P.-R. KettleMEG Review January 20031 MEG – Beam Line Studies Present Status & Overview since July 2002.

Slides:



Advertisements
Similar presentations
Measurement of transverse emittances with a Solenoid (for GUN-0.1) - Jens Völker – ( )
Advertisements

1 MICE Beamline: Plans for initial commissioning. Kevin Tilley, 16 th November. - 75days until commissioning Target, detectors, particle production Upstream.
Preliminary studies for T2 primary target for the NA61 fragmentation beam run 11 th October 2010 – NA61 Collaboration Meeting M. Calviani on behalf of.
1 Neutrino Factory Front End (IDS) -Chicane & Absorber David Neuffer C. Rogers, P. Snopok, C. Yoshikawa, … January 31, 2012.
P.-R. KettleMEG-Review February MEG Beam Line Studies  E5 Z-Branch NOW !!! NOW !!!
P.-R. KettleMEG Review July MEG Beam Line Studies.
FODO-based Quadrupole Cooling Channel M. Berz, D. Errede, C. Johnstone, K. Makino, Dave Neuffer, Andy Van Ginneken.
Yury CHESNOKOV Crystal Collimation workshop, March 7, 2005 CALIBRATION of CMS CALORIMETERS with LHC PROTON BEAM DEFLECTED BY CRYSTAL CALIBRATION of CMS.
Pion yield studies for proton drive beams of 2-8 GeV kinetic energy for stopped muon and low-energy muon decay experiments Sergei Striganov Fermilab Workshop.
Target & Capture for PRISM Koji Yoshimura On behalf of PRISM Target Group Institute of Particle and Nuclear Science High Energy Accelerator Research Organization.
Pion capture and transport system for PRISM M. Yoshida Osaka Univ. 2005/8/28 NuFACT06 at UCI.
SLIDE Beam measurements using the MICE TOF counters Analysis meeting, 23 September 2008 Mark Rayner.
RF Bucket Area Introduction Intense muon beams have many potential applications, including neutrino factories and muon colliders. However, muons are produced.
1 Downstream scraping and detector sizes Rikard Sandström University of Geneva MICE collaboration meeting CERN.
1 G4MICE studies of PID transverse acceptance MICE video conference Rikard Sandström.
Downstream transversal sizes Rikard Sandström University of Geneva MICE detector meeting.
1 OPTICS OF STAGE III Ulisse Bravar University of Oxford 6 October 2004.
1 EMCal design MICE collaboration meeting Fermilab Rikard Sandström.
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
MEBT & RT CH Section Thomas Page Fermilab Accelerator Advisory Committee May 10 th – 12 th, 2006.
Solenoid-Based Focusing Lens for a Superconducting RF Proton Linac Presentation prepared for AEM 11/08/20101I. Terechkine.
October 28-th, 2005Straw tracker 1 Status of Straw Tracker for P236 P.L. Frabetti, V.Kekelidze, K.Kleinknecht, V.Peshekhonov, B.Peyaud, Yu.Potrebenikov,
 A GEANT4-based simulation was performed of the production target, solenoid, selection channel, and spectrometer.  The acceptance was found to be 8.3x10.
2002/7/02 College, London Muon Phase Rotation at PRISM FFAG Akira SATO Osaka University.
Target & Capture for PRISM Koji Yoshimura Institute of Particle and Nuclear Science High Energy Accelerator Research Organization (KEK)
SuperB Meeting, May 2008 Status of the magnetic design of the first quadrupole (QD0) for the SuperB interaction region S. Bettoni on behalf of the whole.
1 W.Ootani ICEPP, University of Tokyo MEG experiment review meeting Feb , PSI W.Ootani ICEPP, University of Tokyo MEG experiment review meeting.
AAC February 4-6, 2003 Protons on Target Ioanis Kourbanis MI/Beams.
Secondary Particle Production and Capture for Muon Accelerator Applications S.J. Brooks, RAL, Oxfordshire, UK Abstract Intense pulsed.
PSI July 2002MuEGamma Review Meeting1 Beam Line Status update 1.  E5 Test Beam Overview : Aims + RequirementsAims + Requirements Zone Layout + Measurement.
Muon cooling with Li lenses and high field solenoids V. Balbekov, MAP Winter Meeting 02/28-03/04, 2011 OUTLINE  Introduction: why the combination of Li.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
J. Pasternak First Ideas on the Design of the Beam Transport and the Final Focus for the NF Target J. Pasternak, Imperial College London / RAL STFC ,
Beam line Experiment area SC magnet Pion production target
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
Studies on pion/muon capture at MOMENT Nikos Vassilopoulos IHEP, CAS August 11, 2015.
Peter-Raymond Kettle MEG Review February BeamBeam LineLine StatusStatus.
BNL High Field and HTS Magnet Program Ramesh Gupta BNL, NY USA H T.
IDS-NF Accelerator Baseline The Neutrino Factory [1, 2] based on the muon storage ring will be a precision tool to study the neutrino oscillations.It may.
1 Question to the 50GeV group 3GeV からの 54π と 81π 、 6.1π の関係 fast extraction 部の acceptance (81π?) Comments on neutrino beamline optics?
COMET. μ-e conversion search from muonic aluminium J-PARC pulsed proton beam to produce pulsed muon beam Forbidden in the Standard Model  clue to the.
Progress in the construction of the MICE cooling channel and first measurements Adam Dobbs, EPS-HEP, 23 rd July 2011.
LHC-CC Validity Requirements & Tests LHC Crab Cavity Mini Workshop at CERN; 21. August Remarks on using the LHC as a test bed for R&D equipment.
Polarized source upgrade RSC, January 11, OPPIS LINAC Booster AGS RHIC ( ) ∙10 11 p/bunch 0.6mA x 300us→11∙10 11 polarized H - /pulse. ( )
Superconducting Technologies for the Next Generation of Accelerators CERN, Globe of Science and Innovation 4-5 December Superconducting Links for the Hi-Lumi.
Mu to e Meeting BNL, June 2006 Extinction requirement relaxation (Kevin O’Sullivan) Stopping Target Geometry (Cenap Ozben, David Morse) Yannis Semertzidis.
MEIC Detector and IR Integration Vasiliy Morozov, Charles Hyde, Pawel Nadel-Turonski MEIC Detector and IR Design Mini-Workshop, October 31, 2011.
P.-R. KettleMEG-Review July MEG Beam Line Studies  E5 Z-Branch Collaborative Effort !!! Effort !!!  E5 Z-Branch Collaborative Effort !!! Effort.
LINAC4 emittance measurements BI Day Divonne, 24 th November 11/24/2011 B.Cheymol, E. Bravin, D. Gerard, U. Raich, F. Roncarolo BE/BI 1.
1 Front End – gas-filled cavities David Neuffer May 19, 2015.
After Protons from RCS 1 st DeeMe Collaboration Meeting Dec. 10, 2012 Kazami Yamamoto J-PARC Center Accelerator Division.
Cryogenics for SuperB IR Magnets J. G. Weisend II SLAC National Accelerator Lab.
The 12th Symposium on Accelerator Physics, Yuzhong, Gansu, China1 Study of Beam Properties at SECRAL and The Solenoid Pre-focusing LEBT Youjin.
J-Parc Neutrino Facility Primary Proton Beam Design A. K. Ichikawa(KEK), Y.Iwamoto(KEK) and K.Tanabe(Tokyo) et.al. 7 th Nov. 2003,
1 Muon g-2 Experiment at BNL Presented by Masahiko Iwasaki (Tokyo Institute of Technology) Akira Yamamoto (KEK) for E821 g-2 Collaboration: Boston, BNL,
Experimental considerations about  physics at DA  NE2 F. Anulli, D. Babusci, G. Pancheri Laboratori Nazionali di Frascati  Physics window at DA  NE2.
Polarized Injector Update
Study of Beam Properties at SECRAL and The Solenoid Pre-focusing LEBT
NC Accelerator Structures
Target and Horn status report
The COMET Experiment Ajit Kurup, Imperial College London, on behalf of the COMET Collaboration. ABSTRACT The COherent Muon to Electron Transition (COMET)
Electron Polarization In MEIC
I Alexander Nass for the JEDI collaboration
K. Tilley, ISIS, Rutherford Appleton Laboratory, UK Introduction
Higgs Factory Backgrounds
November 7, 2008 The meeting on RIKEN AVF Cyclotron Upgrade Progress report on activity plan Sergey Vorozhtsov.
MEBT1&2 design study for C-ADS
as a prototype for Super c-tau factory
IR Beam Transport Status
S. Bettoni on behalf of the whole team
Presentation transcript:

P.-R. KettleMEG Review January MEG – Beam Line Studies Present Status & Overview since July 2002

P.-R. KettleMEG Review January Outline of Addressed Topics Status at the time of the last ReviewStatus at the time of the last Review July/August 2002 Run (  U-Branch)July/August 2002 Run (  U-Branch) November/December 2002 Run (  Z-Branch)November/December 2002 Run (  Z-Branch) Beam Transport SolenoidBeam Transport Solenoid FutureFuture SummarySummary Status at the time of the last ReviewStatus at the time of the last Review July/August 2002 Run (  U-Branch)July/August 2002 Run (  U-Branch) November/December 2002 Run (  Z-Branch)November/December 2002 Run (  Z-Branch) Beam Transport SolenoidBeam Transport Solenoid FutureFuture SummarySummary

P.-R. KettleMEG Review January Status at last Review July 2002 Present Series of Beam Studies started October 2001 “2-in-1“ Method used in  “U“-Branch simultaneous degrading of µ + momentum & spatial separation of beam e + via an induced differential energy-loss to the particles using a degrader and spectrometer simultaneous degrading of µ + momentum & spatial separation of beam e + via an induced differential energy-loss to the particles using a degrader and spectrometer Present Series of Beam Studies started October 2001 “2-in-1“ Method used in  “U“-Branch simultaneous degrading of µ + momentum & spatial separation of beam e + via an induced differential energy-loss to the particles using a degrader and spectrometer simultaneous degrading of µ + momentum & spatial separation of beam e + via an induced differential energy-loss to the particles using a degrader and spectrometer Conclusion: Stopped Surface Muon Beam of Sufficient Intensity & Stopped Surface Muon Beam of Sufficient Intensity & Free from Beam Correlated Positrons NOT POSSIBLE Free from Beam Correlated Positrons NOT POSSIBLE using “2-in-1“ method in “U“-Branch, without channel using “2-in-1“ method in “U“-Branch, without channel modification – modification – limitation of vertical phase space acceptance of last doublet limitation of vertical phase space acceptance of last doubletConclusion: Stopped Surface Muon Beam of Sufficient Intensity & Stopped Surface Muon Beam of Sufficient Intensity & Free from Beam Correlated Positrons NOT POSSIBLE Free from Beam Correlated Positrons NOT POSSIBLE using “2-in-1“ method in “U“-Branch, without channel using “2-in-1“ method in “U“-Branch, without channel modification – modification – limitation of vertical phase space acceptance of last doublet limitation of vertical phase space acceptance of last doublet

P.-R. KettleMEG Review January Status at last Review July 2002 (continued) Plan Presented → up to End 2002 Involving - 2 proposed Test Beam Periods within 6 months Involving - 2 proposed Test Beam Periods within 6 months July/August  “U“-Branch July/August  “U“-Branch November/December  “Z“-Branch November/December  “Z“-Branch goals: goals: Find viable alternative method to “2-in-1“Find viable alternative method to “2-in-1“ Set up full beam line upto COBRA solenoidSet up full beam line upto COBRA solenoid Comparitve study of both branchesComparitve study of both branches Collect data by end of 2002 to make optimal choice ofCollect data by end of 2002 to make optimal choice of branch for MEG experiment early in 2003 branch for MEG experiment early in 2003 Plan Presented → up to End 2002 Involving - 2 proposed Test Beam Periods within 6 months Involving - 2 proposed Test Beam Periods within 6 months July/August  “U“-Branch July/August  “U“-Branch November/December  “Z“-Branch November/December  “Z“-Branch goals: goals: Find viable alternative method to “2-in-1“Find viable alternative method to “2-in-1“ Set up full beam line upto COBRA solenoidSet up full beam line upto COBRA solenoid Comparitve study of both branchesComparitve study of both branches Collect data by end of 2002 to make optimal choice ofCollect data by end of 2002 to make optimal choice of branch for MEG experiment early in 2003 branch for MEG experiment early in 2003 Possible Solutions: Possible Solutions: 1.Re-build last part of Beam Line & use Solenoid or Triplet 2.Use 2-Stage Separation & Degrading method → WIEN Filter & Solenoid → Method (2) chosen for “U”-branch July/August Run → Method (2) chosen for “U”-branch July/August Run Possible Solutions: Possible Solutions: 1.Re-build last part of Beam Line & use Solenoid or Triplet 2.Use 2-Stage Separation & Degrading method → WIEN Filter & Solenoid → Method (2) chosen for “U”-branch July/August Run → Method (2) chosen for “U”-branch July/August Run

P.-R. KettleMEG Review January July/August 2002 Beam Period Z-Branch U-Branch  Layout “U”-Branch Measurements “U”-Branch Measurements Leave existing Beam Line Add WIEN-Filter (Crossed E &B fields)  Particle Separation Add Solenoid + Degrader System  Momentum Reduction Provisional Results showed Provisional Results showed Suitable beam CAN be achievedSuitable beam CAN be achieved using this method using this method Method should also be used asMethod should also be used as comparative study for “Z”-Branch comparative study for “Z”-Branch “U”-Branch Measurements “U”-Branch Measurements Leave existing Beam Line Add WIEN-Filter (Crossed E &B fields)  Particle Separation Add Solenoid + Degrader System  Momentum Reduction Provisional Results showed Provisional Results showed Suitable beam CAN be achievedSuitable beam CAN be achieved using this method using this method Method should also be used asMethod should also be used as comparative study for “Z”-Branch comparative study for “Z”-Branch

P.-R. KettleMEG Review January “U”-Branch Layout & Measurement Principle Measurements in 3 at 3 Locations using various methods: Measurements in 3 at 3 Locations using various methods: 1.Point A – post QSE 41/42 doublet (Normalization Measurement) 2.Point B – post separator/entrance solenoid with/without Collimator (Transmission) 3.Point C – post solenoid, various target sizes & thicknesses & material (Stop Rate) Measurements in 3 at 3 Locations using various methods: Measurements in 3 at 3 Locations using various methods: 1.Point A – post QSE 41/42 doublet (Normalization Measurement) 2.Point B – post separator/entrance solenoid with/without Collimator (Transmission) 3.Point C – post solenoid, various target sizes & thicknesses & material (Stop Rate)

P.-R. KettleMEG Review January Target Geometry for 2002 Runs Measuring Conditions 2002: Measuring Conditions 2002: 4 cm Target E (Proposal 6cm Target + different construction) ~ 1840 µA Proton current Measuring Conditions 2002: Measuring Conditions 2002: 4 cm Target E (Proposal 6cm Target + different construction) ~ 1840 µA Proton current R 4cm =(0.55±0.05)R 6cm Measured  L. Simons et al from geometry alone would expect ~ 0.67 R 4cm =(0.55±0.05)R 6cm Measured  L. Simons et al from geometry alone would expect ~ cm Tg.E as in Proposal 6 spokes continuous 4cm Tg.E as now 12 spokes + slits

P.-R. KettleMEG Review January Provisional Results July/August 2002 Run Phase A Phase B Phase C µ+µ+µ+µ+ µ+µ+µ+µ+ Beam e + Beam Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) Separator 175kV µ/e separation: 11σ !!! 24cm Vertically Transmission Sep=ON: 56% Corresponds to 7.3·10 7 µ+/s 4cm 1800µA (1.3·10 8 µ + /s 6cm Tg.) Separator 175kV µ/e separation: 11σ !!! 24cm Vertically Transmission Sep=ON: 56% Corresponds to 7.3·10 7 µ+/s 4cm 1800µA (1.3·10 8 µ + /s 6cm Tg.) Spot-size with “double-node” mode: “double-node” mode: σ V ~ 6.5mm as in σ H ~ 5.5mm proposal σ H ~ 5.5mm proposalTransmission Sol. ~55% Coll. ~80% N.B. Solenoid NOT matched Spot-size with “double-node” mode: “double-node” mode: σ V ~ 6.5mm as in σ H ~ 5.5mm proposal σ H ~ 5.5mm proposalTransmission Sol. ~55% Coll. ~80% N.B. Solenoid NOT matched Analysis continuing

P.-R. KettleMEG Review January November/December 2002 “Z”-Branch Beam Period Extensive Preparations needed!Extensive Preparations needed! No extraction mechanism easily availableNo extraction mechanism easily available  planned SINDRUM 1 solenoid NOT AVAILABLE after all  planned SINDRUM 1 solenoid NOT AVAILABLE after all  Concrete beam-blocker after ASC( 2m inside shielding)  Concrete beam-blocker after ASC( 2m inside shielding) Triplet extraction system decided onTriplet extraction system decided on  Brand new ”Raw” Quads for LEM-beam borrowed … BUT  Brand new ”Raw” Quads for LEM-beam borrowed … BUT ~2 1/2 months to Design & Construct shielding and ~2 1/2 months to Design & Construct shielding and insertion wagon for quads + build triplet insertion wagon for quads + build triplet & Insert new system & Insert new system  Only possible when Accelerator is OFF  Only possible when Accelerator is OFF Thanks to the excellent work of many of the Thanks to the excellent work of many of the Service Groups involved  Insertion during Service Groups involved  Insertion during 2-day Shutdown end November day Shutdown end November 2002 Extensive Preparations needed!Extensive Preparations needed! No extraction mechanism easily availableNo extraction mechanism easily available  planned SINDRUM 1 solenoid NOT AVAILABLE after all  planned SINDRUM 1 solenoid NOT AVAILABLE after all  Concrete beam-blocker after ASC( 2m inside shielding)  Concrete beam-blocker after ASC( 2m inside shielding) Triplet extraction system decided onTriplet extraction system decided on  Brand new ”Raw” Quads for LEM-beam borrowed … BUT  Brand new ”Raw” Quads for LEM-beam borrowed … BUT ~2 1/2 months to Design & Construct shielding and ~2 1/2 months to Design & Construct shielding and insertion wagon for quads + build triplet insertion wagon for quads + build triplet & Insert new system & Insert new system  Only possible when Accelerator is OFF  Only possible when Accelerator is OFF Thanks to the excellent work of many of the Thanks to the excellent work of many of the Service Groups involved  Insertion during Service Groups involved  Insertion during 2-day Shutdown end November day Shutdown end November 2002

P.-R. KettleMEG Review January “Z”-Branch Layout & Measurement Principle Same Principle adopted as “U”-Branch but with “U”-Branch but with Triplet instead of Doublet + Separator & Solenoid however however Run split into 2 parts Run split into 2 parts November/December 2002 Phase A – Post Triplet Phase A – Post Triplet Phase B - Post Separator Phase B - Post Separator April/May 2003 April/May 2003 Phase C – Solenoid + Phase C – Solenoid + Stop Distribution Stop Distribution Same Principle adopted as “U”-Branch but with “U”-Branch but with Triplet instead of Doublet + Separator & Solenoid however however Run split into 2 parts Run split into 2 parts November/December 2002 Phase A – Post Triplet Phase A – Post Triplet Phase B - Post Separator Phase B - Post Separator April/May 2003 April/May 2003 Phase C – Solenoid + Phase C – Solenoid + Stop Distribution Stop Distribution Large quantity of Data collected Detailed Analysis – just started running in parallel to analysis From July/August Run Large quantity of Data collected Detailed Analysis – just started running in parallel to analysis From July/August Run

P.-R. KettleMEG Review January Very Provisional Results November/December 2002 Run Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) Integrated Rate 4cm 1800µA N µ ~1.3·10 8 µ + /s (2.3·10 8 µ+/s 6cm Tg.) Phase A Phase B Separator 175kV Separator 175kV µ/e separation: µ/e separation: (1) 7σ 12cm Vertically 12cm Vertically Transmission Sep=ON: 67% 67% Corresponds to Corresponds to 8.8·10 7 µ + /s 4cm 1800µA 8.8·10 7 µ + /s 4cm 1800µA (1.6·10 8 µ + /s 6cm Tg.) (1.6·10 8 µ + /s 6cm Tg.) (2)11cm Vertically Transmission Sep=ON Transmission Sep=ON 73% 73% Corresponds to Corresponds to 9.5·10 7 µ + /s 4cm 1800µA (1.7·10 8 µ + /s 6cm Tg.) (1.7·10 8 µ + /s 6cm Tg.) Separator 175kV Separator 175kV µ/e separation: µ/e separation: (1) 7σ 12cm Vertically 12cm Vertically Transmission Sep=ON: 67% 67% Corresponds to Corresponds to 8.8·10 7 µ + /s 4cm 1800µA 8.8·10 7 µ + /s 4cm 1800µA (1.6·10 8 µ + /s 6cm Tg.) (1.6·10 8 µ + /s 6cm Tg.) (2)11cm Vertically Transmission Sep=ON Transmission Sep=ON 73% 73% Corresponds to Corresponds to 9.5·10 7 µ + /s 4cm 1800µA (1.7·10 8 µ + /s 6cm Tg.) (1.7·10 8 µ + /s 6cm Tg.)

P.-R. KettleMEG Review January MEG Transport Solenoid Considerations a First Look July/Aug. Solenoid Scan Rate vs. Bfield for 28 MeV/c surface muons July/Aug. Solenoid Scan Rate vs. Bfield for 28 MeV/c surface muons Single Node Double Node B=0.426 T I=6.39 A B=0.971 T I=14.56 A What does this mean for the What does this mean for the Design of our Transport Solenoid ? 1.Above gives us ∫Bdl for 28MeV/c µ + 2-nodes 2.Have to couple to COBRA at 0.5T 3.Superconducting or Normal Conducting? 4.Air or Iron Warm Solenoid 5.Length 6.Coupling Homogeneity work together with experts from work together with experts from Novosibirsk-Tokyo-KEK-PSI Novosibirsk-Tokyo-KEK-PSI What does this mean for the What does this mean for the Design of our Transport Solenoid ? 1.Above gives us ∫Bdl for 28MeV/c µ + 2-nodes 2.Have to couple to COBRA at 0.5T 3.Superconducting or Normal Conducting? 4.Air or Iron Warm Solenoid 5.Length 6.Coupling Homogeneity work together with experts from work together with experts from Novosibirsk-Tokyo-KEK-PSI Novosibirsk-Tokyo-KEK-PSI

P.-R. KettleMEG Review January Length of Transport Solenoid PSC/ALC Solenoid Simulation = Field Map on axis ∫Bdl= Tm physical length) PSC/ALC Solenoid Simulation = Field Map on axis ∫Bdl= Tm physical length) For ∫Bdl= Tm & B coupling = 0.5T L sol  180cm For ∫Bdl= Tm & B coupling = 0.5T L sol  180cm

P.-R. KettleMEG Review January What about coupling to COBRA? Axial Cobra Bfield Bfield Radius 0 – 60 cm Radius 0 – 16cm (Transport sol) Radial Cobra Bfield Bfield ~2% homogeneity

P.-R. KettleMEG Review January Normal or Superconducting? Rough Cost Estimate NormalConductingSuper-conductingSolenoid ~ 50ksFr 150 ksFr Power Supply  100ksFr ~ 10ksFr Power Costs ~50sFr Cryogenic Parts (Process Control Logic) ~100ksFr Initial outlay ~ 150ksFr ~ 150ksFr~260ksFr Costs 3yrs of Running ~150ksFr Total Costs after 3 yrs ~ 300ksFr ~ 300ksFr~260ksFr Other Arguments/Future Use: Other Arguments/Future Use: Cold – need LHe transfer line or dewarsCold – need LHe transfer line or dewars Cold – power supply easily transferableCold – power supply easily transferable Cold – more useful for future B rangeCold – more useful for future B range larger for fixed supply larger for fixed supply Warm – Special Power Supply neededWarm – Special Power Supply needed Warm – not easily movableWarm – not easily movable Other Arguments/Future Use: Other Arguments/Future Use: Cold – need LHe transfer line or dewarsCold – need LHe transfer line or dewars Cold – power supply easily transferableCold – power supply easily transferable Cold – more useful for future B rangeCold – more useful for future B range larger for fixed supply larger for fixed supply Warm – Special Power Supply neededWarm – Special Power Supply needed Warm – not easily movableWarm – not easily movable Very Rough Estimates Only 1 st Round!!! Needs more realistic modelling & interaction with the experts

P.-R. KettleMEG Review January FutureFuture Follow-up Points: Follow-up Points: Start Design phase for Transport Solenoid Start Design phase for Transport Solenoid Phase C of Test Beam Period – stats end April 2003 Solenoid + Phase C of Test Beam Period – stats end April 2003 Solenoid + Stop Distribution Study Stop Distribution Study Continue Analysis of Test Beam Data Continue Analysis of Test Beam Data Start design of final Triplet + Wagon + Shielding after test Beam Start design of final Triplet + Wagon + Shielding after test Beam should be ready to install shutdown 2003/2004 should be ready to install shutdown 2003/2004 Design of Target System Design of Target System Follow-up Points: Follow-up Points: Start Design phase for Transport Solenoid Start Design phase for Transport Solenoid Phase C of Test Beam Period – stats end April 2003 Solenoid + Phase C of Test Beam Period – stats end April 2003 Solenoid + Stop Distribution Study Stop Distribution Study Continue Analysis of Test Beam Data Continue Analysis of Test Beam Data Start design of final Triplet + Wagon + Shielding after test Beam Start design of final Triplet + Wagon + Shielding after test Beam should be ready to install shutdown 2003/2004 should be ready to install shutdown 2003/2004 Design of Target System Design of Target System

P.-R. KettleMEG Review January SummarySummary 1. Viable Solution for the MEG Beam Line FOUND using “Z”-Branch using separate stages for particle separation & Momentum Degradation using separate stages for particle separation & Momentum Degradation via triplet + WIEN Filter + Solenoid via triplet + WIEN Filter + Solenoid excellent suppression of beam correlated background excellent suppression of beam correlated background (`~7σ possible with higher rate) (`~7σ possible with higher rate) Rate of 9.5·10 7 µ µA and 4cm Tg.E AFTER Separation Rate of 9.5·10 7 µ µA and 4cm Tg.E AFTER Separation (equivalent to ~ 1.7· µA and 6cm Tg. Proposal) (equivalent to ~ 1.7· µA and 6cm Tg. Proposal) Transmission Factor of ~ 73% in WIEN-Filter Transmission Factor of ~ 73% in WIEN-Filter Final Target Beam-spot sizes equivalent to Proposal Values Final Target Beam-spot sizes equivalent to Proposal Values achieved 5.5mm  σ x σ y  6.5mm achieved 5.5mm  σ x σ y  6.5mm 2.Work on Transport Solenoid started length ~180cm with B~0.5T neededlength ~180cm with B~0.5T needed Warm or Cold? EtcWarm or Cold? Etc 3.Solenoid + Degrader & Stop Distribution measurements Final part Phase C of “Z”-Branch measurements April/May 2003Final part Phase C of “Z”-Branch measurements April/May Continue Analysis + Preparations for final Triplet 1. Viable Solution for the MEG Beam Line FOUND using “Z”-Branch using separate stages for particle separation & Momentum Degradation using separate stages for particle separation & Momentum Degradation via triplet + WIEN Filter + Solenoid via triplet + WIEN Filter + Solenoid excellent suppression of beam correlated background excellent suppression of beam correlated background (`~7σ possible with higher rate) (`~7σ possible with higher rate) Rate of 9.5·10 7 µ µA and 4cm Tg.E AFTER Separation Rate of 9.5·10 7 µ µA and 4cm Tg.E AFTER Separation (equivalent to ~ 1.7· µA and 6cm Tg. Proposal) (equivalent to ~ 1.7· µA and 6cm Tg. Proposal) Transmission Factor of ~ 73% in WIEN-Filter Transmission Factor of ~ 73% in WIEN-Filter Final Target Beam-spot sizes equivalent to Proposal Values Final Target Beam-spot sizes equivalent to Proposal Values achieved 5.5mm  σ x σ y  6.5mm achieved 5.5mm  σ x σ y  6.5mm 2.Work on Transport Solenoid started length ~180cm with B~0.5T neededlength ~180cm with B~0.5T needed Warm or Cold? EtcWarm or Cold? Etc 3.Solenoid + Degrader & Stop Distribution measurements Final part Phase C of “Z”-Branch measurements April/May 2003Final part Phase C of “Z”-Branch measurements April/May Continue Analysis + Preparations for final Triplet