D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K.

Slides:



Advertisements
Similar presentations
MICE Collaboration MTG IIT – Feb 2002 The Fiber Tracker Option for MICE Spectrometers The D0 Central Fiber Tracker – Experience and Implications for MICE.
Advertisements

DoE Review June 6-7, 2000 Current Detector Configuration June 6, 2000  Solenoid, Central Preshower installed in central bore  A-layer MDTs installed.
Status of Eric Kajfasz CPPM/Fermilab GDR-Susy, Lyon - 26 novembre 2001.
MICE Video MTG 9/25/2002 MICE Fiber Tracker Design Update Requirements and Proposed Detector Implementations A. Bross Fermilab.
Linda R. Coney – 24th April 2009 Online Reconstruction & a little about Online Monitoring Linda R. Coney 18 August, 2009.
J. Estrada - Fermilab1 AFEII in the test cryostat at DAB J. Estrada, C. Garcia, B. Hoeneisen, P. Rubinov First VLPC spectrum with the TriP chip Z measurement.
CFT Calibration Calibration Workshop Calibration Requirements Calibration Scheme Online Calibration databases.
Fiber, Ribbon Production and Cryo Update Alan Bross Tracker Phone October 26, 2006.
13 January All Experimenters’ MeetingAlan L. Stone - Louisiana Tech University1 Data Taking Statistics Week of 2003 January 6-12 We had to sacrifice.
Main Injector at Fermilab. Silicon Vertex Tracker Integrated system of barrels and disks ~ 800k total channels.
EPS 2003, July 19, 2003David Buchholz, Northwestern University Performance of the D0 Experiment in Run II Detector Commissioning and Performance Accelerator,
Takashi Matsushita Imperial College T. Matsushita 1 Tracker Status.
1 MICE Tracker Update M. Ellis UKNFIC Meeting 25 th August 2005.
CM26 March 2010Slide 1 EMR Status o Intro o Construction o Magnetic shielding o Electronics o Prototype Cosmics test o Schedule Jean-Sebastien Graulich,
1 MICE Tracking Detectors Malcolm Ellis NFMCC Meeting 12 th March 2006.
Collaboration Mtg Cotober 11, 2000 Installation Status Opening Remarks Overview, logistics Recent events, status Outlook, concerns Conclusions Jon Kotcher.
January 22, 1999SciFi L1 Trigger Review 1 Analog Hardware Front-end Board (CTT_FE) –Transmit (and split) the VLPC signal to the Multi-chip Modules –Discriminate.
NIU Trigger Workshop CTT Commissioning Trigger Workshop October 22, 1999 WBS & Presented by Fred Borcherding for the D0 Electronics Group.
D0 PMG 12/2/99 Fiber Tracker Status  Carbon fiber work u All support cylinders done u Some work remains on band/support pieces + work for Silicon Detector.
Fiber Tracker Update Edward McKigney Imperial College July 3 rd, 2002.
Tracker Summary Alan Bross MICE CM October 10, 2007.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
22 June 2000 D  NIU Workshop S. Doulas From Detector to Ntuples: Muons Steven Doulas Northeastern University Boston, MA D0 Muon Upgrade Group.
Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer 8/12/2008 1David Lissuaer, Santa Cruz Meeting.
D0 Collab Mtg Feb 7, 2001 D0 Detector: Status for Run 2 Wistful reminiscences Near term: Roll in, detector status, next few weeks Latest from Beams Division.
Don Lincoln, Fermi National Accelerator Laboratory, Instr’99, November 1999 Characterization and Performance of Visible Light Photon Counters (VLPCs)
PMG, Aug 03, 2000 Slide 1 Schedule In preparation Done Started Done Started Half done.
All DØ Meeting, 12/01/00 Central Fiber Tracker Light Guide Performance Thomas Nunnemann Fermilab 90 days before RunII … (a.k.a. 12/01/00)
7 Feb 2005T. Yasuda, Fermilab D0 Status Report 2/7/2005 Taka Yasuda Fermilab.
Fermilab PMG Jan 20, 2000 Reconsideration of the Installation at D0  Overview  Major constraints  Basics of old, new schemes  Some details on each.
1M. Ellis - NFMCC - 31st January 2007 MICE Tracker.
Forward Muon Installation and Commissioning Dmitri Denisov Fermilab Director’s review 7/12/1999 Plan Forward muon detectors Mini-drift tubes installation.
L0 Technical Readiness Review-Electronics Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage s Filter.
LHCf: installation & commissioning Measurement of Photons and Neutral Pions in the Very Forward Region of LHC Oscar Adriani INFN Sezione di Firenze - Dipartimento.
MICE Phase 1 Koji Yoshimura KEK June
HBD electronics status All the ADC and XMIT boards are installed. –Top 3 crates are for the ADC, XMIT boards –Bottom crate is for test pulse boards/future.
D0 Status: 01/14-01/28 u Integrated luminosity s delivered luminosity –week of 01/ pb-1 –week of 01/ pb-1 –luminosity to tape: 40% s major.
DØ Central Tracker Replaced with New Scintillating Fiber Tracker and Silicon Vertex Detector The DØ Central Detector Upgrade The DØ Detector is a 5000.
All Experimenters MeetingDmitri Denisov Week of July 7 to July 15 Summary  Delivered luminosity and operating efficiency u Delivered: 1.4pb -1 u Recorded:
D0 PMG 6/15/00 PMG Agenda June 15, 2000  Overview (Tuts) u Detector status u Reportable milestones u Financial status u Summary  Response to DOE review.
D0 Status: 04/01-04/08 u Week integrated luminosity –1.7pb -1 delivered –1.5pb -1 utilized (88%) –1.1pb -1 global runs u Data collection s global data.
Director’s Review of RunIIb Dzero Upgrade Installation Linda Bagby L0 Electronics Installation  System Electronics Overview u Low Voltage u High.
VLPC System Update A.Bross MICE CM Feb 9, Cryo  Production cryostats 1 and 2 ran smoothly at operating temperature  However, Cassette 109 in cryo.
Muon Tracker Responsibilities This Year South arm commissioning through this year’s run Analysis Software oversight and development North Arm station 2.
FNAL All Experimenters Meeting January 7, Leslie Groer Columbia UniversityDØ Status 1 DØ Status and Progress Dec 17, 2001 – Jan 7, 2002  Reasonably.
Aurelio Juste (Fermilab) Rencontres de Moriond, March OUTLINE Tevatron Run 2 The upgraded DØ Detector Status Performance First Physics Results Outlook.
All Experimenters MeetingDmitri Denisov Week of September 9 to September 16 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 4.0pb.
February 24, DØ’s VLPC Detectors: The Fiber Tracker and Preshowers Greg Davis University of Rochester.
FPD STATUS Carlos Avila Uniandes/UTA 1. FPD overview 2. Roman pot and detector status 3. FPD readout integration status 4. Software status 5. Stand-alone.
DoE Review June 6-7, 2000 Installation and Commissioning of the D0 Detector Overview since last review Organization Current status Installation sequence,
Detector Summary Tracker. Well, as far as the tracker hardware is concerned, we are done. – Need to do the system test to make sure nothing has degraded.
D0 PMG February 15, 2001 PMG Agenda February 15, 2001  Overview (Weerts) u Detector status u Reportable milestones u Summary  Operations Organization.
1 HBD Commissioning Itzhak Tserruya DC meeting, BNL December 13, 2006 Progress from October 3 to November 28, 2006.
D0 PMG 2/3/00 PMG Agenda Feb 3, 2000  Overview u Project Manager’s Report – Tuts u Fallback options – Weerts  Silicon Support Cylinder Modifications.
04 Feb 03 Shutdown Activities Cryostat warm-up –Dilute contaminates Use purer helium on cooldown –Thermal stress test for cassettes –Move cassette from.
Tracker Readout Progress Terry Hart, MICE Tracker Meeting, July 29, 2008 Cosmic Ray Readout with 1 st Tracker at RAL 2 nd Tracker Preparation at FNAL Firmware.
Director’s Review Dec 1999 DO Timeline Old Version J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup.
Collaboration Mtg April 14, 2000 DO Timeline J F M A M J J A S O N D J F M D Install silicon front-end ICD FPS Lum (L0) CFT install/hookup 1/2.
4 May 2006May 06 PMG - Paul R1 AFEII-t Status May 4, 2006 PMG Paul Rubinov.
D0 PMG 4/19/01 Completed Reportable Milestones MilestoneBaselineActualVar. H Half-Wedge Fabrication 20% Complete 10/15/99 0 w 3 Chip Ladder Fabrication.
All Experimenters MeetingDmitri Denisov Week of July 22 to July 29 D0 Summary  Delivered luminosity and operating efficiency u Delivered: 3.1pb -1 u Live:
Station-4 MuID System: Status Ming X. Liu Los Alamos National Lab 1/7/091E906 Collaboration Meeting.
The ICD Project Alan L. Stone Louisiana Tech University All D0 Meeting - 7 September 2001.
CDMS II Shielding To Installation To Construction From Design.
Evelyn Thomson Ohio State University Page 1 XFT Status CDF Trigger Workshop, 17 August 2000 l XFT Hardware status l XFT Integration tests at B0, including:
Status of the NOνA Experiment Satish Desai - University of Minnesota For the NOνA Collaboration APS Meeting - April 2013 Denver, Colorado.
Nikhef Scientific Meeting 2000Onne Peters D0 Muon Spectrometer December 14-15, Amsterdam Onne Peters Nikhef Jamboree 2000.
Arnd Meyer (RWTH Aachen) Sep 8, 2003Page 1 Integrated Luminosity Total data sample on tape with complete detector > 200pb -1.
MICE VLPC Cryo Update Alan Bross MICE CM18 June 13, 2007.
HF Test station at P5 A.Mestvirishvili.
Presentation transcript:

D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?* Don Lincoln CFT Commissioning Czar Fermilab Run II Meeting May 12, Y2K * that’s John’s title, not mine

D. Lincoln Run II MTG May 12, Y2K What will it take to get data out of the CFT?  Work  Lots and Lots of Work

D. Lincoln Run II MTG May 12, Y2K Central Fiber Tracker Status  8 layers u Outer 6 s 2.52 m u Inner 2 s 1.66 m  r -.2 to.51 m  Axial readout to south  VLPC Readout  Waveguide system u m u “Pipes” light from detector to VLPCs

D. Lincoln Run II MTG May 12, Y2K CFT Status - Done Stuff  Fiber Ribbons (roughly 400 ribbons)  VLPC Characterization 17,000 chips tested, 15,500 OK  VLPC Recovery 2,200 tested, 1,100 recovered u So total useful chips 16,600

D. Lincoln Run II MTG May 12, Y2K CFT Status - Ribbon Mounting 30  m rms 50  m e-e offset Going Very Well - To Spec Last cylinder (1) getting stereo ribbons attached now Project Tomorrow completion

D. Lincoln Run II MTG May 12, Y2K CFT Status - Nesting Cylinders 8,7,6,5,4 & 3 nested CFT Completion - 5/19/00 Delivered to DAB by 6/15/00 Global precision  15  m (Measured vs Desired)

D. Lincoln Run II MTG May 12, Y2K CFT Status - Waveguides  Waveguide Production u CPS complete (IU) u Fiber pulling/sheathing at ND 75% complete for CFT s Fiber sorted –Best (attn.L from Kuraray) - longest runs [8-11.5m] u FPS at IU u CFT WG Connectorization s At ND + Fermilab + IU s 50 with curved end connectors  Expect to complete production in August (100+ July 15)  CFT Hookup and commissioning complete by 9/1/00

D. Lincoln Run II MTG May 12, Y2K CFT Status - Readout System  VLPC Characterization/test /sort now complete  Cassette Assignment u As shown (includes cassettes 1-10)

D. Lincoln Run II MTG May 12, Y2K CFT Status - Readout System II  Cassette production u Approximately 50% of sub-component complete  All components in-house except Flex circuit  Flex Circuit u Production deliveries starting s 600 of 2000 in hand   100/week

D. Lincoln Run II MTG May 12, Y2K CFT Status - Readout III  Cassette Test - Going Well u Noise low (Stereo Board) u Good uniformity

D. Lincoln Run II MTG May 12, Y2K CFT Status - Cryo  Fabrication delayed by delivery of top plates u Now in house u To spec  Making up some time u Welding going well  Final Cryo Operational in June

D. Lincoln Run II MTG May 12, Y2K CFT Status - Conclusions  CFT construction is going well u Mechanical assembly is to specification u Complete in mid-May  VLPC + Cryo u VLPC characterization/selection complete u 1024 channel cassettes working well u Cassette production assembly underway s Subcomponents 50% complete s First 10 (11?) production cassettes assembled s All cassettes leaving factory have met specifications  CFT wave guide production u Fiber pulling/sheathing going well (far along) u Connectorization underway

D. Lincoln Run II MTG May 12, Y2K Major Installation Activities During Next 3 Months April May June July Install/align CFT Platform moves: pick up EF north/south Install VLPC cryostats in platform Collision Wall down – Hi Bay full Rework EF shielding pieces End detectors installed (FPS, ICD, L0) Install N/S A-layer MDTs Install both EF shields Install gas/cooling lines in Collision Hall Rework/reassemble shielding mid-pieces Collision Wall back up Install CFT cable ductwork in platform Collision Wall down Stage/survey N/S shielding Solenoid Test Install N/S A-layer pixels Install EMC-S MDTs and pixels Crane needed Platform occupied ICR occupied CF closed; no cal preamp access survey Survey east PDTs survey Install South truss in Hi Bay, re-weld arms Forward Muon Installation Disassemble EMC-S for move to sidewalk to July 15

D. Lincoln Run II MTG May 12, Y2K DO Timeline Version N J F M A M J J A S O N D J F M D Install silicon front-end CFT install/hookup 1/2 VLPCs installed 1st CFT crate operational Waveguide production All VLPCs installed Cosmic Ray Commissioning Phase I: Central muon, DAQ, RECO, trigger, silicon front-end Phase II: Tracker Commissioning (CFT, SMT, PS), VLPCs, Forward Muon Phase III: Full Cosmic Ray Run (add CAL, full TRIG & SMT) Run II begins: Mar 1, 2001 Roll in detector Remove shield wall Beam- ready Install final CFT electronics Platform moves No Services Install/hookup/checkout SMT South halfNorth half ICD FPS Lum (L0)

D. Lincoln Run II MTG May 12, Y2K Commissioning Plan  CFT arrives DAB mid-June, install and survey (Gaston)  Cryostat install and hookup through mid June, testing cooldown followed by cassette insertion, end of June (Russ)  As waveguides hooked up (CPS, 8, 7, etc.), testing is needed  Current plan: u 2 people/crew, 2 crews/shift, 2 shifts/day, 2 LG/crew/shift u 8 lightguides/day. (300 CFT light guides  8 weeks)  Initial test, LED pulsers on the ribbons, secondary electrical. u Verify light continuity. u Verify photoelectron noise consistent with temperature and voltage u Electrical noise.

D. Lincoln Run II MTG May 12, Y2K Needed Components  CFT cylinders: In DAB mid-late June  Cryostat: Operational late-June  Cassettes: In DAB June/July (30-ish, 11 in hand now)  LHe: Tested already, hiatus early July (end iron)  Lightguides: In DAB June/July, all CPS, 100 CFT (7/8 S/A)  Cables: In house (AFE  sequencer  VRB)  DAQ: Running now  Unpacking: SVX unpacking done, some mapping remains.  Examines: Available now, will need tweaking for commissioning  Cosmics: Piggyback on muon trigger  Tracking: Cosmic tracking mostly OK, minor technical fixes  Event Display: Ready in some form

D. Lincoln Run II MTG May 12, Y2K  Front End Electronics: u AFE not available, use stereo board, limited availability  LED Electronics: u Two components, small card (300-ish), large driver/control card (10-ish) u Small cards available early June u Large controller cards maybe available mid-August...Gack!  Sequencer  VRB cable pull late July u Silicon uses same cables, need splitter, not available u Can pull the small number of CFT fiber optic cables first  CFT Online guru:  CFT Calibration guru: Not yet filled  Control/Download guru: Needed Components  }

D. Lincoln Run II MTG May 12, Y2K Summary  Much of the required components are in place for mid-July hookup/commissioning  Some aren’t  They will be