Measurement and Payment

Slides:



Advertisements
Similar presentations
1 CLIENT CONSULTANT AGREEMENT. 2 Negotiations Types of Consulting Contracts Standard Form of Contract Form of Contract General Conditions Special Conditions.
Advertisements

Change Order Missouri Local Programs How to Complete a Change Order & Get it Approved.
Field Orders on Construction Contracts Guidance Document CLC-8 May 13, 2013.
ISTISNA’.
CONTRACT A binding agreement between two or more parties for performing, or refraining from performing, some specified act(s) in exchange for lawful consideration.
Payments to Individuals  Independent Contractor/Consulting Agreements Purchasing Presented by: Michelle Hodge.
Funds administration, also referred to as funds control, funds disbursement, funds management, and escrow, is a method that sureties use to offset the.
Presenter: Victor C. Tyler, P.E. Estimating and Bidding Strategies that Drive Best Practices.
Chapter 12 Estimate Summaries and Bids. Bid Summaries The format of the summary depends for what the estimate is to be used. –Ordering materials –Calculating.
4/13/2017 1:54 PM.
1 MOSS ADAMS LLP | 1 Case Studies in Contract Close Out Audits May 2014.
Contract Law 2014 NCHCA Education Series- January 23, 2014 Presented by Geoffrey Cantello, City of Ottawa and Ron Price, Rasmussen Starr Ruddy LLP.
MERCHANDISING COMPANY
DPW General Conditions Articles 32 through 37. Articles Covered Today  32 Owner’s Right to Withhold Payment  33 Owner’s Right to Stop Work and Terminate.
OCR Payment Process Training 01/17/2012. Article 9 – Compensation and Payment General Conditions – Article 9 – 9.1 Preconstruction Stage Compensation.
Resolve Business Disputes and Select and Prepare a Construction Contract Lesson Seven Cert IV - M. S. Martin March 2012.
On-Call Signal Contract Options for Discussion March 13, 2015 Cape Cod Joint Transportation Committee.
Cost Planning & Scheduling CTC-415. Bid Estimate Becomes the project budget upon signing of contract Can cost load the schedule –Effective means of cost.
Material Management. Materials should be ordered early –Minimize risk of price inflation, lack of materials –Just in time delivery minimizes space required.
Introduction -Discussed preparation of the overall plan for the project - as well as its implementation. -The control system quantitatively measures actual.
Estimating CTC-415. Estimate Types Concept Detailed Definitive.
PROCEDURES FOR SELECTING THE CONTRACTOR
ANSI/EIA -748 EVMS 32 Guidelines National Aeronautics and Space Administration.
XII- COST CONTROL, MONITORING & ACCOUNTING
EM15 – Contractors COST MANAGEMENT
Chapter 1 Introduction to Cost Estimates What is an Estimate? An estimate is an evaluation of a future cost. A building cost estimate is an attempt to.
Change Orders. Build the project that was bid and awarded.
Procedural Requirements For Force Account Work on Federal and State Projects 2015 ACCA Conference Orange Beach, Alabama.
Completing the State Aid Payment Request (SAPR). Tips Each spring check on the State Aid Finance web page for the current version of the State Aid Pay.
Center of Islamic Finance COMSATS Institute of Information Technology Lahore Campus 1 Adopted from open source lecture of Meezan Bank. Customized for best.
Construction Contracts and Project Delivery Methods
Kenneth D. Fenton P.S. Clark County Engineer’s Office.
Is Your JOC Program Audit Worthy? z Scott Creekmore.
Cost and Time Control. Project completed on time and on budget –Want to get done early –Lower costs –More profit.
Fees, Hourly Rates and Invoices. What is an Hourly Rate? The rate of pay per hour for a job being performed. An ‘ hourly ’ worker may be assigned to various.
Needles Powers Principles of Financial Accounting 12e Accounting for Merchandising Operations 6 C H A P T E R ©human/iStockphoto.
Measurement and Payment. Construction Progress Payments –Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed.
Measurement and Payment
CHANGE ORDER & BACKCHARGES PREPARED BY ABDULAZIZ M. AL-BESHR ID# PREPARED FOR Dr. ABDULAZIZ BUBSHAIT.
Construction Materials and Workmanship. All workmanship, materials, equipment, and articles incorporated into the work are to be of the best available.
TYPES OF CONTRACTS.
ARC 807: Professional Practice and Procedure Department of Architecture, Federal University of Technology, Akure, Nigeria ARC 807: Professional Practice.
Chapter 15 Payments. Payments typically made monthly. Retainage typically withheld (5% - 10%) Project payment: –series of periodic payments –single final.
CONSTRUCTION ADMINISTRATION Measurement and Payment Dr. Alaattin Kanoğlu Spring, 2013 Professional Practice Management I.B.U. Architecture Undergraduate.
Estimates and Quotes Apply procedures to develop plans, estimates and quotes Objective 4.03 Remember key terms, abilities needed, and items included in.
Cash Flow Analysis Part 2 King Saud UniversityCE511- Construction Planning & Control 1.
Volvox Understanding the Budget Angela Pettit – Contracts Officer.
Project Cash Flow.  In order to make a workable project plan, the resources needed for the project and their availability must be checked.  Money is.
Measurement and Payment Module #5 Prepared by Dr. Randy R. Rapp July 2005.
CONTRACT PRICING ALTERNATIVES Presented by: Fahad H. Al-Anazi CEM 520 February 27,1999.
CE 366 PROJECT MANAGEMENT AND ECONOMICS Robert G. Batson, Ph.D., P.E. Professor of Construction Engineering The University of Alabama
Submittals. Submittals key to quality management of project Document or product turned in by construction team to verify that what they plan to purchase,
Construction Eng 221 Project Management and Administration.
Chapter 13 Estimates for Remodeling Work
American Recovery and Reinvestment Act of 2009 Energy Efficiency and Conservation Block Grant Program Small City and County Grant Kick-Off Meeting California.
TOPIC-7- PROJECT CASH FLOW
Unit Price Billing Christine Borato Why use Unit Price Billing? For clients who work for the Department of Transportation, cities or counties To bill.
Collaboration of Entitlement and Cost Efforts in Claims Analysis Rubino & McGeehin Consulting Group June 27, 2005.
HORTICULTURE II - LANDSCAPE Unit B Landscape Design.
COST PLUS. Reasons for Cost-Plus Can’t agree on a price Specialty work Notice of Changed Conditions.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
Estimating Project Costs
Total Reinforcment Solution “So you can work on something else”
TOPIC-7- PROJECT CASH FLOW
Completing the State Aid Payment Request
TOPIC-7- PROJECT CASH FLOW
ARCH 435 PROJECT MANAGEMENT
Practical Aspects and Running of the Project
C2 Follow the Capital Risks
Directed Change Constructive Change
Presentation transcript:

Measurement and Payment

Construction Progress Payments Contractor gives a bill for progress to RPR Outlines what bill is for Give details as needed (quantities) RPR reviews Approves (sends to owner) or disapproves (calls contractor) Contractor gets paid

Approval of Payment Requests RPR responsible for checking quantities and costs Quantity take off Inventory of equipment and materials on site but not used Field measure work completed or claimed Construction Cost Estimate of all completed work Audit of Invoices and costs Review of claims for extra work and completed change orders Check of retention amount Check method used for profit and overhead, material costs for estra work or change orders

Basis for Payment Amounts Accuracy of field measurements determined by contract type Lump sum contracts do not need accurate field measurements Cost plus or Unit price contracts need very accurate field measurements Pg 432

Schedule of Values v. Cost loaded CPM Schedule Unit Price Contracts Do not call for Cost Loaded CPM Schedule Conflicts with line items on unit price sheet Do not call for schedule of Values A breakdown of all line items is submitted w/ contractor’s bid and is binding throughout job

Lump Sum Contracts with Cost Loaded CPM Do not ask for Schedule of Values – cost loaded CPM is equal Request Cost loaded CPM be submitted before first pay period ends Lump Sum Contracts w/o Cost loaded CPM Do not ask for a cost loaded CPM schedule Do not ask for a bid breakdown Request a schedule of values before starting work on project

Evaluation of Contractor’s Payment Requests Contractor submits request for payment at a prearranged date each month for previous month’s work Lump sum contract – payment based on a fair estimate of work completed plus overhead and profit Unit Price Contracts – contractor gets paid based on quantity used – RPR must have accurate field measurements +/- 25 % is okay more or less allows for renegotiations by either party

Equipment And Materials delivered but not used Contractor brings stuff on site early May try to bill owner since stuff is on site Contractor only paid when stuff is used Includes materials used but not completed – pipe not paid for until covered and tested Unit price contracts are usually for installed in place materials – on site is not in place Can make exceptions for long lead items which arrive on site early

Force Account Daywork or for any type of cost plus payment In US associated with extra work and change orders May be used to pay contractor when it is difficult to provide adequate measurements or estimate cost of certain items of work Should be last choice when setting up items for payment

Force Account Change order is a must Force account payments not authorized for supers. Allowances for supers is in contractors O&P. Foremen working full time on item would be covered by account PM has authority to direct every aspect of force account work

PM and Contractor must agree on Labor Classification and approximate N of workers, wage rates, travel allowance, subsistence, are foremen included Equipment Types to be used including size, rating, capacity, which indicate that item can do work required, owned or leased, cost per hour for use Materials Cost and freight charges, purchased for project or from contractor’s stock

PM prepares lists of equipment and labor classifications actually used and corresponding rates Equipment list includes complete nomenclature of the equipment to establish rental rate from a Rental Rate Book Labor list includes labor classification and composite hourly rate (basic wage + added costs listed in DOT standard specs)

Payments for Extra Work and Change Orders Usually laid out in Contract Common is cost plus with a reasonable allowance for O&P State agencies may allow 15, 20, 24,33 % on labor and then 15% on equipment, 15% on materials 5% on primary subs (not subs subs)

RPR must evaluate all change orders and requests for payment of extra work RPR should consult PM or owner to determine the exact terms of the agreement that cover extra work RPR keeps daily record of extra work performed and materials used