NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14.

Slides:



Advertisements
Similar presentations
Cisco 6500 E-Series Chassis Up-grade
Advertisements

NCSX Machine Platform FDR June 15, 2005 Erik D. Perry.
LCW Upgrades - Final Booster RF Cavity LCW Isolation Valve Replacement. – 8 valves and unions previously replaced – An additional 10 valves and unions.
E163: Laser Acceleration at the NLCTA Goal: Demonstrate the technical feasibility of laser-driven particle acceleration Photonic band gap structures made.
Plans for Diagnostic Removals, Storage, and Re-installations during NSTX Upgrade Outage B. Stratton NSTX Team Meeting 9/13/2011.
Crane & Hoist Training & Inspection Requirements Crane Safety.
Tagger and Vacuum Chamber Assembly Procedure. Preassembly of second bottom yokes and poleshoes. a) Install special support. b) Place the second bottom.
1 Daya Bay Muon system Installation Workshop, IHEP, July 14, Updated RPC Gas System Installation Plan Changguo Lu Princeton University.
Bad Fibers LIU Qian. Today we put the bundle 2 (West bundle) into the protecting tube. Common end 9 m barrel 5.6 m 9.4 m Put into coiled tube Put into.
Today’s (12.7) Report LIU Qian. East EC is ready, we are going to install the EC TOF next Monday.
Recently Report LIU Qian. Putting the common end into the moon box We removed this surface of rack when we were installing the common end. We didn’t move.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
Machine Installations and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
Machine Installations and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
REQD FUTURE POWER SYSTEM CHANGES  Following additional work is required to be performed to restore full capability of the machine: 1. Provide power feed.
1 RWM P OWER FEED TO EACH COIL S. Ramakrishnan. 01/29/20102 RWM COILS Existing Status The Six RWM coils are grouped in pairs Each Pair is fed from one.
NSTX Supported by Erik Perry May 5, 2009 NSTX Upgrade Status.
NCSX NCSX Preliminary Design Review ‒ October 7-9, 2003 G. Oliaro 1 G. Oliaro - WBS 5 Central Instrumentation/Data Acquisition and Controls Princeton Plasma.
Machine Installation and Construction Management Erik D. Perry Princeton Plasma Physics Laboratory NSTX Upgrade Project Office of Science Review LSB B318.
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Installation Erik Johnson ASD Deputy Director and Interface Manager NSLS-II CFAC Meeting November 9-10, 2009.
Visit Gangway FromLHBIEP__0181 by Andre Coin ~ 2600 GANGWAY POSITION.
NSTX-U Diagnostic Installations S.P. Gerhardt, B. Stratton, R. Kaita With help from A. von Halle, E. Perry, F. Jones NSTX-U Supported by Culham Sci Ctr.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
July LEReC Review July 2014 Low Energy RHIC electron Cooling Al Pendzick LEReC Civil Construction.
Integration, Installation & Infrastructure Ans Pardons, with input from the WP4 members September 2014.
1 NSTX Upgrade Progress Report May 7 th, 2013 Ron Strykowsky, Erik Perry, Tim Stevenson, Larry Dudek, Steve Langish, Tom Egebo, Mike Williams and the NSTXU.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
April NSTX-U Team Meeting. Engineering Operations April 25, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in mid-June to shift activities.
Metrology Milestones Metrology Task Force –Vacuum vessel manufacture - P. Goranson –Mod. Coil Form manufacture - D. Williamson –Mod. Coil winding- S. Raftopoulos.
Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave.
Progress to Date PPPL Advisory Board Meeting May 20101NSTX Upgrade – R. L. Strykowsky CD-0 Approved February 2009 The NSTX Upgrade Project organization.
1 NSTX Outage - Plan 1. 2 NSTX Outage – Diagnostic considerations 2 1.Erik Perry will be the manager of the construction activities in the Test Cell.
Spectrometer Solenoid Fabrication Status and Schedule Steve Virostek Lawrence Berkeley National Lab MICE RAL October 20, 2008.
NSTX NSTX Center Stack Upgrade Ensure fatigue resistant Welds: minimum # of locations shown, could be more. Various Weld Reinforcements & Hardware Replacement.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Refurbished Booster RF John Reid October 24, 2012.
1Page # Machine Assembly WBS 700 By: James H. Chrzanowski January 24, 2001.
NSTXU Project Update Jim Chrzanowski, Larry Dudek, Erik Perry, Tim Stevenson, Ron Strykowsky and the Project Team October 4th, 2013 NSTX-U Supported by.
NSTX Upgrade Project – Final Design Review June , NSTX Supported by College W&M Colorado Sch Mines Columbia U CompX General Atomics INEL.
Gas System production for LHC detectors Stefan Haider EP / TA1 - Gas.
Americas Cavity Specification C.M. Ginsburg (Fermilab) On behalf of the Fermilab cavity crew October 20, 2010.
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab NFMCC at LBNL January 25, 2009.
SC Project Review of NCSX, April 8-10, 2008 Plant Design Integration, General Arrangement Drawings E. D. Perry.
Engineering Operations Outage Schedule Center Stack casing is scheduled to go back in the vessel today Complete NB armor, Diagnostic calibrations, clean/photo/close,
SC Project Review of NCSX, April 8-10, 2008 NCSX Machine Assembly E. D. Perry.
1 BROOKHAVEN SCIENCE ASSOCIATES Accelerator Systems Installation F. Willeke, ASD Director 6 th ASAC October 22-23, 2009.
Engineering Operations Outage Status: New shielding of HHFW/in-vessel components has been completed. Fit-ups of OH bus lead upgrades to reduce error fields.
ELLIPTICAL HEAD PROTECTING COVER 01_INSTRUCTION DISCONNECTING THE ELLIPTICAL HEAD.
August 2007 Booster RF Upgrades J.Reid Booster RF Upgrades West Gallery LCW modifications: – Headers in select locations to be upgraded by.
Engineering Operations Outage Schedule The vessel & beamline are under vacuum. 1st Bake-out complete. Air leaks found and fixed. The OH coil will be installed.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Visiting DESY for S1-G module Norihito Ohuchi 2009/8/251 19th Biweekly Webex meeting (S1-G, Cryomodule, Cryogenics)
LCLS-II Cryoplant Overview
TF Fabrication Progress is being made on TF bundle fabrication activities but the schedule remains tight. All 24 outer conductors have been machined but.
LHC schedule status K. Foraz EN-MEF 12/04/2013LSC - K. Foraz1.
MICE Coupling Coil Fabrication Steps to Complete Allan DeMello Lawrence Berkeley National Laboratory Coupling Coil Working Group January 28, 2014 January.
… getting there … 112/02/2014A. Fabich, EN-MEF-LE.
Operations meeting on FY07 Shutdown Date: June 27, W.B. Christie Outline Brief Overview of Shutdown Plan Details/discussion of next few weeks Comments.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
B10 D19 Diode Repair March 29, 2016 Gary McIntyre.
Status Report of the Review of Vacuum Systems and Procedures Tug Arkan, Allan Rowe 3/7/
S A Griffiths CM42 June 2015 Electrical & Control.
Chapter 9 Safety Permit Systems
Cryomodule test stand at ESS site
Complementary ISTC Projects #3888, 3889p
Experimental equipment Edgar L. Black February 17, 2019
Cryomodule Assembly Plan
Reader Swap out Guide.
Polarized 3He target installation
Presentation transcript:

NSTX Upgrade Test Cell Initial Schedule Vent vacuum vessel by 9/19 No vessel entry at this time Period of removals prior to start of outage: 9/19 – 10/14 Must complete by October 14th Machine Technicians will provide assistance Install new 118’ platform on west side by 10/14 Needed for racks being moved out of the way of NB2 Establish construction power by 10/14 Portable carts in 3 places in NTC Disconnect all power in NSTX Test Cell except construction power Will occur on 10/17 Assures all power has been removed from racks and equipment Marks the end of free access to the Test Cell 1E. Perry 9/13/11

NSTX Upgrade Test Cell Initial Schedule Remove cable tray at top of machine start 10/18 To provide access for structural modifications Remove RF piping within 10’ of machine starts 10/18 To provide access to the east side of the machine Rack and equipment removals to make room for NB2 starts 10/18 Removals by machine technicians working to written procedures Reviewed and coordinated by the Work Control Center Removals of diagnostics from on/near vacuum vessel starts 10/18 Start with Bays J, K, and L Coil up and protect cables, tubing and fibers Structural modifications to umbrella and coil supports starts 1/2 Grinding and welding involved in all bays – top, mid-plane and bottom 2E. Perry 9/13/11

NTC Layout at End of Upgrade 3E. Perry 9/13/11

NTC Layout at End of Upgrade 4E. Perry 9/13/11

NTC Layout at End of Upgrade 5E. Perry 9/13/11