October 18, 2005 1 Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the.

Slides:



Advertisements
Similar presentations
M1 Installation Schedule Plans Burkhard Schmidt Muon Meeting
Advertisements

02-Mar-09A. Cardini / CERN & INFN1 Muon Detector Status (week 9: Feb 23 rd  Feb 27 th ) Present: Ale, Thomas, Nikolai, Oleg, Sasha, Maria Luisa, Perluigi,
Walls crates cables gas chambers electronics CERN adb.
For more information, please contact 19/11/2010 EN/CV/DC Chiller design and purchase by Elena Perez Rodriguez.
October 23rd, 2009 Visit of CMS Computing Management at CC-IN2P3.
December 3, 20031Muon Integration Meeting B. Schmidt Introduction: The present architecture of the Muon System is based on the assumption that the maximal.
Fcal upgrade for sLHC: Cryogenics modifications – TE-CRG/ C.Fabre 1 ATLAS FCal Upgrade for sLHC: Modifications to the Calorimeter Cryogenic.
18 June 20031Integration Review B. Schmidt Outline: Filter design and basic concept to ensure seismic stability Filter Installation and the required tooling.
Peter Sharp CERN CMS Electronics CMS LV Power System Peter Sharp 7 April 2003.
1 Fulvio TESSAROTTO Update on the thin RICH beam pipe project - prototypes validation and pipe production - microflanges and fixation system - the intervention.
P. 1Mario Deile – TOTEMino: Infrastructure Status and Schedule Mario Deile Zone 2.Gas system 3.Cabling 4.Cooling water 5.Counting-Room 6.Safety.
TGC Big wheel Sector assembly plan Tatsuo Kawamoto ATLAS workshop 2005.
VELO workshop, Amsterdam, april ‘00M.Ferro-Luzzi Difficulties with current mechanical design recent FEA results: to obtain sufficient stiffness of center.
LHCb CO 2 cooling meeting Burkhard Schmidt – February 18,
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
Evaporative Heater Design, qualification and planning M.Olcese PRR SCT off-detector cooling PRR SCT off-detector cooling March March 2005.
Tariq J. Solaija, NCP Forward RPC EDR, Tariq Solaija Forward RPC EDR The Standard RPC for low  regions Tariq J. Solaija National Centre for.
Muon Stations M2-M5 Hardware status Outline: Gas System status UF/PNPI HV-system status Remaining M2-M5 installation tasks – Air cooling system status.
GEM chambers for SoLID Nilanga Liyanage University of Virginia.
G. Carboni – Muon Meeting – April 2002 Muon Meeting LHC schedule is now official (Council Committee) First protons (Pilot run) delayed to
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
G. Pugliese RPC requests for GIF++ G.Pugliese, N. Zaganidis and I. Pedraza on behalf of the RPC group 1.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
09/07/20021Muon Meeting Status of MWPC activities at CERN and PNPI Outline: Module 0 status and plans –M3R1 (CERN) –M3R2 (CERN) –M3R4 (PNPI) Tooling status.
Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.
CMS Experiment at the LHC, CERN Date Recorded: :21 CET Run/Event: / Candidate Collision Event Report from Belgium Michael Tytgat.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
CERN adb Chamber Support Structure Installation MUON SYSTEM INTEGRATION MEETING - Status of Production of support panels - Things to be settled.
G. Carboni - Muon Meeting – Draft Agenda Muon Meeting 6 April 2004 Introduction (15 min) Total 15 min MWPC prodution Material supplies,
18 June 20031Integration Review B. Schmidt Outline: Overview of the support structures Requirements –Some details on electronics, cabling and piping Constraints.
CMS Pixels upgrade CO2 cooling transfer lines Draft spec – for introduction Paola Tropea & Hans Postema 5 December 2012.
PHIN Fabrication of a photo-injector for the CTF3 accelerator and for the NEPAL test stand WP 4 of the JRA2 PHIN 1.Status of the construction of RF guns.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
Cryogenics for crab cavities – SPS/LHC 2 nd HiLumi LHC meeting – Frascati (Italy) 15 November 2012 K. Brodzinski and L. Tavian on behalf of cryogenic team.
Status of the ATLAS ID Evaporative cooling system JCOV 25 Nov P. Bonneau TS/CV/Detector Cooling CONTENTS Overall statusOverall status Cooling plant.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
Progress and plans for HO Installation S. Dugad, K. Sudhakar Tata Institute of Fundamental Research India-CMS Meeting at BARC, July 2005.
Muon barrel cooling G. Aielli and J. Godlewski LS1 TC planning.
LHCb Install Meeting - 12 / 05 / 2004 Paolo Guglielmini - TS / CV LHCb Cooling of the sub – detectors INNER TRACKER TRACKER TRIGGER RICH 1 RICH 2 Status.
Summary of FEE-Integration Meeting LNF, Summary of the Frascati meeting on chamber & front-end integration on 10 September 2003, provided.
Joerg Dubert’s Questions as you all aware we currently do not yet know how the final mechanical design of the new Small Wheel will look like. Nevertheless,
EN-CV Progress EHN1 Extension Project Jérôme Rodary EN-CV-PJ 2016/01/21.
Brief Status of LHC Experimental Vacuum Project Ray Veness CERN TE/VSC.
Totem Gas Systems ( T1, T2 ) F. Hahn and S. Haider PH / DT1.
T2 Status Report IP5 Installation Future plans. IP5 installation The mechanical structure has shown problems on installation and should be changed slightly.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
Accelerator Tunnel Layout (G01) Nick Gazis Senior Mechanical Engineer Review of ESS Accelerator Conventional Facility Design.
LHCb Muon Station Cooling Studies (done by Ricardo Antunes Rodrigues (ST/CV)) This simulations were made for the Muon Station 1, with the follow assumptions:
1 Chamber Interfaces Adalberto Readout-, I2C-, HV-, LV-, Gas- and chamber support interface. Space issues.
LHCb CO 2 cooling meeting Burkhard Schmidt – May 20,
CV Activities for PSB-LIU POPS-B (new MPS for the PSB-LIU) B 245 PSB Demi water cooling plant Stefano Moccia, EN-CV Meeting 07/03/16.
Upgrade activities DT-LHCb coordination meeting 14 March 2016.
September 5, Burkhard Schmidt Integration and Installation Outline: Integration and Infrastructure issues -Suspended platforms -Cable chains -Beam.
Demineralised water cooling system
DT-LHCb coordination meeting 18 April 2016
Francois and Lau EATM 17 July 2012
on behalf of the RF group
Target and Horn status report
Renovation of the 45-year old PS magnets
ATLAS ITk CO₂ Cooling pipe routing CO₂ Meeting, 28 June 2016
MicroMegas Mechanical Meeting --- Cern April 2014
Overview & baseline of LS2 and roadmap for CRG
ATLAS ITk CO₂ Cooling pipe routing Common Mechanics meeting
as a prototype for Super c-tau factory
East Hall under construction
Presentation transcript:

October 18, Muon Meeting B. Schmidt Outline: Installation schedule under Discussion Status of Integration activities Possible modifications to the schedule Integration and Installation

October 18, Muon Meeting B. Schmidt Official Installation Schedule: Installation Schedule under Discussion

October 18, Muon Meeting B. Schmidt Comments: Sequence of chamber installation needs to be aligned to chamber production/dressing schedule. We should try to accelerate the installation of the chambers on the PZ-side, to finish before the sector test. Installation Schedule under Discussion

October 18, Muon Meeting B. Schmidt Constraints: Installation Schedule under Discussion

October 18, Muon Meeting B. Schmidt Manpower required: Resources

October 18, Muon Meeting B. Schmidt Platforms and staircases behind M5 (US-side): Integration and Installation Scaffolding for the cryo-line has been removed, despite the fact that the tests are not completed... -> Installation of the staircases and platforms started.

October 18, Muon Meeting B. Schmidt Platforms and staircases behind M5 (PZ- side): Integration and Installation Design ready Price Enquiry being launched Installation could earliest start December 1, 2005

October 18, Muon Meeting B. Schmidt General Support Structures: Integration and Installation Delivery of preassembled components this week. Work on traction system not finished. Nacelles need ‘certificate of conformity’ to be approved by the safety commission.

October 18, Muon Meeting B. Schmidt Proposed schedule: 1.Refurbishing of zone behind M5 US-side: – PZ-side:10.12 – Mounting general support structure US-side – PZ-side: – Installation chamber structure (LNF) US-side: – PZ-side: – Integration of nacelles and guiding system > Only possible if the open safety issues don’t cause a delay (visit to company scheduled for Friday). 5.On detector cabling, gas piping M4/M5: – > Cables for M2/M3 come only in Feb’06, installation only in April ’06 -> Conflict with chamber installation, starting at the same time, due to nacelles, needed for both tasks. -> We have to consider buying a 3 rd nacelle ! Installation of Services

October 18, Muon Meeting B. Schmidt Conclusions The installation of the M2-M5 infrastructure is on the critical path. With the open questions (e.g. on the nacelles and the cable quality) it is difficult to take the decisions required to bring the project back on schedule.

October 18, Muon Meeting B. Schmidt Cabling: Good news: - Best bidder for cable well within our budget - Positive experience of CMS, but not on big samples Bad news: - Prototypes have to be done. Plan (agreed with Adalberto and CERN purchase office): - Order ~10% of LVDS and ~15% of ECS cables (for M4/M5 cryo side) -> Allows to avoid delay in chamber installation (which will start with M5 cryo side). -> In case of unexpected problems with prototype, financial losses are limited, while schedule problems are then unavoidable. Similar situation for HV-cables (same company). Situation with LV-cables to be clarified further. Integration and Installation

October 18, Muon Meeting B. Schmidt On detector Gas Piping: Progress in LNF (Emiliano, Massimo) on design of distribution box. Gas pipes of PEEK type turned out to be MUCH too expensive (~15 × more expensive than copper) ->Optimized design now being finalized (meet next week) ->Validation tests can hopefully been done within the next 3-4 weeks Integration and Installation

October 18, Muon Meeting B. Schmidt Impedance (Δp) adaptation requirement: Ensure an equal pressure drop of about 1mbar for each individual chamber. Old scheme: New scheme: Gas Distribution Scheme Manifolds Distr.box Chambers 3mm PEEK pipe Capillary 8mm copper pipe x16 Manifolds Distr.box Chambers 4/2mm copper pipe Capillary 8mm copper pipe x8

October 18, Muon Meeting B. Schmidt Cooling: Reminder about power consumption: Reminder of cooling strategy: The chambers in regions R1 and R2 have up to 24 FE-boards/chamber and hence quite a large power consumption on a small area ->We foresee to have a sort of air cooling, where air of about 17 o C is blown into or around the chambers in R1 and R2 in stations M1-M3 Integration and Installation

October 18, Muon Meeting B. Schmidt Cooling for FE-boards: In order to avoid hot spots close to the beam pipe, air blowers are foreseen for both sides, providing an airflow of about 400m3/h (this would be enough to remove about 2.5kW of dissipated power by air. Distribution principle: Temperature reduction due to cooling: ΔT 2,3 ~ 7.5 o C Hoses have 30mm diameter Something similar is planned for M1 Cost estimate: ~30kCHF Schedule: Blowers for M2-M3 ready for installation in January 2006 Integration and Installation