LHC Cryogenics HWC day 19 March 2009 Serge Claudet TE-CRG-OA (LHC Cryo OP)

Slides:



Advertisements
Similar presentations
LHC Cryogenics Status and Perspectives
Advertisements

Status of Cryogenics at point 4 following the power cut L. Tavian 20 August 2011.
Cryogenic system in P4: Possible options S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005 (Mostly for RF & beam scrubbing)
Going towards LHC Run2 CRYOGENICS 5 th Evian Workshop 2-4 June 2014 SESSION 4 - Systems 2 - Status and commissioning plans (HW perspective) Krzysztof Brodzinski.
A. Perin, CERN, TE-CRG, 26 May Review of the cryogenic by-pass for the LHC DS collimators 26 May 2011 Modifications to the DFBs, DSLC and cryogenic.
H. MAINAUD DURAND, A. HERTY, A. MARIN, M. ACAR PERMANENT MONITORING OF THE LHC LOW BETA TRIPLETS: LATEST RESULTS AND PERSPECTIVES.
Laurent Tavian Thanks to contribution and helpful discussions with M. Jimenez, V. Parma, F. Bertinelli, J.Ph. Tock, R. van weelderen, S. Claudet, A. Perin,
Workshop Accelerator Operation 2012, SLAC S. Claudet (CERN, Geneva) on behalf of the “Cryogenics Group” Technology Department Operation of the LHC Cryogenics.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
SC - 04Feb'13Cryo Heaters Review Cryogenic Heaters Review Operation use and wishes S. Claudet - A. Suraci LHC Cryogenic Operation.
Large-capacity Helium refrigeration : from state-of-the-art towards FCC reference solutions Francois Millet – March 2015.
CRYOGENICS AND POWERING
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
HC review - 12 May 2005Luigi SERIO - AT/ACR/OP1 SECTOR COOL DOWN AND CRYOGENIC COMMISSIONING L. Serio.
Workshop Chamonix XIV Shortcuts during installation and commissioning: risk and benefit H. Gruehagen, G. Riddone on behalf of the AT/ACR group 18 January.
LHC Cryogenics: “From cool-down & HWC to operation with beam” S. Claudet, for LHC cryogenics Extended LTC, 3 Mar’08.
How can we reduce the “no beam„ time? Walter Venturini Delsolaro D. Arnoult, S. Claudet, G. Cumer, K. Dahlerup Petersen, R. Denz, F. Duval, V. Montabonnet,
Introduction to LHC cryogenic system (layout, architecture) Preparation before cool-down (Purge, flushing) Transient operations to reach nominal operating.
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
André Augustinus 21 June 2004 DCS Workshop Detector DCS overview Status and Progress.
CERN plans towards energy efficiency Serge CLAUDET Nov 2014.
The HiLumi LHC Design Study is included in the High Luminosity LHC project and is partly funded by the European Commission within the Framework Programme.
S. Claudet - 31st May 2007Power refrigeration for LHC Power refrigeration at 4.5K & 1.8K for the LHC S. Claudet, CERN AT-ACR.
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
HC review, A. Perin, 12-MAY DFB Project LHC hardware commissioning review May 2005 Hardware commissioning of the DFBs and DSLs and connection.
L. Serio COPING WITH TRANSIENTS L. SERIO CERN, Geneva (Switzerland)
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
Process Definition of the Operation Modes for Super-FRS Magnet Testing CSCY - CrYogenic department in Common System, GSI, Darmstadt Y. Xiang, F. Wamers.
8 th November 07-OP Workshop Machine Checkout E. VEYRUNES CRYOGENICS 8 th November 2007 OP Workshop Machine Checkout E. VEYRUNES AB/OP 2008 AB/OP CRYO.
BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
Luigi Serio CRYOGENICS PERFORMANCE AND OPERATION L. Serio, on behalf of the LHC Cryogenics Operation and Cryogenics Performance Panel.
LHC Cryogenics for sector 45 and Perspectives S. Claudet, for LHC cryogenics HWC Review, 28 Fev’08.
Heat loads and cryogenics L.Tavian, D. Delikaris CERN, Cryogenics Group, Technology Department Accelerators & Technology Sector Friday, October 15, 20101HE-LHC'10.
AB/CO Review, Interlock team, 20 th September Interlock team – the AB/CO point of view M.Zerlauth, R.Harrison Powering Interlocks A common task.
SM18 cryogenics infrastructure upgrade L. Serio TE-CRG.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Can we change a magnet without warming-up a full arc ? Serge Claudet, With help from P. Cruikshank & J-P. Tock (Chamonix Jan’10)
Roberto Saban TS HC Review bis Outline  Interviews of all the Group Leaders loosely or tightly concerned by hardware commissioning proposing them.
An invitation to an open discussion We are team reviewing its performance globally We want to help each other to reach the objectives We know the other.
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
LHC Commissioning Status Gianluigi Arduini CERN – AB Department For… 23/10/20081LHC Commissioning Status - G. Arduini.
5-year operation experience with the 1.8 K refrigeration units of the LHC cryogenic system G. Ferlin, CERN Technology department Presented at CEC 2015.
LHC Cryogenics From cool-down to 1st beams Serge Claudet (LHC Cryo OP), On behalf of cryo teams involved.
LHC Cryogenics, equipment & interventions around P3/P7 S. Claudet, “volunteer” for TE_CRG 16 Oct’14.
Logo area HL LHC IT STRING M. Bajko CERN TE-TM and QXF Review.
Bruno Vullierme Sept LHC-CC09 - 3rd LHC Crab Cavity Workshop Slide 1 CRAB CAVITY INTEGRATION CRYOGENICS INSTALLATION.
The Large Hadron Collider The 19 th Sep 2008 incident [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] NIKHEF Seminar ( )
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Cryogenics Operations 2008, CERN, Geneva, Switzerland 1 CRYOGENICS OPERATIONS 2008 Organized by CERN Industrial contributions to the maintenance of CERN.
HL-LHC IT STRING and Series test of SC link
Cryo equipment strategy in the R2E context
Innovative He cycle Francois Millet.
Markus, Mathieu, Enrique, Rudiger, Serge
SPS cryogenic proximity equipment and SM18 validation
The LHC - Status Is COLD Is almost fully commissioned
CRYOGENICS – strategy, unavailability root causes and limitations
Coordination of Hardware Commissioning
Keeping LHC cold during LS periods Preliminary proposal
Hollow e- lens, Cryogenic aspects
Powering from short circuit tests up to nominal
TEST PLANS for HL LHC IT STRING
Summary Tuesday h23: Machine closed. Precycle started.
Guidelines defined early Dec 2012
Summary post TCC#54_02Aug’18
Review of hardware commissioning
Cryogenic management of the LHC Run 2 dynamic heat loads
Laurent Delprat CERN, Geneva, Switzerland
Presentation transcript:

LHC Cryogenics HWC day 19 March 2009 Serge Claudet TE-CRG-OA (LHC Cryo OP)

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Content Introduction: experience gained so far Consolidations and re-commissioning Calorimetry Organisation and staff matters Summary

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Christmas and water maintenance shut-down Short in connection cryostats and repairs Open Days Cooling sectors + Cryo tuning + Powering activities UX85 Ph1 works All sectors at nominal temperature Simultaneous Cryo start/maintain First beams around LHC 8 sectors - 8 months Tuning: ≈ 6 wks / sector

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 LHC Cryogenics: towards beams Target for global (8 sectors) “Cryo OK for Powering” UX85 Ph1 works Electrical Transformers Cool-down and commissioning (systems, instrumentation, logic) Beams !!! 19 Sept’08 Cryo conditions for 3 months of intense HWC

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 LHC Cryogenics: just after beams Target for 4 sectors tested with calorimetry A bit frustrating !!! 19 Sept’08 Switch EL network Rather good stability without specific efforts A dream for HWC w.r.t Spring’08 !!!

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Experience gained so far All cryo-subsystems were tuned and put into service (if it has worked once, it will come back) Procedures established and teams trained Weak points identified and consolidation programs established: –Already visible in 2008 for EL, CV, CO, Cryo –Continued since with many support teams

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Tuning LSS components Electrical Feed Boxes (DFBs): –We could operate all of them close to nominal conditions (maximum scenario required so far during HWC) –Few delicate cases (heat loads, levels measurements, levelling of sc link to magnets, valves for cooling current leads, thermometers and noise, High Voltage perturbation on instrumentation cards) Stand alone Magnets (SAM): –Difficult Level measurements due to Cold GHe capillary with too small diameter and possible low points, most delicate cases being treated Triplets: –DFBX: Commissionned with moderate ramp rates on some leads (Cu) –NC found on some Q1 (Missing Cu braid), being treated on critical cases in R1 and 5L Superconducting links (DSLs): –No problem encountered on four DSLs (<80m), except for DSLC_P3 –DSLC design/installation weak point being treated Might come back ! Nothing special expected for re- testing of Y-lines or DSLC

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Electrical feed boxes (DFB’s) QRL On-going work on valve positioners (and plugs ?) => Expected gain in stability - Rangeability of all valves tuned - Filters installed ahead of all valves => Effects already P8 Current leads control Filling valve

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Levels for stand-alone magnets 2008: Case by case lengthy tuning AND global QRL_line_D pressure stability required LSD0809: Pipe work being consolidated for most cases 2009: At least first sector to be re-assessed with complete boil-off tests, should become more straight forward once consolidation validated Reference: P6 already conform, due to specific design due to beam dump line Old small diameter capillary

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Calorimetry Operation: –Establish global stable conditions, with specific settings for cooling and filling valves –Almost on-line assessment of temperature drifts (mK/hr) mostly to validate the test or identify possible non-standard zones Analysis (off-line so far): –Evaluation of the power deposited in helium (internal energy) to define the total resistance of a cryo sub-sector, and by comparison quantify singularities. –Specific studies required to confirm the origin of the singularities Manual tuning So far manual, drifts to be included in supervision So far manual (Timber & XL) Many specific cases (cryo cells, instrumentation, operation facts and accuracy) being considered, so far with success

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Standard cells (≈27/sector) QRL Filling valve Q D DD Preparation from 1.9K operation: 2-3 days to set-up conditions Test configuration: 4-5 hours before ramping current Q D DD Q D DD Q D DD Magnets 1.9K control Beam screen T control

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Arc sub-sector resistance variation assessed by calorimetry 23R3 15R1 31R6, 31R1 31R7 ~ 2 7 kA Although we try to reduce our uncertainty, we feel that specific behaviour of DS zones would be of greater interest! Triplets: being tested right

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 “Cryo view” of tasks ahead this year Challenges for this year: Completion of consolidations (like others!) Cooling 4 sectors + filling/tuning 8 sectors in four months !!!

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Affectations LHC Cryo CRG-OA Ing. OP référents experts académiques Ing. production Encadrement site Opérateurs Sites + Shifts CCC interface Site coordination HWC

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 LHC Cryo shifts 2009: 15 Avril Final adjustments being implemented Timing: 6h - 14h - 22h (+/- 1/4h over-lap) Tel Cryo CCC: Additional support am/pm (2x2 pers.) for CCC or LN2 logistics + Double on-call service for interventions + Eng. Support via “Best Effort”

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Proposal for definition of tasks site/shifts We will adapt to reality and needs for global efficiency Winter’09Spring’09 Summer’09 Aut’09 CCC for Cryo Start/Maintain Direct interface for BE/OP Local CCR for support and site periodic activities CCC for global overview and continuity of activities Local CCR for cool-down, tuning and HWC activities PP BeamsCooling-Tuning-HWC Cryo shifts in CCC Being reviewed and more closely precised

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Summary LHC Cryogenic system has been put in operation with success in 2008 and was “ready” for 5 Tev operation Since september 2008, test programs were conducted and improved our understanding and tuning of sub- systems (calorimetry, 1 refrigerator on two sectors) Consolidation programs were launched to improve safety and to increase availability (to be completed) We should manage foreseen program with less stress, but we know we have about 500 PID control loops per sector to be active simultaneously, and we will have surprises and temporary down-time to be dealt with!

Complements

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Cryo conditions for powering Cryo Start: set of conditions to allow powering of concerned sub-sector (rather strict = good stability of process) Cryo Maintain: Few important conditions checking integrity of HW, with slow power abort in case this signal is lost CM: No adjustment possible during operation CS: Adjustments within pre-set limits

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Recovery Time after Limited Resistive Transitions More than 14 cells or full sector: recovery up to 48 hours In case of fast discharge (even w/o quench): 2 h recovery (heating due to eddy currents). (Predictions at design stage) Achieved or achievable From x3 down to x1.5 w.r.t design values Without loosing helium, and powering permit on other powering subsectors

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Helium storage 50 t: 50 x 250 m x 76 m3 30 t: 2 x 15 t for Spring 2008 ! Now completed by (Ph. 1): A good basis, but “rather long” logistics LHC: 130t

S. ClaudetLHC Cryogenics - LHC HWC day - Mar'09 Two sectors on one cryoplant Powering tests 4.5K 15 mbar 4.5K Ref.: ≈10% capacity left per sector for dynamic loads, after specific adjustments made ≈ 5MW of power input, instead of 8MW (2x4MW) Competitive for recovery after stops (<10hrs for CC, <24hrs after power failure for 2 sectors) Not valid for large transients, but an interesting feature for low beam loads, or validated fall-back scenario if serious problems with a refrigerator OK P6, possible P8 (3Qx) P4 ? (RF/DSLC), P2/P18 ?!? (ex-LEP, 3Qx)