VINES & LOW GROWING GROUNDCOVERS: OVERLOOKED RESTORATION TECHNIQUES.

Slides:



Advertisements
Similar presentations
BANK EROSION PINS.
Advertisements

NITROGEN & PHOSPHORUS REMOVAL FROM SHALLOW GROUNDWATER.
Soil-choked Riprap covered with Erosion Control Blanket (ECB), & planted with native trees & shrubs through the ECB.
DINGMANS CREEK RIGHT BANK RIPARIAN VEGETATION PLANTINGS, WITH SOME SOIL CHOKE & PLANTING OF EXISTING Rt. 209 DELAWARE WATER GAP NATIONAL RECREATION.
MONKEY RUN, ARCADE, NY. HISTORIC RAILROAD PROTECTION & DEMONSTRATION PROJECT, 41 METHODS AND TECHNIQUES IN COMBINATION.
Bioengineering & “Funnel” Strategy Nichols Road Bridge, Onondaga Creek, NY A completed project needed some “tweaking” and veg. Top bank stone.
ONONDAGA CREEK, NEAR SYRACUSE, NY. SITE 5-D & OTHER REACHES {Engineered Rocked Riffles (with all stones in compression), Traffic Control Stones, LPSTP,
WAYNE KINNEY’S REALLY TALL ENGINEERED ROCKED RIFFLES (ERR) CASE STUDY: ERR #12, WHICH IS A 4.7 FT TALL STRUCTURE.
SAND THE FOOT OF KANOPOLIS DAM, KANSAS Let’s build Engineered Rocked Riffle #5 the most upstream of the five riffles that will be constructed.
Irish Gulf, Boston, NY  Vertical eroding banks  Urban  Pool-riffle-pool regime  Gravel-cobble bed stream  Small stream (average width 30 ft, 10 ft.
BUSTING MYTHS. BUSTING MYTHS ADVENTITIOUS ROOTING PLANTS CANNOT BE PLANTED DEEP Onondaga Nichol Road Bridge, Lafayette, NY.
GRADE CONTROL. STABILIZE HEADCUTS FIRST, THEN WORRY ABOUT BANK INSTABILITY SECOND.
DINGMANS CREEK, SITE 4, SMALL SLIDE, DELAWARE WATER GAP PROJECT VEGETATED KEYS; TRAFFIC CONTROL STONES; PLANTINGS; SINGLE STONE BENDWAY WEIRS; & A RANDOM.
ACCOTINK AIRFIELD RUNWAY & RECHLORINATION PLANT PROJECTS GARRISON FORT BELVOIR, FAIRFAX, VA CONSTRUCTED Dec 2-5, 2008.
THE ENGINEERED FLOODPLAIN BENCH. Conceptually, for an incised system you can: raise the stream, lower the floodplain, or a little of both Lower either.
Check out the bingo sign! CAZENOVIA STEPHENSON ST. BRIDGE.
TRADITIONAL WINDROW & TRENCH-FILL REVETMENTS, & A NEW INVENTION, VEGETATED TRENCH-FILL REVETMENT {All 3 are classified as “Setback Revetments”}
SITE 6 – DELAWARE RIVER RIGHT BANK BLOW-OUT UP THE HILL FROM THE DELAWARE RIVER (SWIRLING RIVER EROSION & GROUNDWATER PIPING) DELAWARE WATER GAP NATIONAL.
BEE–WARE OF THE BEES-ELTON 7 BRIDGE Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007.
GOODWIN MCBRIDE PROPERTY, NEAR BATESVILLE, MS. CONSTRUCTED FEB 26 - MAR 2, 2007 The final design was based on the landowner’s required stream and.
OSBORNE HOLLOW CREEK ROAD PROTECTION PROJECT. Gravel-Cobble Bed Stream – Rural, Pool-Riffle-Pool, Stream Slope 2-3% Goals: Halt bank erosion to protect.
ONONDAGA CREEK, NEAR SYRACUSE, NY. SITE 5-D & OTHER REACHES {Engineered Rocked Riffles (with all stones in compression), Traffic Control Stones, LPSTP,
STONES DRILLED & PINNED TO BEDROCK WITH METAL RODS (Two case studies) by Dave Derrick.
The Slit Brush Layering Method. THIS METHOD IS A DAVE DERRICK DISCOVERY (DDD)
LOCKED LOGS (LL). THIS METHOD IS A DAVE DERRICK DISCOVERY (DDD)
Sulphur Dunnigan Burn Dump, Yolo County, CA. (30 miles north of Sacramento, CA.) BUILT 1998.
AT-GRADE, HINGED, & UNDERGROUND GRADE CONTROL. AT-GRADE & HINGED GRADE CONTROL STRUCTURE ON HICKAHALLA CREEK NEAR SENATOBIA, MS. Constructed in 1989 to.
Check out the bingo sign! CAZENOVIA STEPHENSON ST. BRIDGE.
RANDOM BOULDER FIELDS {RBF} (For bank protection) 2 EXAMPLES
Check out the bingo sign! CAZENOVIA STEPHENSON ST. BRIDGE.
ICE DAMAGE REDUCTION PROJECT- CHAUTAUQUA MOUTH (LAKE ERIE) WESTFIELD, NY Pix by Dave Spann.
STONES IN COMPRESSION – BOTH NATURALLY & MACHINE PLACED by Dave Derrick.
MISSOURI RIVER INNOVATIVE BANK STABILIZATION & AQUATIC & RIPARIAN HABITAT LEWIS & CLARK REGIONAL WATER SYSTEM, VERMILLION, SD.
CASE STUDY- West Fork Beaver River, West Point, OH. Constructed Sept
West Fork Beaver River, West Point, OH. Constructed Sept Minimal height Bendway Weirs in a gravel-cobble-sand-silt bed stream for thalweg realignment.
DUCK CREEK EAST OF EASTERN AVENUE DAMAGED BY THE BIG RAIN ON JUNE 12, 2008 (7 inches in an hour, Q-75 year flow) PROJECT CONSTRUCTED BY CITY OF DAVINPORT,
Sulphur Dunnigan Burn Dump, Yolo County, CA. (30 miles north of Sacramento, CA.) BUILT 1998.
SINGLE STONE BENDWAY WEIRS
Big Pipeline Crossing Protection Project for Williams on the Guadalupe River, South of Victoria, TX. (near the harbor) 1.3 Million Dollars Took 3 crews.
BW - CHAPTER 14: CASE STUDY- NEOSHO RIVER, ALLEN COUNTY, (MIKE GEFFERT’S PROPERTY) SOUTHEAST KANSAS Constructed May-July 2000 Using Bendway Weirs for thalweg.
DEAD DIKES. DEAD DIKES USING DEAD POSTS IS A DAVE DERRICK DISCOVERY (DDD)
HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE ROAD,
Check out the bingo sign! CAZENOVIA STEPHENSON ST. BRIDGE.
Check out the bingo sign! CAZENOVIA STEPHENSON ST. BRIDGE.
River Research & Design, Inc.
Bioengineering & “Funnel” Strategy Nichols Road Bridge, Onondaga Creek, NY A completed project needed some “tweaking” and veg. Top bank stone.
HAW CREEK, PIKE COUNTY, MISSOURI-TRIB TO SALT RIVER ERODING STREAM THREATHENING COUNTY ROAD #107, FOURTEEN FT TALL ERODING BANK WITHIN 4 FT OF THE ROAD,
NYS-DOT REGION 6 ROAD PROTECTION FOR ROUTE 248 CHENUNDA CREEK, SOUTH OF WELLSVILLE, NY. CONSTRUCTED AS A HANDS-ON WORKSHOP SEPTEMBER 2006.
CASE STUDY:Grand River at Route “A” 100 miles north of Kansas City, MO. Constructed June 2001 False Banklines using LPSTP (medium-sized river)
GRADE CONTROL: the VIFFLE {Combo of the cross- Vane & rocked rIFFLE}
McKinstry Creek NYS DOT Mitigation Project STREAM & RIPARIAN COORIDOR RESTORATION, WETLAND REWETTING, VERNAL POOLS, “RPM” PLANT EXPERIMENTAL TEST PLOTS,
Check out the bingo sign! CAZENOVIA STEPHENSON ST. BRIDGE.
DINGMANS CREEK, SITE 4, SMALL SLIDE, DELAWARE WATER GAP PROJECT VEGETATED KEYS; TRAFFIC CONTROL STONES; PLANTINGS; SINGLE STONE BENDWAY WEIRS; & A RANDOM.
BUSTING MYTHS VEGETATION TAKES A LONG TIME TO GET ESTABLISHED GOODWIN CREEK, MS. CONSTRUCTED AS A HANDS-ON WORKSHOP, MARCH 2007.
BEE–WARE OF THE BEES-ELTON 7 BRIDGE Under construction-Elton Creek DS of Freedom 7 Bridge-derrick-Oct 2007.
Half-Drowned Bushes with Traffic Control Stones & additional plantings.
ELTON CREEK, DS OF FREEDOM 7 BRIDGE, FREEDOM, NY. Bank erosion is threatening a farm road NRCS –Environmental Quality Incentives Program {EQIP} cost share.
GOODWIN WARNER MCBRIDE PROPERTY, NEAR BATESVILLE, MS. CONSTRUCTED FEB 26 – MAR 2, 2007 The final design was based on the landowner’s required stream.
Headcut gets taller & ACM mat flips out of the upstream key trench of the downstream pipe crossing, which causes problems. Project.
GRADE CONTROL.
WAYNE KINNEY’S REALLY TALL ENGINEERED ROCKED RIFFLES (ERR) CASE STUDY: ERR #12, WHICH IS A 4.7 FT TALL STRUCTURE.
ONONDAGA CREEK, NEAR SYRACUSE, NY
VINES – THE OVERLOOKED RESTORATION TECHNIQUE
CASE STUDY- West Fork Beaver River, West Point, OH. Constructed Sept
When should you fix a stream????
SINGLE STONE BENDWAY WEIRS
VEGETATION DOES NOT TAKE A LONG TIME TO GET ESTABLISHED GOODWIN CREEK, MS. CONSTRUCTED AS A HANDS-ON WORKSHOP, MARCH 2007.
When should you fix a stream????
DINGMANS CREEK, SITE 4, SMALL SLIDE, DELAWARE WATER GAP PROJECT VEGETATED KEYS; TRAFFIC CONTROL STONES; PLANTINGS; SINGLE STONE BENDWAY.
Guadalupe Williams Pipeline Crossing, South of Victoria, TX
Presentation transcript:

VINES & LOW GROWING GROUNDCOVERS: OVERLOOKED RESTORATION TECHNIQUES

THESE METHODS ARE DAVE DERRICK DISCOVERIES (DDD)

SITE 2-A: BANK STABILIZATION TO PROTECT STATE HIGHWAY RT. 209, BUSHKILL, PA. DELAWARE WATER GAP NATIONAL RECREATION AREA NATIONAL PARK SERVICE PROJECT CONSTRUCTED SEPTEMBER 14-26, 2009

WILDLIFE ON SITE !! His twin had just crossed. Derrick scared this one by yelling “BEAR”... CONSTRUCTION BUSHKILL CR-SITE 2-A PIX BY DERRICK

VINES – THE OVERLOOKED RESTORATION TECHNIQUE Use vines for aesthetics, habitat, & temperature mitigation (reduction in thermal heat transfer from stone structures). For this project a 9 inch long cutting of Virginia Creeper was planted every 5 ft along the top of an existing stone wall.

1 YEAR BW #7 & great first year growth of Virginia Creeper on stacked stone wall. 1 YEAR LATER-BUSHKILL CR-SITE 2-A - DERRICK

1 YEAR LATER-Looking planted Virginia Creeper vines on stacked stone wall. Great vine growth for first year 1 YEAR LATER-BUSHKILL CR-SITE 2-A - DERRICK

1 YEAR LATER-Close-up of vines on stone wall. 1 YEAR LATER-BUSHKILL CR-SITE 2-A - DERRICK

CHAUTAUQUA CREEK ICE DAMAGE REDUCTION PROJECT –Near its Lake Erie WESTFIELD, NY  Severe scour from ice and high flow velocities on the right descending bank had resulted in an overwidened section of stream.  Catskill Sand Cherry planted 3 years ago  Under water & under ice every winter.  Some examples growing 12 to 14 ft above base flow water surface elevation  Needs full sun

Catskill Sand Cherry growing well, covered with ice all winter, growing ft above base flow. 3 YEARS AFTER PLANTING-CHAUTAUQUA CR.-JOE GALATI

Mid & Upper bank vegetation growing well Pix by Derrick - 8/23/2006 TreesNo protection, 2 rows of shrubs Riprap with grasses Square cut stone with willow & dogwood whips Sheetpile

Vines & some veg growing amongst large toe stone 3YRS 1 MONTH AFTER-CAZENOVIA STEVENSON ST-DERRICK

3 YEARS & 1 MONTH AFTER PROJECT COMPLETION Photos By Derrick JUNE 12, 2009

Looking left bank. Nice species diversity of plants. 3YRS 1 MONTH AFTER-CAZENOVIA STEVENSON ST-DERRICK

Close up of robust mid & upper bank veg. 3YRS 1 MONTH AFTER-CAZENOVIA STEVENSON ST-DERRICK

4.66 YEARS AFTER PROJECT COMPLETION Photos by Derrick JUNE 16, 2010

4.66 YRS LATER-CAZENOVIA STEVENSON ST-DERRICK years after completion. From the bridge looking DS. Except for narrow band of stone at toe, dense veg has covered the entire bank.

4.66 YRS LATER-CAZENOVIA STEVENSON ST-DERRICK years after completion. From the bridge looking DS. Good diversity of plant species with some volunteer plants (Cottonwood, Black Locust, herbacious, some invasive Japanese Knotweed).

4.66 YRS LATER-CAZENOVIA STEVENSON ST-DERRICK years after completion. From the bank looking DS. Willow is growing well in the riprap section.

4.66 YRS LATER-CAZENOVIA STEVENSON ST-DERRICK years after completion. Looking at top bank.

5 YEARS AFTER PROJECT COMPLETION Photos by Chuck Godfrey Feb. 18, 2011

5 YRS LATER-CAZ STEVENSON ST-CHUCK GODFREY YEARS AFTER PROJECT COMPLETION. Ice is back!! DOT closed the bridge for 2 days, concrete channel UGLY but OK.

5 YRS LATER-CAZ STEVENSON ST-CHUCK GODFREY YEARS AFTER PROJECT COMPLETION. Ice flowing around plants & pounding project, plants look OK!!!

This PowerPoint presentation was developed & built by Dave Derrick. Any questions or comments, call my personal , or Enjoy the information!!

Brothers separated at birth!!

Cleophus Speed Elvis Derrick, note ear on big paw to left This river engineering is really exciting stuff…