1 MICE PM Report Phase One installations to date Some problems with target & Decay Solenoid Phase One remaining items, schedule & milestones Progress with.

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
CMPB Alain Blondel 14 April STATUS OF MICE.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 MICE-Video Conference Status of MICE Hall Contents: General status Electrical Mechanical Preparing for Steps II & III Risks and worries Andy Nichols,
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
UKNF/MICE PSAG, 3/5/11 Spectrometer solenoids: –Repair plan still ‘in approval’, already two months late –Workshop/mini review at LBNL 10 th /11 th May.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 MICE PSAG PM report Brief overview Re-planning the project Solenoids, decay and spectrometer Open issues and worries Andy Nichols, STFC, PSAG, 5/5/10.
MICE status. Mice layout Beam line elements (including channel magnets) Detector components Civil Engineering Software target Decay Solenoid Beam Stop.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Technical Board Summary Alan Bross MICE CM17 CERN February 25, 2007.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 MICE CM25 Engineering Session Summary Contents: Infrastructure Diffuser Coupling Coils Radiation Shutter AFC module EMR Andy Nichols, STFC, 4-7 th November.
S A Griffiths CM42 June 2015 Electrical & Control.
Step IV Step IV extended through 2016 QP/QD – in progress at FNAL Target dates SSU ECE for Feb now only 20% probability – no-field Feb Remainder for April/March.
Project Manager’s Report + DC/MoM Report
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE PM Report Phase One installations to date Some problems with target & Decay Solenoid Phase One remaining items, schedule & milestones Progress with Phase Two Staffing & visitors Don’t have time for a detailed status report, have a look at: MICE CMPB, 3rd September, 2008

2 Phase One Installations to date South shield wall: –All plates except a few are fitted, aim to finish next few days –West end staircase fitted –Aluminium mezzanine & fireproofing to be installed (is already made), floor shield plates to fit –All plates now delivered –Contract troubles fixed amicably

3 Installations to date DSA PPS is installed and working –Has been demonstrated to Mark Arnold of ISIS –All PPS electrical inputs to ISIS system verified OK –Full integration with ISIS takes place when MICE reaches BS SIL2 rating – in progress, all parts are compliant –That’s when we accept as fully implemented –Currently we have extended permission to run with manually locked DSA Grateful thanks to John Alexander, Craig Macwaters and many others –Main Hall PPS planning is in progress: –Meeting in late September with ISIS at JA’s request to confirm plans

4 Installations to date Mound excavation: –The hard work is done! –Digging and shoring complete, need to fit vacuum ducts then backfill –Approval from ISIS given to continue after next run starts, subject to radiation survey (this is a crucial step)

5 Installations to date Progress with the beamline: –TOF0 now installed in DSA and cabled up but not tested –Noise pick-up problem with Beam profile monitors will be addressed in October shutdown (ISIS needs to be off) –Fixed beamstopper is made –Full sliding beamstopper at end of DSA will be late due to design & manufacturing difficulties, but: –We do have an approved by ISIS remotely operated system in place, so can run if necessary –TOF1 will come to RAL on mid-September by RAL transport –No changes with KL or cKOV –Every endeavour to finish heavy civil work by mid-end November – this dictates when tracker/readout can be integrated in Hall, effectively the start of step two –Diffuser is almost done at Oxford, but needs lower mass version of can end plate – comes to RAL 20 th October

6 Problems with Target & Decay Solenoid Decay Solenoid: –Oil leak on compressor – fixed quickly –Compressor unit still over sensitive to ambient conditions –Hot week in July caught us out – it failed –Fixed by temporary air conditioning –Long term fix is: Install permanent A/C – in the plan and paid for Or buy water cooled compressor (60 KCHF?) –But the solenoid finally got cold –Power test revealed a normal coil –Some minor re-wiring needed before we could be sure –Getting clearer, latest news it’s probably the coil nearest the end cap – joint between current leads and superconductor – quite good news, but still don’t know for sure –What do we do…..? –Best case is to remove end cap from in-situ solenoid

7 Problems with Decay Solenoid and Target Remove end cover Also need to remove BPM Withdraw D2 to park position Mike Courthold is working on plan Do it in short October shutdown (20 th -30 th ) Need to construct temporary hoist In DSA under access platform

8 Problems with Decay Solenoid & Target But worst case is to withdraw cold mass –Need to do this at Christmas shutdown –Tooling needs to be recovered from PSI –And some parts designed & made –Awaiting detailed workplan Withdraw D2 Re-install rails Remove part of Shield wall

9 Problems with Decay Solenoid and Target Target: – Target #1 arrived in July, ran and failed after a short time –This was planned to go in ISIS! –The shaft seized badly in the bearings –DLC coating completely chewed up –So we took it to bits –First suspicion mechanical misalignment of bearings –Metrology proved OK at 20 micron level –Could the magnetic axis be tilted causing side load on shaft –Tom Bradshaw is checking – not easy though –Current target in ISIS still OK, but we don’t now have a demonstrator –We should not be pressured to hurry with the second target till we understand the failure

10 Problems with Decay solenoid and target What to do? –ISIS has approved 60K cycles with existing online target –We do not have the scope in UK for a bottom-up target re-design –We should accept that there might always be some funny transverse forces we’ll never understand, but we should make mechanical provision for them: Redesign/make bearings Re-tolerance the shaft/bearings Address QA for DLC coatings with supplier New mechanical test programme agreed with ISIS –Meeting arranged with Sheffield group this week –And brainstorming session at October CM, including external participation

11 Problems with Decay Solenoid and Target Must remove this sharp edge DLC removed from lower bearing Ditto upper bearing Effects of seizure On target bearings

12 Phase One remaining items North Shield Wall: –Order placed with Regal Engineering in July, installation with all plates, etc complete by 24 th November. Fabrication of supports nearly done, start installation 8 th Sept. False floor –Order placed, again with Regal, completion by mid- November. Since last meeting need arisen for concrete reaction block for quench forces on floor – included with false floor order, all design work done DSA roof and walkways –Solenoid platform installed, roof panels installed, railings and gate in fabrication, aim to install around DSA while ISIS running, subject to radiation survey.

13 Phase One remaining items Fencing on R5.2 roof Roof-extract fan –Somehow escaped from previous estimates –Estimate £15K –Firm quote of £8K received, including approved access walkway across Upgrade compressed air supply: –All volume and filtration requirements now received from each subsystem, currently waiting to find if ISIS supply can cope –Estimate £12K –mound, still exploring ‘Well-Found Lab’ route for payment, but…..last minute change of height to 1.8m request from ISIS, so need to go round again –Estimate £10K Main Hall door upgrade –ISIS pays apparently, must do before December, as Hall- PPS critical RF refurbishment –Restoration/Installation costs - £30K, firm quote

14 Phase One Remaining items LH2 Installation: – September installation for prototype system will certainly slip to November/December 2008 – this is now confirmed –Two more safety reviews required: Hazop 2 review, by Serco, prototype control system needs to be finalised first Final safety review (RAL-ISIS-MICE) Both being organised by Jane Vickers & Mike Courthold for October –A concern: the same very overloaded group is responsible for: Decay solenoid Focus coils LH2 implementation –They cannot work in parallel or work pro-actively – the cuts we made will make this worse, not better. The Decay solenoid problems should be a warning!

15 Phase One remaining items Rolling platforms 1 & 7 delayed by yet more problems with subcontractors Contractors visited – delivery end September – this is believable Fundamental part of step two, but off critical path (just) due to spectrometer solenoid difficulties – see later Design work in progress for cheaper rolling platform 2-6 substitutes

16 Progress with Phase Two Organisation: –Blondel,long, Zisman, Nichols met in early July to discuss the shape of the UK Phase Two project over four years, with all known constraints –Action: Nichols to produce both technical and resource- limited project plans –Need realistic date targets from each subsystem, aim to do by series of reviews – October CM convenient time to start Phase Two deliverables: Spectrometer solenoids –(Although part of UK Phase One), problems with spectrometer solenoids –Magnet #1 is being cooled by contractor (Wang NMR), but needs independent LN2 supply to cool rad shield –Also vent pipework is inadequate cross-section –What this means for us:

17 Progress with Phase Two –A delay to step two, first magnet was due at RAL end August –Both of the problems ultimately require dis-assembly of magnet – not trivial –Might be sensible to do that on magnet #2 and shift priority to that –And/or postpone field mapping till later in project – currently planned at FNAL and due to take six weeks –Impossible to forecast delivery date yet, but it’s hard to see the first solenoid arriving in UK before end November Coupling coils –Staffing problems at Harbin with subcontractors – now back on track, but probably six months’ delay for the first (MuCool) coil –Productive design review at June CM, will follow up in October

18 Progress with Phase Two Focus Coils –Preliminary design review at Tesla Engineering in August was a failure – little evidence of progress with detail design, thermal and structural calculations –Made large action list for them – will re-convene on 18 th September –MICE formally expressed their dis-satisfaction to Tesla Project Manager –Good news is delivery schedule still looks OK and there don’t appear to be any gaping open design issues

19 Staffing & Visitors Over the last few months a good number of collaborators have come to MICE Feedback seems to be good The monthly cycle of MOMs (MICE Operations Manager) was a good idea and works well We have streamlined the visitor induction/safety process to avoid repetition (with full approval of RAL H&S) Local transportation is a problem, but we now have a van Tricia, Susan and the ISIS user office have been a huge help Four candidates have been shortlisted for the MICE admin/liaison post, interviews on Thursday