Vogtle 3 & 4 Commercial Facility Turnover and Information Handover Lessons Learned Elizabeth J. Johnson SNC CM Project Lead.

Slides:



Advertisements
Similar presentations
Contractor Management. Struggling with Contractor Management ? ? ? Getting purchasing on board? Specifically stating environmental compliance in contracts?
Advertisements

Contract CloseOut.
Sustainability Implementing Sustainable Practices for Productivity Enhancement for Productivity Enhancement Presented by Ryte Byte, Inc.
Food Parks Initiative FAO/AGS Presentation on the basic concepts in ‘Food Parks Initiative’ for discussion, Strategy with Rome- Based Food Agencies Organisation”
Integrated Facility Management (IFM) For NSLS-II October 6, 2010 Chris Johnson Facility Complex Manager Facilities and Operations.
HIPAA How It Is Affecting Information Systems Within Companies Around Us.
Defense Security Service Facility Clearance Branch (FCB)
1 Human Resource Management Systems Chapter 6: HRMS Vendors Joseph Y-W. Deng
The Office of Information Technology Information Security Administrator Kenneth Pierce, Vice Provost for IT and Chief Information Officer.
Plant Information Model (PIM) Breakout N1 – (1:00pm – 2:30pm), Monday, June 16, 2014 Russell Adams – EPRI Consultant Laurent Perkins, Bentley Kent Freeland,
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Operations Erik D. Johnson, Deputy ALD for Programs NSLS-II Project Advisory Committee February 8-9, 2011.
Developing a Chemical Risk Management Program
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Readiness Stephen Sawch, Assistant Director for Construction Management Conventional Facilities.
TRAX International Overview Operations, Management, and Engineering Services for Government, Security, and Commercial Energy Sectors Employee-Owned Corporation.
National Property Management Association Understanding the Statement of Work… Request for Proposal --- Section C.
2012 VA IRB Administrators Meeting Stephania H. Griffin, JD, RHIA, CIPP/G VHA Privacy Officer Director, Information Access and Privacy Privacy Officer.
1 Configuration Management 101 ITS Professional Capacity Building Program T3 Webinar February 21, 2008.
PMP® Exam Preparation Course
Process Safety Management
Server Virtualization: Navy Network Operations Centers
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
VPPPA Mentoring Program. The VPPPA Mentoring Program is a formal process to assist companies and facilities interested in participating in the Voluntary.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 Working Group on Archives and Records Management WGARM.
Quality Assurance Program National Enrichment Facility Warren Dorman September 19, National Energy and Environmental Conference.
Langley Research Center FY 2002 Safety and Health Managers’ Meeting.
Mechanical Integrity Quality Assurance. Lesson Objectives  Describe How to Ensure Controls in Place for QA  Describe Standard Record for Inspection.
© Property of ERCOT /8/20061 TPTF ERCOT 30/60/90 day Plan Raj Chudgar, Nodal Program Manager February 20, 2006.
Web (Website) Records Management. Agenda:  Brief Definitions and Outline – NARA  Vendors  Member Q & A  Who has formal policies for web/website management?
W. A D V I K. RU Introduction materials. W. A D V I K. RU Lines of activity General contracting; Telecommunication; Engineering; Security; Construction.
The DCF Leadership Plan Brief Overview. 2 Website Continuous Learning… Tracking…Reports Managing for Excellence Introducing ………… Supervising for Excellence.
1 Information Handover at UniStar Lessons Learned Presented By: Bob Renuart UniStar.
2006 CMBG Conference Sam Melton Supervisor, Configuration Management Brunswick Nuclear Plant Progress Energy June 11-14, 2006 Richmond, VA CM04 Facility.
Engineering Design Dein Shaw. Chapter 1 Introduction What is design?
Westinghouse/Southern/SCANA – New Build Configuration Management
PAGE 1 New Plant - CM Configuration Management For The Next Generation Of Nuclear Facilities Joseph Burack Consulting Engineer Configuration Management.
New Reactor Construction Inspection
Configuration Management of Post-Fukushima Regulations CMBG June 2013 David Gambrell Director, Severe Accident Management Southern Nuclear.
Josh Olson Southern Nuclear - Vogtle 3&4
1 CREATING AND MANAGING CERT. 2 Internet Wonderful and Terrible “The wonderful thing about the Internet is that you’re connected to everyone else. The.
The following training presentation is for all 1Prospect subcontract employees and is taken upon joining a contract or task order to which 1Prospect is.
2007 CMBG Conference Sam Melton Progress Energy June 19, 2007 Charleston, SC Configuration Management Principles And Practices for New Nuclear Plants.
Illuminating Britelite’s Internal Services for Success Strategy for Process Improvement.
Tom Lenart & John Field CT DEMHS Region 2.  Department of Emergency Services and Public Protection (DESPP)  Commission on Fire Prevention and Control.
Small Business Programs Tatia Evelyn-Bellamy Director Small Business Division Small Business Center February 2016.
Washington State Work Zone Rule  Work Zone Rule Implementation  New Work Zone Policy Cathy Nicholas, FHWA - WA Division Office Frank Newboles, WSDOT.
Finance Sub-Committee Report NGEC Annual Meeting Washington, DC February 21, 2014.
An Overview Of The MBP CM Leadership Manual Presented by: Robert J. Carter, CCM Robert M. Pfeiffer, CCM.
1 EASTERN MUNICIPAL WATER DISTRICT Temecula Valley Regional Water Reclamation Facility 23-MGD Expansion Project Joe Mouawad, P.E. Senior Director.
AUDITING BUSINESS CONTINUITY PROGRAMS AND PLANS What to Look For Presented by: Tommye White, CBCP, DRP Chuck Walts, CBCP, CRP.
The following training presentation is for all 1Prospect employees and is taken upon joining the company team. Quality Management System (QMS) Training.
The Intricacies of the Beginning and the End of a Project CM Leadership Manual Presented by: Todd Scholtz, LEED AP Carlos Sanchez, LEED AP BD+C.
Records Management with MOSS, K2, & PsiGen Deepa Patadia
From the Dry Run and National Implementation of the
Accelerator Operations Department Readiness (Part 2)
SNC/SCANA – New Build Configuration Management
Software and Systems Integration
Enterprise Content Management Owners Representative Contract Approval
Project Management for RIMI
بازاریابی و بازرگانی زمستان 93.
Vogtle 3&4 Configuration Management
WGARM Appraisal Decision Assistance Phase 1, Dec. 2002
SNC/SCANA – New Build Configuration Management
G Project Sponsor & Business Owner : Jane Johnston & Anna Stamp
Anna Bradford, Deputy Director Division of New Reactor Licensing
The Survival Plan.
ALBANIA ROAD MAINTENANCE PROJECT TRAINING WORKSHOP.
Break Out 1: CM of Digital Equipment
System Safety Regulation
CEO Kickoff.
Presentation transcript:

Vogtle 3 & 4 Commercial Facility Turnover and Information Handover Lessons Learned Elizabeth J. Johnson SNC CM Project Lead

Introduction Education Professional Personal

Objectives To provide Operating Experience of Facility Turnover and how it relates to Plant Turnover. Discuss current Information Handover challenges at Vogtle 3&4.

About the Project Received COL February 2012 Expected COD –Unit 3 in 2016 –Unit 4 in 2017 Interesting Fun Facts

Commercial Facility Turnover Vogtle 3 &4 Training Center Fire Training Facility Executive Office Building Engineering and Administrative Building Maintenance and Support Building Communications Building Warehouses

Vogtle 3&4 Training Center Constructed by a local A&E firm Early occupancy needed –Included partial turnover of the facility Fire Protection System (FPS) issues No Formal Turnover process developed

Fire Training Facility Constructed by Primary Construction Contractor Early occupancy needed No Formal Turnover process developed Documentation discrepancies and issues

Mitigation Strategy Development of Facility Turnover Procedures Turnover Strategy Meetings Point of Contact identified Development of Document Receipt Procedures

Similarities to Plant Turnover MUST HAVE a process and plan Roles and Responsibilities identified Communication between SNC and the Consortium Process and plan for receipt of documents and records

Vogtle Documentum Information Handover/Turnover Shaw Design/Licensing Documents WEC Information Handover / Turnover PDMS (ECF) Maximo Available for Ops Readiness & Startup Team WEC Vendor Documents Shaw Design Documents Shaw Vendor Documents Process Into Permanent Storage Data Documents & Records w/ Metadata Process Into Interim Storage WEC Procedures PDF Files Meta Data CM Software

Information Handover Challenges Contract Resources Planning –Pre-operational Program –Information Handover Plan –CIMS –Commercial Facility Turnover

Configuration Management Program Activities Policy Statement Procedure Development Program Document Procedure Development Handover Plan Development Handover Specification Development DecOctSepAugJulyJuneAprilMarchFebJanMayNov ND-EN-008 Approved 5/9/12 3rd Quarter CM Software RFP CERT Approval CM Software Implementation 3rd Quarter 2nd Qtr 3rd Quarter 4th Qtr Recieve Handover Information From Consortium Until Turnover

Lessons Learned Recap Commercial Facility Turnover –Develop and Implement a Plan Information Handover –Plan early including the EPC contract

Questions