PHENIX WEEKLY PLANNING 10/18/2007 Don Lynch. 10/18/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.

Slides:



Advertisements
Similar presentations
PHENIX WEEKLY PLANNING 9/13/2007 Don Lynch. 9/13/2007 Weekly Planning Meeting 2007 PHENIX Shutdown April-June 2007: Complete run, De-mount HBD West, Begin.
Advertisements

PHENIX WEEKLY PLANNING 2/8/2007 Don Lynch. 2/8/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress Pink.
PHENIX WEEKLY PLANNING 1/17/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 1/4/2007 Don Lynch. 1/4/207 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 6/7/2007 Don Lynch. 6/7/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day No More Planned Remove.
PHENIX WEEKLY PLANNING 9/6/2007 Don Lynch. 9/6/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upin progress.
2/2/20121 PHENIX WEEKLY PLANNING 2/2/2012 Don Lynch.
PHENIX WEEKLY PLANNING 2/15/2007 Don Lynch. 2/15/207 Weekly Planning Meeting 2 Remaining Schedule StartComplete Cosmic Ray Run (Run 6.9)In Progress All.
PHENIX WEEKLY PLANNING 10/25/2007 Don Lynch. 10/25/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
PHENIX WEEKLY PLANNING 11/1/2007 Don Lynch Daylight Savings Time ends Sunday Nov. 4 at 2:00 AM.
2/9/20121 PHENIX WEEKLY PLANNING 2/9/2012 Don Lynch.
PHENIX WEEKLY PLANNING 5/17/2007 Don Lynch. 5/17/2007 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 5/31/2007 Don Lynch. 5/31/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6 or 6/13/07?
PHENIX WEEKLY PLANNING 2/21/2008 Don Lynch. 2/21/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
1 1/13/2011 PHENIX WEEKLY PLANNING 1/13/2011 Don Lynch No Meeting Today Due to snow shortened work week, today’s planning meeting has been cancelled. Slides.
1/5/20121 PHENIX WEEKLY PLANNING 1/5/2012 Don Lynch.
8/9/20121 PHENIX WEEKLY PLANNING 8/9/2012 Don Lynch.
1 3/5/2009 PHENIX WEEKLY PLANNING 3/05/2009 Don Lynch.
12/26/2013-1/2/ PHENIX WEEKLY PLANNING Dec. 26, Jan. 2, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 5/24/2007 Don Lynch. 5/24/2007 Weekly Planning Meeting 2 Schedule End of Run Party 6/29/07 Next Maintenance Day 6/6/07 Remove HBD.
PHENIX WEEKLY PLANNING 3/8/2007 Don Lynch. 3/8/207 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Continues…. All Up Commissioning In Progress.
12/29/20121 PHENIX WEEKLY PLANNING 12/29/2011 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
PHENIX WEEKLY PLANNING 7/19/2007 Don Lynch. 7/19/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 10/11/2007 Don Lynch. 10/11/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec.
PHENIX WEEKLY PLANNING 3/6/2008 Don Lynch. 3/6/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Technical Support /1/08 PHENIX WEEKLY PLANNING 5/1/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/27/2008 Don Lynch. 3/27/2008 Weekly Planning Meeting2 Shutdown ’08 Schedule CM Crane ReviewMar Purge Flammable Gas, Magnet.
5/1/ PHENIX WEEKLY PLANNING May 1, 2014 Don Lynch.
PHENIX WEEKLY PLANNING 2/2/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 11/2/06 Don Lynch. 11/2/06 Weekly Planning Meeting 2 New Detectors TOF West HBD RXNP MPC North.
PHENIX WEEKLY PLANNING 3/22/2007 Don Lynch. 3/22/2007 Weekly Planning Meeting 2 Schedule Re-Start 5 man shifts 3/20/07 Beam: blue ring 3/8/07, in yellow.
PHENIX WEEKLY PLANNING 8/9/2007 Don Lynch. 9/9/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 1/10/2008 Don Lynch. 1/10/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going1/18 Gas.
PHENIX WEEKLY PLANNING 2/9/06 Don Lynch. Prep Schedule for Run 6 BBC N&S dried, tested re-installed, final tested [DONE] MuTr FEE and anode purge lines.
PHENIX WEEKLY PLANNING 9/14/06 Don Lynch. 9/14/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown '065/1/200612/8/2006.
PHENIX WEEKLY PLANNING 12/6/2007 Don Lynch. 12/6/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
1 3/10/2011 PHENIX WEEKLY PLANNING 3/10/2011 Don Lynch.
PHENIX WEEKLY PLANNING 10/4/2007 Don Lynch. 10/4/2007 Weekly Planning Meeting 2007 PHENIX Shutdown October 2007: Finish MPC South Installation, replace.
PHENIX WEEKLY PLANNING 12/7/06 Don Lynch. 12/7/06 Weekly Planning Meeting 2.
PHENIX WEEKLY PLANNING 10/20/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
1 12/30/2010 PHENIX WEEKLY PLANNING 12/30/2010 Don Lynch.
12/6/20121 PHENIX WEEKLY PLANNING 12/6/12 Don Lynch.
1/26/20121 PHENIX WEEKLY PLANNING 1/26/2012 Don Lynch.
PHENIX WEEKLY PLANNING 11/15/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn Going11/30.
PHENIX WEEKLY PLANNING 12/27/2007 Don Lynch. 12/27/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
PHENIX WEEKLY PLANNING 3/15/2007 Don Lynch. 3/15/2007 Weekly Planning Meeting 2 Schedule Cosmic Ray Run (Run 6.9) Done All Up Commissioning On Going Re-Start.
PHENIX WEEKLY PLANNING 3/02/06 Don Lynch. BLM Test.
Technical Support /15/08 PHENIX WEEKLY PLANNING 5/15/2008 Don Lynch.
PHENIX WEEKLY PLANNING 1/24/2008 Don Lynch. 1/17/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
Technical Support /18/08 PHENIX WEEKLY PLANNING 12/30/2008 Don Lynch.
PHENIX WEEKLY PLANNING 6/28/2007 Don Lynch. 6/14/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set up5/ ?
PHENIX WEEKLY PLANNING 12/20/2007 Don Lynch. 12/20/2007 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC Tent preparationOn GoingOn Going.
12/19/ PHENIX WEEKLY PLANNING Dec. 19, 2013 Don Lynch.
PHENIX WEEKLY PLANNING 7/26/2007 Don Lynch. 7/26/2007 Weekly Planning Meeting 2007 Summer Shutdown Schedule ItemStartComplete RPC Factory set upStarted.
PHENIX WEEKLY PLANNING 5/7/2007 Don Lynch (Thursday is Monday this week)
PHENIX WEEKLY PLANNING 1/31/2008 Don Lynch. 1/31/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going Switch.
PHENIX WEEKLY PLANNING 10/26/06 Don Lynch. 10/20/06 Weekly Planning Meeting 2 PHENIX Shutdown Overview Task_NameStart_DateFinish_Date PHENIX Shutdown.
PHENIX WEEKLY PLANNING 5/3/2007 Don Lynch. 5/3/2007 Weekly Planning Meeting 2 Schedule HyTec CM vibration modes test5/23/07 End of Run Party 6/29/07 Next.
5/30/20131 PHENIX WEEKLY PLANNING 5/30/2013 Don Lynch.
1 1/29/2009 PHENIX WEEKLY PLANNING 1/29/2009 Don Lynch.
Technical Support /16/08 PHENIX WEEKLY PLANNING 10/16/2008 Don Lynch.
PHENIX WEEKLY PLANNING 3/1/2007 Don Lynch March: in like a lion Out like a lamb.
1 7/9/2009 PHENIX WEEKLY PLANNING 7/9/2009 Don Lynch.
PHENIX WEEKLY PLANNING 11/8/2007 Don Lynch. 11/8/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish Elec. Cooling Water upgrade(CA) (under.
PHENIX WEEKLY PLANNING 6/8/06 Don Lynch. 6/8/2006 Weekly Planning Meeting 2 This Week Rec’d TOF West Access: move HBD to Dead Turtle Position Sec’y of.
1 11/25/2010 PHENIX WEEKLY PLANNING 11/25/2010 Don Lynch.
2/20/ PHENIX WEEKLY PLANNING Feb. 20, 2014 Don Lynch.
1 2/19/2009 PHENIX WEEKLY PLANNING 2/19/2009 Don Lynch.
PHENIX WEEKLY PLANNING 2/14/2008 Don Lynch. 2/14/2008 Weekly Planning Meeting2 Run 8 Task Schedule ItemStartFinish RPC supportOn GoingOn Going CM Crane.
Presentation transcript:

PHENIX WEEKLY PLANNING 10/18/2007 Don Lynch

10/18/2007 Weekly Planning Meeting2 Run 8 Prep Schedule ItemStartFinish MPC South InstallationDoneDone Elec. Cooling Water upgrade(CA) (under EC)In progress? (elsewhere in IR)In progress11/2 CM Move to Run position DoneDone MPC South InstallationDoneDone Borated PE neutron shield installationDoneDone More decapacitor removalsDoneDone Close out all shutdown ’07 open work permits10/1811/1

10/18/2007 Weekly Planning Meeting3 ItemStartFinish EC Roll In10/1510/31 C-A fold scaffolding10/1510/15 Move MuID collars to IR10/1210/15 Remove Plates, cart & move Manlift10/1210/15 Roll in-to IR and North to run pos.10/1510/16 PHENIX techs reconnect water, elect., gas, fibers10/1610/19 Carpenters restore scaffolding, Re-install lift & ladder, re-connect gas sniffers10/1710/19 Mike Rau re-install lift wiring, Re-connectTOF blower 10/1610/19 Blue Sheet/Pink sheets10/2211/2 Run 8 Prep Schedule (cont’d)

10/18/2007 Weekly Planning Meeting4 ItemStartFinish DC East & West repairs (permits done)10/1110/26 Pre-run Commissioning10/110/31 Assemble shield wall10/2211/1 Shield wall roll in11/111/5 Start of Run 8 (Cooldown)11/111/1 HBD Pre survey at SBA-1 wkA-1 day HBD West Mechanical/Gas Reinstall12/3?12/17? HBD EAST Mechanical/Gas Reinstall ?????? HBD Electrical Reinstall?????? HBD installation survey10/1?12/22? Run 8 Prep Schedule (cont’d)

10/18/2007 Weekly Planning Meeting5 Safety Systems/ UPS Blue Sheeting/Pink sheeting UPS update HSSD system status Other Issues

10/18/2007 Weekly Planning Meeting6 CM Ladder/Stair Shutdown Access PO pinned Waiting for delivery Purchasing SNAFU causes delay Delivery ~10/15

10/18/2007 Weekly Planning Meeting7 Station 1, 2, 3 access plan Work to begin on these items after prep for run 8 is finished

10/18/2007 Weekly Planning Meeting8 RPC Factory Issues What we can do now: Install and move in furniture, equipment, gas piping and leak tests, and test equipment operations What we can’t do now: Operate gas system (other than N2 leak tests), store, assemble and/or test detector modules and/or other components. Electrical – nearly done. Walkthru needed Safety- to be ready by Nov. 9 Gas – procedure needs to be formatted/ Approved end of next week?

10/18/2007 Weekly Planning Meeting9 Equipment – PHENIX techs (John and Kenny) will assist in assembling shelving already at tent and complete the cosmic ray test stand per RPC group directions. RPC group will determine where to locate shelving. Ali will arrange for riggers to move excess equipment from tent area as requested. Carter will coordinate this. RPC group will provide specs for the gap transportation cart (vertical high and low lifting requirements, horizontal/ vertical orientation, table top dimensions, max load capabilities, etc.) PHENIX will design and fabricate. RPC group will provide specifications for gap and module storage racks. PHENX will design, fabricate and install. Work plan – existing work plan covers work to be done between now and factory start up (Factory startup is when production testing and assembly of modules and half octants begins) Work allowed now includes set iup of gas system including all components and N2 testing for leaks (use of gases other than N2 requires approved gas operation procedure and full working safety system- see above). Electrical setup testing of prototypes, instrumentation and related equipment in preparation for factory operation may commence as soon as a final walkthru by C-A experimental safety group is completed and any action items generated by walkthru are addressed to the satisfaction of the experimental safety group. RPC Factory Issues, cont.

10/18/2007 Weekly Planning Meeting10 Security – The man door needs a lock. PHENIX techs cannot do this by lab policy and lab locksmith is backed up too much to rely on. RPC non-BNL techs will get a dead bolt lock which operates by key from outside but by hand from inside. All zipper doors are to be closed when not in use and zip tied down from inside. Locking tool and equipment cabinets inside tent. Additional security required when raw materials arrive. RPC group to review C-A policy (3 tier requirement as required by C-A procedure 1.20) RPC group will prepare a one page description of how they intend to comply with this requirement. This will be reviewed by C-A. Tent air quality/ air exchange: Ali will coordinate with C-A industrial hygiene representative to determine if additional provisions are needed for tent air turn over per applicable code. RPC Factory Issues, cont.

10/18/2007 Weekly Planning Meeting11 Action Items from C-A safety review: Tent needs man door – Done Electrical one line drawing of tent electrical services needed – Done Gas monitoring equipment to be calibrated and tested per BNL requirements – Equipment is manufacturer calibrated. Will be tested with mini blue sheets check out. Gas exhaust vent lines to be exhausted from building – Done Gas schematic/ procedure needed – Done Gas lines per applicable codes – Done Gas cylinders to be secured and have proper flow restrictors – Done racks and regulators Fire protection to be designed in consult with J. Levesque – Done Max flow rates incl. chambers in storage for all gases to be forwarded to M. van Essendelft – still needs to be done before factory startup Electronics to be approved installation and use (including NTRL equivalence approval) – Done, walkthru needed. Any chemicals to be purchased through BNL to assure compliance – Will be complied with Adequate ventillation to be designed into tent – (see above0 Crane lifting to be performed by site specific properly trained personnel – Covered in factory work plan Approved security apparatus to protect against theft – see above Covered gas pad for storage of spare bottles outside of 912 – Will store bottles at PHENIX gas pad and use N2 buggy outside of 912 RPC Factory Issues, cont.

10/18/2007 Weekly Planning Meeting12 Other Work Empty (except clean metal waste) and discard old container Neutron shielding test (4’ x 4’ x 2” borated polyethylene Shield support design in progress Install in October for Run 8 tests Shield to be fly cut to 1.25” thick, drilled and Tapped fo 3/8-

10/18/2007 Weekly Planning Meeting13 Safety, Security, Etc. : Work Control Coordinators should attend one of the classes given by BNL on the revised Work Planning SBMS Oct 19, 29 & 30 Bldg 555 Hamilton Seminar room. PHENIX floors (counting house, trailer offices, mixing house) to be cleaned this weekend. Please get everything off the floors before you leave Friday. Check your training. Anything that expires in 2007 should be attended to.

10/18/2007 Weekly Planning Meeting14 5 Year Plan 2007 HBD Repairs, DC (minor) repairs), MPC N&S upgrade,MuTr FEE upgrade prototype, infrastructure upgrades & repairs, misc. subsystem work 2008 MuTr FEE upgrades 1 octant 1&2 S, Cu absorber test, RPC3 S, infrastructure upgrades & repairs, misc. subsystem work 2009 Scaffolding in MMS and MMN, MuTr FEE N&S stn. 2 & 3, MuTr N&S stn. 2 & 3 repairs, RPC2 S&N, RPC3 N, Cu absorbers, infrastructure upgrades & repairs, misc. subsystem work 2010Remove HBD & RXNP, remove beampipe, DC West upgrade, VTX barrel, RPC1 N&S, MuTr FEE stn. 1 N&S, MuTr stn. 1 N&S repairs, infrastructure upgrades & repairs, misc. subsystem work 2011NCC S, FVTX, infrastructure upgrades & repairs, misc. subsystem work 2012NCC N, upgrades contingency & wishlist, infrastructure upgrades & repairs, misc. subsystem work * Years refer to the shutdown year and follow the run with the similar number (i.e. work in 2007 is to be done in the shutdown that follows run 7, and so on)

10/18/2007 Weekly Planning Meeting15 Links for the weekly planning meeting slides, long term planning, pictures, videos and other technical info can be found on the web site: Where To Find PHENIX Technical Info We’re on track to run 8