1 FY05 Shutdown at CDF Rob Roser for the CDF Operations Group January 18, 2004.

Slides:



Advertisements
Similar presentations
Status of the CTP O.Villalobos Baillie University of Birmingham April 23rd 2009.
Advertisements

Final Commissioning Plan and Schedule Cheng-Ju Lin Fermilab Installation Readiness Review 09/27/2004 Outline: - Work to be done during shutdown - Work.
Steve Hahn, CDF Meeting - October 7, CDF Operations Summary Shutdown progress  Work finishing up in west and east bores COT  Loose cables SVX 
Bob Wagner, ANL Dec 15, 2005 CDF Weekly Meeting
The LAr ROD Project and Online Activities Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Eric, Jean-Pierre,... Journée de réflexion du DPNC Centre.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
CDF Silicon Workshop th May 2006 New BLM & BLM electronics Jose E. Garcia, Jennifer Gimmell, Ulrich Husemann.
13 January All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 January 6-12 We had to sacrifice.
October 24, 2000Milestones, Funding of USCMS S&C Matthias Kasemann1 US CMS Software and Computing Milestones and Funding Profiles Matthias Kasemann Fermilab.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Jon S Kapustinsky 11/17/2010 Jon S Kapustinsky FVTX Commissioning Plan 1.71 Jon S Kapustinsky 1.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
H. MatisTracking Upgrade Review – Dec. 7, SSD Update Howard Matis.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester July 8, 2013.
V. Bobillier1 Long distance cable installation status Calorimeter commissioning meeting.
DAQ MICO Report Online Monitoring: –Status All histograms are now implemented Still not fully online –Only monitoring from data file (slightly offline,
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
11 SSD Power and Cooling on the Cone STAR Integration Workshop Howard Matis May 16, 2008 STAR Integration Workshop Howard Matis May 16, 2008.
M&O status and program for ATLAS LAr calorimeter R Stroynowski (on vacations)
Dmitri Denisov D0 Weekly Summary: August 18 to August 24  Delivered Luminosity and operating efficiency u Delivered 6.9pb -1 u Recorded 6.0pb -1 (87%)
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
John Coughlan Tracker Week October FED Status Production Status Acceptance Testing.
U.S. ATLAS Executive Committee August 3, 2005 U.S. ATLAS TDAQ FY06 M&O Planning A.J. Lankford UC Irvine.
Online Reconstruction 1M.Ellis - CM th October 2008.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
1Malcolm Ellis - Tracker Meeting - 28th November 2006 Electronics - Station Acceptance  Hardware: u 1 MICE cryostat with 1 VLPC cassette. u VME crate,
D. Still-FNAL/Tevatron HALO '03 Tevatron Collider II Halo Removal System Dean Still Fermilab Tevatron Department 5/21/2003 Motives for the Collider Run.
18 March 2002 All Experimenters’ Meeting Alan L. Stone Louisiana Tech University 1 DØ Status: 03/11 – 03/18 Week integrated luminosity –1.1 pb -1 delivered.
Transversity Readiness and Timeline Xiaodong Jiang, March 17th, This document specifies the overall readiness for Hall A experiments E06-010/E
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
MINER A Operations Report All Experimenters’ Meeting Steve Hahn, FNAL July 1, 2013.
R. Fantechi. Shutdown work Refurbishment of transceiver power supplies Power supplies dismounted Shipped to Orsay this week Refurbishment work to start.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
Tevatron BPM Upgrade Stephen Wolbers CD Accelerator Coordination Meeting September 21, 2004.
FNAL All Experimenters Meeting January 7, Leslie Groer Columbia UniversityDØ Status 1 DØ Status and Progress Dec 17, 2001 – Jan 7, 2002  Reasonably.
All Experimenters MeetingDmitri Denisov Week of September 9 to September 16 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 4.0pb.
All Experimenters MeetingDmitri Denisov Week of September 2 to September 8 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.9pb.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
FPD STATUS Carlos Avila Uniandes/UTA 1. FPD overview 2. Roman pot and detector status 3. FPD readout integration status 4. Software status 5. Stand-alone.
Hall D infrastructure and integration Elton Smith Hall D Collaboration Meeting September 9-11, 2004.
H. MatisSTAR Inner Silicon Tracking Detector Review – July 8, SSD software and hardware maintainability Howard Matis.
February 14, Comprehensive Review B. Schmidt Outline: Status and overview of activities: –Platforms and staircases –Muon Filters and beam plugs.
DAQ Status & Plans GlueX Collaboration Meeting – Feb 21-23, 2013 Jefferson Lab Bryan Moffit/David Abbott.
Tracker Cosmic Ray Test 2011 Linda R. Coney UC Riverside CM 29 - February 16, 2011.
Detector Summary Tracker. Well, as far as the tracker hardware is concerned, we are done. – Need to do the system test to make sure nothing has degraded.
RRB scrutiny Report: Muons. Internal scrutiny group for RRB report Internal scrutiny group composition – J. Shank, G. Mikenberg, F. Taylor, H. Kroha,
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
R. Fantechi. Shutdown work Refurbishment of transceiver power supplies Work almost finished in Orsay Small crisis 20 days ago due to late delivery of.
Proton Plan PMG 2/22/07 E Prebys 1 Proton Plan Status January Eric Prebys.
SPHENIX MECHANICAL D. Lynch September 11, AGENDA Global Design Concept – Updated Global Assembly Concept – Updated Inner HCal Installation concept.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
D.Macina TS/LEATOTEM Meeting25/02/2004 Roman Pot test at the SPS Test of the Roman Pot prototype in the SPS proposed in December 2003 (CERN/LHCC ):
Evelyn Thomson Ohio State University Page 1 XFT Status CDF Trigger Workshop, 17 August 2000 l XFT Hardware status l XFT Integration tests at B0, including:
L1Calo News Activity Summary, Run coordination and Operation Planning Bruce M. Barnett Rutherford Appleton Laboratory.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Target Status 27 th August 2009 Chris Booth The University of Sheffield.
Summary of IAPP scientific activities into 4 years P. Giannetti INFN of Pisa.
ELENA installation progress F. Butin / ELENA collaboration.
The MINER A Operations Report All Experimenters Meeting Howard Budd, University of Rochester June 3, 2013.
Jim Fast Pacific Northwest National Laboratory
CLAS12 DAQ & Trigger Status
Machine operation and daily maintenance management in SOLEIL
U.S. ATLAS TDAQ FY06 M&O Planning
Online Software “To Do” List
Plans for the 2004 CSC Beam Test
XFT2B: Plans and Tasks XFT Workshop FNAL 19 December 2003; p.1.
Presentation transcript:

1 FY05 Shutdown at CDF Rob Roser for the CDF Operations Group January 18, 2004

2 CDF’s Bottom Line  We completed ALL work in the FY04 shutdown that we set out to complete  The projects that we have proposed will NOT drive the end date of the shutdown  Much of our upgrade tasks are not located in the collision hall.  The implementation of the upgrades can be staged -- the net impact will ultimately be on data taking efficiency  We will not allow work to fill entire time shutdown – significant time will be reserved for calibrations/cosmic ray running/trigger torture tests to ensure we are as ready for beam as possible

3Assumptions  Shutdown will begin on August 8 th  Shutdown will last 8 weeks  Electron Cooling has been commissioned and we will have more pbars available at collision starting very soon after accelerator startup  Manpower will be tight – we expect to have access to our entire crew, but probably not alot of additional help available

4 Inside the Collision Hall  General Maintenance/Repair COT Maintenance –May want to remove an inner SL wireplane for electron microscope inspection Silicon Junction Card work? Installation of new Diamond Detectors around beampipe on both ends of the CDF detector to better monitor silicon radiation Installation of SNEG beampipes? Alignment of low beta quad magnets Final referencing of deep rod monuments Alignment of CDF detector wrt DRM Replace Air Filters in electronics racks Replace or Rebuild two Hillmann Rollers (NW IMU, SW CMP) Remove a heat exchanger on the detector, cut it open, and inspect for rust/thinning

5 Outside the Collision Hall DAQ/online computer Maintenance/upgrades Database maintenance HVAC Maintenance Motor Generator Maintenance Rebuild cryo expansion engines Rebuild Solenoid power chokes – requires lab support Rebuild water cooling system in Solenoid PEI power supply Replace all water hoses on solenoid dump switches and power bus leads Install Gas Filtering System on COT recirculation system Place a subset of on-line computers on diesel generator

6 My Major Worries At This Moment  COT Aging  No evidence to date – slides to follow  Still early in FY05  We have not had luminosities above 80e30 yet  Survivability of CDF Electronics in the Collision Hall  A number of “single event upset” problems as of late during the ramp, squeeze and scrape  Losses during the store have been outstanding for the most part  Physicist Manpower  Beam Incidents  Losses  Kicker Prefires  D0 Pots

7 COT Operations in FY04 COT Experienced Significant Aging Feb 13-May 15, we operated the COT in a compromised state while we attacked the problem Assembled a team of International experts to help us determine a direction Problem has been “fixed” if not fully understood Adding 100ppm of Oxygen to the Ar-Eth Gas

8 COT Aging Status as of today Still Not fully understood but no signs of aging at the moment Still Adding Oxygen and monitoring closely Building a Filtering system to pass recirculated gas through

9 Upgrade Projects  Completed Projects EM Timing Installation on the central calorimeter Calorimeter Crack/Preradiator installation  Work in Progress Modify Existing TDC’s with fast clear option Install PULSAR Level 2 trigger system Install new Event Builder Install new XFT stereo trigger system Install new Secondary Vertex Trigger (SVT)

10 Pulsar System The new Level 2 trigger decision system Currently installed and operating in parallel with our existing level 2 system (using fiber splitters to allow this) Hardware is complete Firmware development and testing is in progress Have had several internal reviews of this system Committee’s belief that this system will be fully operational and turned over to the Operations Crew as the new Level 2 trigger decision system by March 1 st

11 TDC Upgrade Goal is to modify ALL existing TDC’s with this “fast clear” feature –Provide a larger pool of spares –Make Operations easier by minimizing the “flavors” of TDC boards In reality, only TDC’s used for SL’s 5 and 6 need to be modified – 90 of the 204 required for SL 5-8 Plan is to modify current spares pool immediately Swap a crates worth of modified TDC’s during accesses of an appropriate length (several hours) Plan is to complete most of this upgrade work prior to the shutdown – PPD Tech’s have already started modifications Shutdown will be used to finish up the remaining details If for some reason we start this job during the shutdown, we would have enough time to complete SL5 and 6 in the 8 weeks.???

12 XFT Upgrade  Requires some work in the collision hall  Route fiber optic cables from the first floor to each of the COT TDC crates on the detector  Install transition boards on all of the stereo TDC slots  Install XTC cards on at least SL3 (5 and 7 will hopefully be done in conjunction with the TDC work)  Again, we plan to make use of accesses during the FY05 run to get as much of this done as possible prior to the shutdown  Commissioning can be done in parallel – should have minimal impact on data taking efficiency

13 Event Builder  All Hardware resides in our counting rooms  To speed up readout time, we will install more crates and have fewer VRB’s/crate  Given Board density, power and heat load in any given crate is low, we can install as many as 3 VME crates/rack.  Simplify installation and not impact our spares pool  Most of this work can be done while we are taking data with no impact  Can test in parallel – should have minimal negative impact on operations

14 SVT Upgrade  Hardware resides fully in our 2 nd floor trigger room  Of the upgrades, this is the most disruptive  Can not be done in parallel  Once you begin, you can’t go back easily  Requires hardware and software to be ready before we can begin  We will try to minimize the downtime by performing vertical slice tests  We must integrate these crates of electronics with the rest of our trigger/DAQ system

15Schedule  Microsoft project file for the shutdown in progress.  Many of the jobs we have done before so estimates are solid  We can fit all of our jobs well within the 8 week time allotment

16Labor  Manpower Assumptions We will staff the control room 24x7 with a scientific coordinator and a DAQ expert on day and evening shift We will be taking all of the process systems technicians off shift rotation for the first 6 weeks of the shutdown. We will use ALL of the technicians currently assigned to CDF We will be asking for mechanical rigging help from the mechanical support department – 1 week total Usually require a few COT tech’s for ~2 weeks We will require alignment help

17 Summary of 2005 Shutdown  A fair amount of work to do in 8 weeks  We have an experienced crew that has been through this several times before  Most of the jobs are similar in nature to other work that we have done that we have a high comfort level