17 February 2009 ERCOT Board of Directors Texas Nodal Market Implementation: Program Update Trip Doggett Sr. Vice President and Chief Operating Officer.

Slides:



Advertisements
Similar presentations
Program Management Office (PMO) Design
Advertisements

June 26, 2008 TAC Texas Nodal Market Implementation: Program Update Jerry Sullivan.
Project Process Discussion Adam D. Martinez Mgr, Market Ops Divisional Projects Organization ERCOT RMS Meeting May 10, 2006.
1 April 2010 TX SET Timeline Project Conceptualization 11 weeks Market Requirements 12 weeks ERCOT Requirements 12 weeks Conceptual Design 6 weeks Detail.
Pertemuan Matakuliah: A0214/Audit Sistem Informasi Tahun: 2007.
Page 1 Program Management Office “PMO” Update Steve Wallace February 3, 2003.
1 Project Update and Summary of Project Priority List (PPL) Activity RMS August 4, 2015.
January 8, 2009 TAC Texas Nodal Program Implementation: P rogram Update Ron Hinsley.
Lead FromThe Front Texas Nodal May 17 th 2006 – Nodal Organization V1.5 1 Getting physical – high-level packaging for delivery accountability Commercial.
1 Texas Nodal Texas Nodal Program Implementation TPTF June 6, 2006 Agenda.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
ERCOT and Utilicast Public Document ERCOT Board of Directors Meeting April 22, 2009 Nodal Program Oversight Report 10 – Infrastructure.
April 9, 2009 Technical Advisory Committee Meeting Texas Nodal Program Implementation: Program Update Mike Cleary Sr. VP and Chief Technology Officer.
Market Implementation Board Presentation October 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program status.
1 Single Entry Model (SEM) Go-Live Update ROS Update July 16, 2009.
Texas Nodal Program ERCOT Readiness Update TPTF March 31, 2008.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation TPTF Nodal Status Update November 6, 2006.
Market Implementation Board Presentation July – v1.1F 1 Texas Nodal Market Implementation ERCOT Board of Directors Meeting Program.
March 20, 2008 TPTF CIM Update Raj Chudgar Program Director for Market Redesign.
Texas Nodal Timeline Options, TPTF Jul 11, Timeline Options Trip Doggett TPTF
September 8, 2008 TPTF Nodal Core Projects Updates Nodal Project Managers.
A Strawman for Discussion by Dottie Stockstill & Greg Ramon Special ERCOT Board Meeting June 24, 2003.
TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.
February 5, 2009 Technical Advisory Committee Meeting Texas Nodal Program Implementation: Program Update Trip Doggett.
ROS Meeting – 05/15/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 05/15/08.
1 Business Integration Update to PRS January 19, 2012.
January 15, 2008 Monthly Board of Directors Meeting Texas Nodal Market Implementation Program Update Jerry Sullivan.
1 Project Update and Summary of Project Priority List (PPL) Activity July 16, 2015.
Lead from the front Texas Nodal 1 Integrated ERCOT Readiness and Transition (IRT) TPTF - November 6 th, 2006.
1 Project Update and Summary of Project Priority List (PPL) Activity June 11, 2015.
September 25, 2007 TPTF Meeting Texas Nodal Program Update Jerry Sullivan.
PMO Update to PRS Troy Anderson ERCOT Program Management Office December 17, 2009.
Reconfiguring Nodal Stakeholder Participation Presentation to the ERCOT Technical Advisory Committee Texas Nodal Transition Planning Task Force February.
Texas Nodal Market Implementation Metric Sub Group Readiness Advisor January 30, 2006.
Impact Analysis and Feasibility Study Review – NPRR164, NPRR169 and SCR752 Troy Anderson ERCOT Program Management Office January 15, 2009.
PMO Update to PRS Troy Anderson ERCOT Program Management Office January 21, 2010.
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation ERCOT Board Of Directors – August 15, 2006 TPTF Meeting August.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management May 19, 2011.
PMO Update to PRS Troy Anderson Program Management Office February 22, 2007.
Nodal Program Update Mike Cleary Sr. VP and Chief Technology Officer.
August 25, 2008 TPTF Nodal Status Report: Integrated Schedule Update Change Control Update Adam Martinez Troy Anderson.
Texas Nodal Program ERCOT Readiness Update TPTF June 23, 2008.
TPTF CIM Health Check Raj Chudgar Program Director for Market Redesign.
ERCOT Market Services Organization Dale Goodman Director, Market Services (office) (cell) (fax)
Lead from the front Texas Nodal 1 Texas Nodal Market Implementation Program Implementation Scenarios September 6, 2006.
1 Project Priority List (PPL) Update Troy Anderson ERCOT Enterprise Project Portfolio Management January 2011.
September 22, 2008 TPTF Nodal Status Report: Project Status Updates Nodal Project Managers.
PMO Update to PRS Troy Anderson ERCOT Program Management Office June 17, 2010.
August 11, 2008 Texas Nodal - Integrated Schedule Update Integrated Schedule Update for TPTF Janet Ply.
August 27, 2007 Executive Committee Meeting Texas Nodal Program Update Jerry Sullivan.
1 Texas Nodal Texas Nodal Program Implementation TAC July 6, 2006 Agenda.
1 SCR756 – Enhancements to the MarkeTrak application –Fondly called - MarkeTrak Phase 3 –ERCOT CEO determined that SCR756 is not necessary prior to the.
Network Operations Model Go-Live Decision Kenneth Ragsdale TAC July 1, 2010.
October 2, 2008 TAC Texas Nodal Market Implementation: Program Update Ron Hinsley.
January 3, 2008 TAC Meeting Texas Nodal Program Update Jerry Sullivan.
June 5, 2008 TAC Texas Nodal Market Implementation Program Update Jerry Sullivan.
ROS Meeting – 06/12/081Texas Nodal Program - TPTF Update Texas Nodal Transition Plan Task Force ROS Meeting Stacy Bridges, ERCOT Thursday, 06/12/08.
October 27, 2008 TPTF Nodal Status Report: Program Update Ron Hinsley.
1 Single Entry Model (SEM) Go-Live TAC Update May 7, 2009.
1 Business Integration Update to PRS Troy Anderson ERCOT Enterprise Project Portfolio Management October 20, 2011.
1 Single Entry Model (SEM) Go-Live Update TAC Update August 6, 2009.
October 13, 2008 TPTF Nodal Status Report: Program Update Ron Hinsley.
IS&T Project Reviews September 9, Project Review Overview Facilitative approach that actively engages a number of key project staff and senior IS&T.
PMO Update to PRS Troy Anderson ERCOT Program Management Office May 20, 2010.
March 5, 2009 Technical Advisory Committee Meeting Texas Nodal Program Implementation: Program Update Trip Doggett.
2011 Prioritization Update to Market Subcommittees
Troy Anderson ERCOT Program Management Office November 6, 2008
By Jeff Burklo, Director
Presentation transcript:

17 February 2009 ERCOT Board of Directors Texas Nodal Market Implementation: Program Update Trip Doggett Sr. Vice President and Chief Operating Officer

2 ERCOT Board of Directors17 February 2009 Agenda Program Highlights Utilicast Report 8 – Audit Points to Address Detailed Risk Status –Nodal Program Risks –ERCOT Enterprise Risks that Affect the Nodal Program Budget – Forecast/Actual Trend Stand-alone Benefits

3 ERCOT Board of Directors17 February 2009 Program Highlights Since the schedule was replanned June 1, 2008, all tasks on the program critical path are currently on schedule –Of 16 scheduled tasks on the critical path (to date), the program has hit 16 –Of 2,575 total scheduled tasks (to date), the program has hit 2,262 Core projects and associated releases NMMS Delivered a validated model (v1.21 schema and data set) on Jan. 9. The delivery of the validated model ensures that data can be utilized from the new Nodal network model in downstream systems (MMS and EMS). Started functional acceptance test (FAT) for NMMS 6 release on Jan. 19; scheduled to complete by Mar. 17 EMS Started FAT on Release (release to address several SIG issues and NPRRs 97 & 102) on Jan. 7; scheduled to complete by Feb. 6 MMS Completed FAT testing for MMS4 Patch6 (CIM importer additions, partial NPRR113, and partial SIG Rounding Paper) on Jan. 9 Received MMS4 Patch7 from ABB on Jan. 23; release is currently undergoing smoke testing to prepare for start of structured testing in FAT COMS Completed FAT of COMS integration with MMS4 Patch6, remaining billing determinants and smoke testing integration between Settlements and Billing and Credit Monitoring System on Jan. 30

4 ERCOT Board of Directors17 February 2009 Utilicast Report 8 Audit Points to Address – 1 IDDescriptionAction PlanTarget Date UTI08-01The individual project budgets should be challenged in the following areas: a. Vendor contracts b. Contract staff c. Internal staff a.Long –term vendor contracts will be negotiated with the assistance of a 3 rd party negotiator, to address budget matters as well as others. 3 rd parties are being interviewed at this time b, c. Plans for use of contract staff, as well as the orderly transition to ERCOT teams are being examined, as we refine the schedule and plan for the remainder of the schedule a)2/17/09 for 3 rd party negotiator decision; 6/30/09 for contracts to be renegotiated for top 5 vendors b)Integrated schedule is being re-planned incrementally, with full re-plan to be complete in March, 2009 UTI08-02Given the high risks of the integration phase of the Nodal Program, this area should be reviewed in detail and be the subject of Nodal Oversight Report 9. This item is closed. The integration phase of the Nodal Program was made the subject of Nodal Oversight Report Number 9. Closed, 2/2/09 UTI08-03Scope for the December 2010 release of the Nodal Program should be locked down with any proposed changes subject to a strict change control process. This item is closed. There is now a clear policy supported by the Board of Directors that any change that affects Nodal schedule and budget must by approved by the ERCOT CEO and Board of Directors. Expect board approval of PRR799 on 2/17/09

5 ERCOT Board of Directors17 February 2009 Utilicast Report 8 Audit Points to Address – 2 IDDescriptionAction PlanTarget Date UTI08-04No enhancements should be considered for zonal market applications or processes unless assessed as business critical. This item is closed. The ERCOT PMO is carefully monitoring Zonal project work, with guidelines in place to avoid use of Nodal resources. As of 1/30/09, there are no known requirements for use of Nodal resources in the work for Closed; 1/30/09 UTI08-05There should be immediate investment in new data center capacity to allow for expansion of IT infrastructure to support the Nodal Program. A project has been initiated to expand the data center in Taylor (PR-80047). The planned occupancy date is September The plan to add or move hardware is under development. Additional data center space is planned as part of the Met Center disposition project (PR-80001). Those data centers should be online in early Plans are under development to provide capacity prior to those new data centers becoming available. Early 2011 UTI08-06Given the risks of market readiness and Market Participants potentially delaying "Go-live" due to ambiguous EDS exit criteria, this area should be subject to a detail review. as of 2/4, this recommendation on hold at the request of Utilicast. They want to discuss the subject of Report #10 with the Special Nodal Committee. 2/10/09 – next meeting of the Committee

6 ERCOT Board of Directors17 February 2009 Nodal Program Risk: Integration Testing Strategy Needs Updating Risk: Integration Testing Strategy Needs Updating The existing integration testing strategy (e.g. planning approach, team structure, methodology) may not be adequate to successfully perform integration. Risk Life Cycle State DefinePlanManageWatch Mitigation PlansWhoTarget DateCurrent Status 1. Identify leader for the entire Enterprise Verification effort (interface and end-to- end testing, market trials and system cutover) J. Ply1/13/09Complete; Linda Clarke named as the Nodal Enterprise Verification Lead 2. Develop high level approach for Enterprise Verification. L. Clarke2/16/092/6/09 - Work is in progress; high level approach was discussed with project managers this week 3. Review and refine the leadership and staffing levels for Nodal Enterprise Verification. L. Clarke2/27/092/4/09 – Work is in progress, with organization structure established Key positions to be filled by end of February.

7 ERCOT Board of Directors17 February 2009 Nodal Program Risk: Nodal Integration Test (iTest) and EDS Environments Risk: Nodal Integration Test (iTest) and EDS Environments Because the current iTest environment is set up in the EDS (passive) environment, and because it lacks all of the required platform software and permissions, the Nodal program cannot effectively conduct integration testing. Delays in integration testing threaten program delivery. Risk Life Cycle State DefinePlanManageWatch Mitigation PlansWhoTarget DateCurrent Status 1. Review current iTest environment and strategy. K. Meinen2/6/09Complete 2. Establish a detailed plan and project schedule for key activities and milestones to establish and maintain the iTest environment. Include elements such as: –Ensure all technical architecture documents are current –Deploy all needed HW –Install all Nodal systems, with required components –Establish release procedures with appropriate controls –Ensure iTest environments match needs of integrated testing strategy K. MeinenTBD2/6/09 Identified elements for initial iTest environment, to be complete 3/20/09 Detailed plan is under development

8 ERCOT Board of Directors17 February 2009 ERCOT-Wide Risk: Zonal Resource Constraints for Nodal Program Risk: Zonal Resource Constraints for Nodal Program Because the Nodal go-live date has been delayed, there are a number of Zonal projects, PRRs, and IMM suggestions for Zonal improvements that may result in resource constraints for the Nodal Program. Risk Life Cycle State DefinePlanManageWatch Mitigation PlansWhoTarget DateCurrent Status 1. Manage list of PRRs and SCRs to a resource plan that uses a strategy to avoid impacting Nodal personnel resources when delivering additional Zonal enhancements. D. Troxtell T. Anderson ongoing1/30/09 – Completed review with PRS and WMS on the current list of reconsidered and new PRRs and SCRs. No expected impact to Nodal. Updates will be provided to Nodal PMO as the list evolves. March/09 – To review the list with TAC 2. Manage Project Priority List (PPL) with clear view of resources needed for any projects in flight or about to be launched, with a strategy to avoid impact on Nodal personnel resources. D. TroxtellOngoing1/28/09 – Current PPL shows no threat to Nodal personnel resource; updates to be provided to Nodal PMO as the PPL evolves; sent the list to Nodal PMO.

9 ERCOT Board of Directors17 February 2009 ERCOT-Wide Risk: Data Center Space Concerns Risk: Data Center Space Concerns Data center capacity, space, and power may be inadequate for Nodal Program go-live, unless plans for expansion are adequate. Risk Life Cycle State DefinePlanManageWatch Mitigation PlansWhoTarget DateCurrent Status 1. Establish an Information Lifecycle Management approach, to manage the life cycle of data being managed. R. HinsleyRoadmap by March 6 Implementation ongoing ERCOT project PR 90006_01 Commercial Systems Information Lifecycle Management: Project SAIC to be Project Manager SAIC is engaged to complete a roadmap for a strategy by March Expand current data center space, and build out new data center, to increase ERCOT data center capacity. R. HinsleyTCC1 build out complete by 9/09 South DC in production Feb 2011 TCC3 in production May 2011 ERCOT project PR_80047 TCC1 equipment to be purchased May ERCOT project PR_80001 South DC will run parallel Oct 2010 – Feb 2011 to test and avoid disruption to Nodal 3. Validate and monitor Nodal data capacity assumptions R. HinsleyMay 2009Study underway to validate current assumptions ERCOT-Wide Risk:

10 ERCOT Board of Directors17 February 2009 Measures and Trends Nodal Program – Cost Management Please note: forecast numbers are preliminary until approved by the BOD and the PUCT PRELIMINARY

11 ERCOT Board of Directors17 February 2009 Stand-Alone Benefits Resulting from Nodal Activity To Date ItemDescription Hardware/ Infrastructure Usable for either Zonal or Nodal efforts. NMMSReusable with some retool efforts to address interfaces to EMS and MOS. COMS – Credit Monitoring Reusable with some retool efforts to address Zonal market. COMS – Data Aggregation Performance enhancements to application are reusable. Outage SchedulerReusable with some retool efforts to address interfaces to EMS and MMS. Wind Forecasting Tool The AWS Wind Forecast Service and related applications are usable in Zonal. Mid-Term Load Forecast (MTLF) Tool The enhanced MTLF is usable in Zonal. TrainingSome general education modules developed by Nodal can continue in a Zonal market.

Questions ?