MEASURING AND FORECASTING COMPLETION
PROGRESS BY DISCIPLINE
PROGRESS PAYMENTS CHANGE IMPACT CONFORMANCE TO PLAN PROJECT FINAL COST PROJECT DATE OF COMPLETION
ENGINEERING
DRAWING MILESTONES START DRAFT - 20% DRAFT COMPLETE - 65% OFFICE CHECK - 80% OWNER REVIEW - 85% FINAL DRAFT - 90% APPROVAL WITH HOLDS - 95% FINAL OWNER APPROVAL - 100% DRAWING MILESTONES
BUDGETED MANHOURS DISCIPLINE CIVIL ARCHITECTURAL STRUCTURAL MECHANICAL PIPING ELECTRICAL INSTRUMENTATION TOTAL ENGINEERING VALUE DISCIPLINE WGT. VALUE % ESTIMATED DRAWINGS
TOTAL PIPE DWGS. START DRAFT DRAFT COMPLETE OFFICE CHECK OWNER REVIEW FINAL DRAFT APPRV. W/ HOLDS FINAL APPROVED TOTAL PIPING DISCIPLINE PROGRESS 65.5 MILESTONE DISCIPLINE % COMPLETE DWGS. IN MILESTONE MILESTONE VALUE %
PROJECT CONTRIBUTION WEIGHTED VALUE CIVIL ARCHITECTURAL STRUCTURAL MECHANICAL PIPING ELECTRICAL INSTRUMENTATION TOTAL ENGINEERING PROGRESS 67.7 % DISCIPLINE % COMPLETE
PROCUREMENT MEASUREMENT PROCUREMENT MEASUREMENT
MATERIAL TAKE OFFS PURCHASE REQUISITIONS PURCHASE ORDERS
FUNCTION % WEIGHTED VALUE ESTIMATED MANHOURS MATERIAL TAKE-OFF (DWGS) PURCHASE REQUISITIONS PURCHASE ORDERS TOTAL PROCUREMENT VALUE FUNCTIONS ESTIMATED QUANTITIES
TAKE OFFS % DRAWINGS REQUIRING TO'S DRAWING WITH TO'S COMPLETE PHYSICAL PROGRESS
PURCHASE REQUISITIONS PURCHASE REQUISITIONS % ESTIMATED PR's PR's APPROVED FOR PURCHASE PHYSICAL PROGRESS
PURCHASE ORDERS PURCHASE ORDERS 28 PO's OUT OF 100 = 14% 1 MILLION DOLLARS EXPLANTED OUT OF 50 MILLI0NS = 1% PHYSICAL PROGRESS = = 15% QUANTITY PLACED = 50% DOLLAR VALUE SHIPPED = 50% QUANTITY PLACED = 50% DOLLAR VALUE SHIPPED = 50%
FUNCTIONS% COMPLETE WEIGHTED VALUE PROCUREMENT CONTRIBUTION MATERIAL TAKE-OFFS PURCHASE REQUISITIONS PURCHASE ORDERS TOTAL PROCUREMENT PROGRESS
MOBILIZATION & GRADE FOUNDATION COMPLETE STRUCTURAL COMPLETE EQUIPMENT ERECTION COMPLETE PIPING COMPLETE ELECTRICAL COMPLETE MECHANICAL COMPLETION COMMISSIONING TOTAL PROJECT VALUE WEIGHTED PERCENTAGE ESTIMATED MANHOURS MILESTONE
WEIGHTED % MOBILIZATION & GRADING FOUNDATION STRUCTURAL STEEL EQUIPMENT ERECTION TOTAL PHYSICAL PROGRESS 18.7 PROJECT CONTRIBUTION % COMPLETE MILESTONE
TOTAL ENGINEERING PROGRESS
TOTAL CONTRACT DESIGN/ENGINEERING OVERALL COMPLETE WEIGHTED VALUE % ENGINEERING PROCUREMENT PROGRESS PROJECT CONTRIBU- TION BUDGETED MANHOURS TOTAL CONTRACT % COMPLETE
PRODUCTIVITY PROFILES
FACTORS AFFECTING PRODUCTIVITY PROFILES PROJECT LOCATION JOB COMPLEXITY WORKING HOURS LABOR DENSITY SUPERVISION QUALITY WEATHER MIXTURE OF NATIONALITIES DISCIPLINE
THEORETICAL % BUDGET MANHOURS UTILIZED O * * * * * * * * * * PRODUCTIVITY PHYSICAL COMPLETION %
CREDIT BY EARNED MANHOURS CREDIT BY EARNED MANHOURS 2000 MHRS 1000 MHRS ORIGINAL ESTIMATE ESTIMATE REMAINING EARNED
P = % PHYSICAL COMPLETION % QAB MHRS UTILIZED P = % PHYSICAL COMPLETION % QAB MHRS UTILIZED
BCWS BCWP ACWP
CREDIT BY UNITS INSTALLED
COST VARIANCE CV = BCWP - ACWP SCHEDULE VARIANCE SV = BCWP - BCWS
INTERMEDIATE MILESTONE PERCENTAGE COMPLETE
CONSTRUCTION