GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS GLAST Large Area Telescope: Tracker Subsystem WBS B: Electronic Parts & Materials Robert Johnson Santa Cruz Institute for Particle Physics University of California at Santa Cruz Tracker Subsystem Manager Gamma-ray Large Area Space Telescope
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS ASICs See Presentation 5D for more detail. Status: wafers for both GTFE and GTRC chips have been procured and are awaiting wafer probing and screening. Relevant documents: –LAT-PS-01279Overview of Tracker ASIC procurement –LAT-PS-01201GTFE wafer procurement specification –LAT-PS-01222GTRC wafer procurement specification –LAT-PS-01250Tracker ASIC wafer probing procedure –LAT-TD-00247GTFE wafer test procedure –LAT-TD-00248GTRC wafer test procedure –LAT-PS-01321Wafer lapping & dicing procedure and wafer lot acceptance testing –LAT-TD-00249TMCM test plan –LAT-TD-01325Radiation test plan
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS PWB & Pitch Adapter & Bias Final prototypes were recently produced and are being tested: –PWB: loaded with parts and new ASICs for functional testing –Pitch Adapter: Teledyne is bonding 3 of them to MCMs to check that the new design works –Bias: sent to Italy for review PWB: –Design files and specification sent to Young Electronics (L.A.) for quotation –Needs to include raised edge and precision machining of radius –Procurement spec: LAT-DS Pitch adapter and Bias Circuit: –Local Santa Clara vendor (Tycho) –Procurement spec: LAT-PS –Pitch adapter is single layer, no vias, very simple, but with Ni/Au plating
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS Flex Circuit Readout Cables Procurement spec: LAT-PS-01132, includes specification of qualification and acceptance testing. Full-size prototypes manufactured by Parlex for the EM are being put through the specified test regime. Planning a visit to Parlex in early April. Short versions for the EM mini-tower were made at a local vendor (Tycho) and are being used in the electronics testing. The designs for the flight versions are being updated and verified in preparation for the procurement.
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS Connectors Nano-connectors: Omnetics was recently approved and the parts are now on order, including the connector savers. Micro-D connectors: Kristek connectors are not yet approved, but we don’t expect any issues On MCM On cable Larger 080 screws
GLAST LAT ProjectMarch 24, B Tracker Peer Review, WBS SMT Parts HV capacitors: Novacap –Procurement spec: LAT-PS –On order for the Tracker and Calorimeter Polyswitches: Raychem (Tycho) –Procurement spec: LAT-SS –Recently finalized and approved, and the parts are on order –Long process of testing at UCSC and discussions with the vendor 100% of parts: screening after thermal cycle 10% of parts: more extensive tests after soldering Smaller sample for qualification testing at UCSC Ceramic & tantalum capacitors: approved with no issues Resistors: approved with no issues Thermistor: approved with no issues