame
Overview of the TARGET Monolith Rough Vacuum
Presentation transcript:

Mitglied der Helmholtz-Gemeinschaft ESS cold and thermal Moderators Moderator & Reflector System Project Introduction Meeting | Yannick Beßler, Johannes Wolf, Petra Schumacher, Marc Hofmann, Jörg Wolters, Michael Butzek

Mitglied der Helmholtz-Gemeinschaft Updates current work Top cold Moderator from neutronic to real Modell Running weld tests (through welding) Weld test for Invar pipework Lower cold Moderator Manufacturing tests (th. Moderator disc Al6061-T6) Parameter study eBeam welding FEM simulation top cold Moderator Twister design optimization General questions (requirement ESS ) RCC-MRx??? Contents 29. Januar

Mitglied der Helmholtz-Gemeinschaft 29. Januar BF2.1 PDR ModelBF2.2 + holding structureBF2.3 + cover Full contact with FG and outer surface Necessary because Stress locally>84 MPa Including fluid guide structure (FG) From neutronic Modell to real Modell

Mitglied der Helmholtz-Gemeinschaft 29. Januar BF2.4 with real contact surface FG contact with cover (1,5 mm) shown in red are the real contact surfaces thickness FG 2mm / real contact mm thickness cover (weld area) 1.5 mm for eBeam power reduction in order to keep as much as possible T6 conditions run-in and out length (<10 mm) is necessary for the eBeam in order to reduce burn out risk From neutronic Modell to real Modell Reducing thickness of the cover Real contact

Mitglied der Helmholtz-Gemeinschaft 29. Januar Grooves for filler BF2.5 with filler (AlSi12) Because heat crack risk! Increasing of Si content is necessary (see weld report DUP) Welding from the inside with beam deflection (mirror system) From neutronic Modell to real Modell

Mitglied der Helmholtz-Gemeinschaft 29. Januar upper moderator pipework space for welding 40 mm space necessary for connecting the pipework

Mitglied der Helmholtz-Gemeinschaft 29. Januar Running weld tests (through welding)

Mitglied der Helmholtz-Gemeinschaft Through welding test 29. Januar Groove for filler (AlSi12) Beam power reduction

Mitglied der Helmholtz-Gemeinschaft Weld test for Invar pipework 29. Januar  Filler = base material! for low temperature applications

Mitglied der Helmholtz-Gemeinschaft Lower cold Moderator 29. Januar First simulation model ready!

Mitglied der Helmholtz-Gemeinschaft Manufacturing tests (th. Moderator disc Al6061-T6) 29. Januar There are no significant deformation during machining! at the used time-consuming and expensive machining type Background: the tempering process create additional inner stress. This stress could deform the structure during machining….

Mitglied der Helmholtz-Gemeinschaft 29. Januar

Mitglied der Helmholtz-Gemeinschaft Parameter study eBeam welding 29. Januar ,6 1,5 4 “Top plate” “Vessel”

Mitglied der Helmholtz-Gemeinschaft 29. Januar BF2.1 PDR Model BF2.2 + holding structureBF2.3 + cover FEM simulation top cold Moderator

Mitglied der Helmholtz-Gemeinschaft FEM simulation top cold Moderator 29. Januar BF2.4 with real contact surface

Mitglied der Helmholtz-Gemeinschaft  Twister handling and bearing  Twister shielding  LH2 pipework 29. Januar Potential for optimization

Mitglied der Helmholtz-Gemeinschaft 29. Januar Twister handlding and bearing additional sliding and handling device is required empty pit with radial bearing flange final alignment, shielding completely mounted

Mitglied der Helmholtz-Gemeinschaft 29. Januar Twister handling and bearing contact / spring insert axial bearing

Mitglied der Helmholtz-Gemeinschaft 29. Januar Twister handlding and bearing 6 radial bolts lifting device bayonet, gearing bubble level 4 lifting shafts

Mitglied der Helmholtz-Gemeinschaft 29. Januar Twister shielding 2,5 internal gap 30 internal step 30 external step 5 external gap milled shaft welded tubes shielding stone milled groove

Mitglied der Helmholtz-Gemeinschaft 29. Januar LH2 pipework interface plate, H 2 O, vacuum

Mitglied der Helmholtz-Gemeinschaft The MR Plugs are cooled by water and liquid hydrogen. Water and hydrogen will get activated when passing through. The MR Plugs shall be tight and confine the radioactive water and hydrogen inventory The MR Plugs will be leak controlled and monitored The total weight of the MR Plugs and MR Plugs Structure shall be 5,5 t or less p.H2O=4 bar / p.H2O.Design=5 bar SS / 304L (X2CrNi19-11) or better (<10dpa) Materials Handbook 316LN or 316L (<7,5dpa) MR Plug reliability 0,9997 and availability 0,99???  361 d/y??? A new set of top and bottom MR Plugs and MR Plugs Structure shall be available. General questions (requirement ESS ) 29. Januar

Mitglied der Helmholtz-Gemeinschaft basic material still is equivalent to 3.1 The main difference during manufacture stamped by extern (3.2) during manufacture stamped by internal authorized (3.1)  With 3.2 we lose a lot of important time! 3.2 certificate versus 3.1 certificate 29. Januar

Mitglied der Helmholtz-Gemeinschaft Heat Deposition File (top plug only) 29. Januar Top Plug RCC Modell real Modell comment Cell IDMaterialDensityVolumeErrorHeatingErrorHeat densityVolumeHeatingdeltaQ [-] [g/cm3][cm3] [W] [W/cm³][cm3][W] 80001Hydrogen0,07530,178,141519,350,302,87494,471417,03-102,31without pipes! 80002Cryo-Al2,73163,572,401655,310,6610,12193,301956,16300,86without pipes! 80003Void0,00323,194,190, Al2,70225,552,862120,670,859, Hydrogen0,07530,178,141499,370,302,83494,471398,40-100,97without pipes! 80006Cryo-Al2,73163,572,401148,750,467,02193,301357,54208,79without pipes! 80007Void0,00323,194,190, Al2,70225,552,861479,940,446, Water1,00565,737,924761,580,958,42 Plus Heat Vakuummantel (Teil) 80010Al2,7066,611,31490,400,347, Water1,00716,9910,573745,651,505, Al2,7093,501,71563,800,456, Water1,00716,9910,572216,290,663,09 real LH2/Valuum/Al/H2O 80014Al2,7093,501,71254,670,152, Water1,008362,0441, ,255,486, Al2,701589,628,277885,081,584, Water1,001168,8910,055842,580,585, Al2,70549,184,672727,400,554, Void0,0099,521,630,00 wo zu???? 80020Al2,70449,653,822096,470,634, Be+Water1, ,63239, ,7510,811, Al2,703343,7512,374747,700,951,42 realTop cold Moderators 6,13[kW]without pipes! RCC Mo. Top th, Modertor 86,90[kW] Vorsicht Reflektor/th Modertor gleiche Wand oben RCC Mo. Top Be Reflector 114,97[kW]

Mitglied der Helmholtz-Gemeinschaft Backup Design / operating Pressure…… 29. Januar

Mitglied der Helmholtz-Gemeinschaft RCC-MRx 29. Januar ??????????????????? RCC-MRx training in Jülich!