Progress of X-Band Accelerating Structures LINAC10, Tsukuba 17 Sep. 2010 T. Higo (KEK)

Slides:



Advertisements
Similar presentations
COOLING TUBE ACCELERATING STRUCTURE MANIFOLD COUPLER VACUUM INTERFACE FLANGE RF INTERFACE FLANGE TUNING STUD ENGINEERING DESIGN AND FABRICATION OF X-BAND.
Advertisements

IWLC2010Walter Wuensch19 October 2010 Progress on CLIC rf structures.
Breakdown Rate Dependence on Gradient and Pulse Heating in Single Cell Cavities and TD18 Faya Wang, Chris Nantista and Chris Adolphsen May 1, 2010.
CLIC08 workshop Structure production: CERN activities and Master Schedule G. Riddone, W. Wuensch, R. Zennaro, Contributions from C. Achard, S. Atieh, V.
Choke-mode Damped X-band Structure for CLIC Main Linac Hao ZHA, Jiaru SHI CERN Sep 27, 2011 Jiaru Shi, LCWS11 Workshop, Granada1.
Choke-mode damped accelerating structures for CLIC main linac Hao Zha, Tsinghua University Jiaru Shi, CERN
CERN-KEK X-band collaboration 3 Dec T. Higo on behalf of X-band group of KEK.
High gradient studies in simple setups (for discussion) T. Higo.
Report from KEK High gradient study results from Nextef (+ other related activities) LCWS2011, Granada Sep. 27, 2011 T. Higo.
Status of KEK production July 11, 2008 at SLAC KEK T. Higo et al., Accelerator div. T. Takatomi et al., Mech. Eng. Center.
High gradient features from Nextef on recent CLIC prototype structures US-HG workshop, SLAC 9 February 2011 T. Higo representing X-band group of KEK.
CLIC RF structure master schedule and CERN production
1 X-band Single Cell and T18_SLAC_2 Test Results at NLCTA Faya Wang Chris Adolphsen Jul
Report from Nextef IWLC10, Genève, Oct. 20 T. Higo (KEK)
CLIC MAIN LINAC DDS DESIGN AND FORTCOMING Vasim Khan & Roger Jones V. Khan LC-ABD 09, Cockcroft Institute /14.
Design of Standing-Wave Accelerator Structure
Walter Wuensch CLIC project meeting, 31 March 2015 Accelerating structure program: design and testing.
Report from NLCTA CERN Built T18’s degC Vacuum Braze degC H2 Braze (SLAC procedure) - New T24s 1.CERN Built (cells pre-fired) 2.KEK/SLAC Built.
HIGH RF POWER TESTING FOR THE CLIC PETS International Workshop on Linear Colliders 20 th October 2010 Alessandro Cappelletti for the CLIC team with.
5 th CLIC X-band collaboration meetingWalter Wuensch16 May 2011 CLIC rf structure program.
Results from Nextef Observations in high gradient tests of CLIC Prototype Structures and associated study activities CLIC2013, CERN 29 January, 2013 T.
Accelerating structure test results and what’s next Walter Wuensch CTF3 collaboration meeting
R&D status and future strategy in KEK X-band area May 16, 2011 T. Higo (KEK)
Update of KEK X-band Research Activity March 3, 2009 Shuji Matsumoto Accelerator Laboratory, KEK 2009/3/31US High Gradient Workshop.
日米協力 US/Japan cooperation Research of High Gradient Acceleration Technology for Future Accelerators progress report New proposal 7.
Investigation threads on fabrication technologies for the CLIC X-band Accelerating Structures C. Rossi on behalf of the CLIC X-band Activity Thanks for.
040220LCPAC 2004 Structure (T. Higo)1 X-band accelerator Structure LCPAC Feb. 20, 2004 T. Higo KEK.
Fabrication of accelerator structures for CLIC study CLIC Workshop Oct , CERN T. Higo, KEK.
An Overview of the CLIC Testing Program W. Wuensch CLIC ACE
CLIC RF structure development meeting Structure cost study (introduction) G. Riddone,
Overview of CLIC main linac accelerating structure design 21/10/2010 A.Grudiev (CERN)
Marc Ross The Normal-Conducting Linear Collider preparation - status and plans.
X-Band: test stand and structure program
NLC Status and Milestones D. L. Burke ISG9 KEK December 10-13, 2002.
Recent High-gradient test result at KEK Linear Collider Workshop 2012 Arlington, Texas (WebEx) 25 October, 2012 Toshi Higo and X-band group of KEK.
ENGINEERING DESIGN AND FABRICATION OF X-BAND DAMPED DETUNED STRUCTURE V. Soldatov¹, D. Gudkov¹, A. Samoshkin¹, G. Riddone², A. Grudiev², S. Atieh², A.
Performance of CLIC prototype accelerator structures tested at Nextef CLIC February 2014 Toshiyasu Higo (KEK)
CLIC08 workshop CLIC module layout and main requirements G. Riddone, on behalf of the CMWG Home page of the TBM WG:
PBG Structure Experiments, AAC 2008 Photonic Bandgap Accelerator Experiments Roark A. Marsh, Michael A. Shapiro, Richard J. Temkin Massachusetts Institute.
Recent high-gradient results, rf testing, places and plans Steffen Döbert, CLIC Workshop, Test facilities High gradient results Future testing.
Summary of progress towards CLIC goals and next steps for structure testing 6 th X-band collaboration workshop, April 18 th- 20 th 2012 Steffen Döbert,
KEK workshopWalter Wuensch18 April 2012 Status and objectives of the CLIC X-band and high- gradient activity.
The CLIC accelerating structure development program Walter Wuensch CARE05 23 November 2005.
CLIC Accelerating Structure R&D Introduction W. Wuensch X-band workshop
ENGINEERING DESIGN AND FABRICATION OF X-BAND ACCELERATING STRUCTURE TD24 WITH WFM Abstract To achieve high luminosity in CLIC, the accelerating structures.
5 th CLIC-ACE Structure production in laboratories and industries G. Riddone, 02/02/2010 (contribution from KEK/SLAC colleagues) 1.
Status report from KEK Feb. 26, 2010 T. Higo, S. Matsumoto T. Takatomi, Y. Higashi and X-band group.
TD18 High Power Test Results Faya Wang Chris Adolphsen May 3, 2010.
W. Wuensch CLIC project meeting High-power rf structure testing.
Status of high gradient experiments at Nextef Kazue Yokoyama, Toshiyasu Higo, Yasuo Higashi, Shuji Matsumoto, Shigeki Fukuda Accelerator Laboratory, KEK.
Title 2 nd X-band Accelerator Structure Design and Test-Program Collaboration Meeting Discussion with WebEx on March 17 between CERN and KEK W. Wuensch,
Nextef results & status International Workshop on Breakdown Science and High Gradient Technology KEK, Japan 18 April 2012 Toshi Higo.
Discussion on critical issues for testing: breakdown identification, preparation for test, processing protocol, etc. 4 th Annual X-band Structure Collaboration.
Some information from Nextef For poster session in IWLC T. Higo.
GOLD- ELECTROPLATING COOLING FITTING ADAPTER ACCELERATING STRUCTURE CONCEPTUAL DESIGN OF X-BAND ACCELERATING STRUCTURE TD26 CC SIC Abstract Many accelerating.
Test Accelerating Structures Designs, Objectives and Critical Issues
WP5 Elliptical cavities
KEK Status and plans of structure production and testing
A 6 GeV Compact X-ray FEL (CXFEL) Driven by an X-Band Linac
Effort to identify the critical issues for high gradient
X-band and high-gradient development plans at Tsinghua University
Review of rf structure test results
Developments on Proposed
Testing Infrastructure, Program and Milestones
Update of CLIC accelerating structure design
Recent high-gradient testing results from the CLIC XBoxes
High Gradient tests at the KEK Nextef Facility
T24 results and comparison to the preceding studies on CLIC prototype structures May 17, 2011 T. Higo (KEK)
5th X-Band Structure Collaboration Meeting
T18_VG2.4_Disk_#2 processing summary
Presentation transcript:

Progress of X-Band Accelerating Structures LINAC10, Tsukuba 17 Sep T. Higo (KEK)

Contents Evolution in 20 years Judgment with breakdown rate Supplemental high-gradient studies Effort with parameter optimization for stable high gradient Effort with other HOM damping scheme Efforts in fabrication technology X-band collaboration 2010/9/172Higo, LINAC10, Tsukuba

Evolution of LC structures in 20 years 2010/9/173Higo, LINAC10, Tsukuba

LINAC94 at Tsukuba “Linear Collider Structures” 16 years ago, the beginning 2010/9/174Higo, LINAC10, Tsukuba Discussed 100 MV/m level.

VLEPP based on 100 MV/m in LC /9/175Higo, LINAC10, Tsukuba

CERN made 20cm vg/c=1% structure tested up to 100 MV/m in early 90’s 90 MV/m with SLED at KEK >100 MV/m at SLAC 2010/9/176Higo, LINAC10, Tsukuba

DDS scheme was confirmed in mid. 90’s sharp edges in its cells  no high gradient test 1.8m RDDS1 2010/9/177Higo, LINAC10, Tsukuba

Many of the HDDS 60cm structures were made and tested in collaboration among SLAC, FNAL and KEK in late 90’s till 2004 Unloaded 65 MV/m was established in wake-field suppressed structures. These opened a base which extended to  CLIC 100 MV/m design choice  medium-gradient applications 2010/9/178Higo, LINAC10, Tsukuba

Series of CLIC test structures made as twins Targeting 100 MV/m In collaboration among CERN, SLAC and KEK 2010/9/179Higo, LINAC10, Tsukuba

Cell shape evolution 2010/9/1710Higo, LINAC10, Tsukuba

Nominal test procedure Design for CLIC (CERN) Fabrication of parts (KEK) Bonding (SLAC) CP (SLAC) VAC bake (SLAC) High power test (NLCTA- SLAC) High power test (Nextef- KEK) Two structures are made and treated as the twin for the evaluation. 2010/9/1711Higo, LINAC10, Tsukuba

Three existing test facilities and one under construction at CERN CERN - CEA – PSI – SLAC CERN X-band test stand K. Shirm in May 2010 NLCTA & ASTA at SLAC Nextef of KEK 2010/9/1712Higo, LINAC10, Tsukuba 1, 2 3 4

Judgment with breakdown rate 2010/9/1713Higo, LINAC10, Tsukuba

75 ㎝ 53 ㎝ 90 ㎝ 60 ㎝ Some NLC/GLC structure performance well in short pulse A. Grudiev, Dec /9/1714

Possibility of 65  100 MV/m BDR: promising result in CLIC prototype structure CLIC undamped T /9/1715Higo, LINAC10, Tsukuba

BDR of CLIC prototye but undamped structures T18_SLAC_2 T18 tested at SLACT18 tested at KEK 1.A pair of the same structures are tested in different laboratories. 2.Both agrees after nominal processing period. 3.BDR decreases as processing proceeds. 4.Not yet completely stable. Need study more. 2010/9/1716Higo, LINAC10, Tsukuba

BDR: Undamped T18  Damped TD18 T18 vs TD18 Undamped vs Damped SLAC vs KEK Sensitive to Eacc (Es, Hs) ~ X5~10 / 5 (MV/m) BDR(damped) ~ 100 X BDR (undamped) To be studied! Damped structure: High  T Any other mechanism? 2010/9/1717Higo, LINAC10, Tsukuba

BDR versus RF width or  T (pulse heating) TD18_Disk_#3 BDR versus  T (pulse temperature rise) Undamped Damped Tight correlation with pulse temperature rise. Same at 100MV/m but pulse length   T Same  T 83~84 degC but diff. Eacc TD18_Disk_#2 BDR versus pulse width Similar correlation with pulse width. 2010/9/1718Higo, LINAC10, Tsukuba

Supplemental high-gradient studies DC arc at CERN  Calatroni MOP070, Yokoyama MOP075 Waveguide RF at SLAC and KEK Single-cell SW at SLAC  Valery talk FR105 Pulse heating at SLAC  Laurent MOP076 CZ 10-cell setup at SLAC Some of these are presented in the following talk by Valery 2010/9/1719Higo, LINAC10, Tsukuba

Breakdown rate for 5 single cell SW structures 1C-SW-A2.75-T2.0-Cu-SLAC-#1 (green empty diamond), 1C-SW-A3.75-T1.66-Cu-KEK-#1 (black solid circle), 1C-SW-A3.75-T2.6-Cu-SLAC-#1 (blue empty triangle), flat part of the pulse 200 ns, and 1C-SW-A5.65-T4.6-Frascati-#2 (red empty circle), and 1C-SW-A5.65-T4.6-Cu-KEK-#2 (red full diamond) ), flat part of the pulse 150 ns Valery, AAC 2010/9/1720Higo, LINAC10, Tsukuba TT BDR

Effort with parameter optimization for stable high gradient 2010/9/1721Higo, LINAC10, Tsukuba

Grudiev, at FNAL 2010/9/1722Higo, LINAC10, Tsukuba Compilation

Grudiev, at FNAL 2010/9/1723Higo, LINAC10, Tsukuba Sc

Unloaded 100MV/m T18 TD18 P (MW), Es (MV/m), Ea (MV/m),  T(C), Sc*50 (MW/mm2) Iris number P Ea Sc Es TT T18 unloaded 100MV/m P (MW), Es (MV/m), Ea (MV/m),  T(C), Sc*50 (MW/mm2) Iris number P Ea Sc Es TT TD18 unloaded 100MV/m From Grudiev, May th WS at CERN 2010/9/1724Higo, LINAC10, Tsukuba TT

Acc mode parameters TD18  TD24 From Grudiev, May th WS at CERN Both Sc and  T decreased by taking cell parameter optimization TestedTo be tested 2010/9/1725Higo, LINAC10, Tsukuba

Effort with other HOM damping scheme 2010/9/1726Higo, LINAC10, Tsukuba

Consists of rods, quads or halves Still poor high gradient performance. Adolphsen, CLIC09, /9/1727Higo, LINAC10, Tsukuba

E-fieldH-field Sc 6.75 W/μm 2 40 o K 50 o K R. Jones for CLIC DDS design, DDS scheme for CLIC Fabrication test was started. May evaluate high gradient performance and wake field. 2010/9/1728Higo, LINAC10, Tsukuba

Choke-mode design Possible test in C10 setup J. Shi CLIC choke mode design, CLIC collaboration with Asia Design in collaboration with Tsinghua U. High gradient test at KEK Design with choke mode 2010/9/1729Higo, LINAC10, Tsukuba

Efforts in fabrication technology Before – CERN: diamond-tool machining + vacuum brazing – SLAC/KEK: technology hydrogen diffusion bonding + vac baking Present to future – Collaboration among three – CERN follows SLAC/KEK to understand CERN-made T18 runs well, <2x10 -7 BD/pulse/m (CLIC req.) – Technologies are developed which can be realized at multiple places 2010/9/1730Higo, LINAC10, Tsukuba

GHz, damped structure, 26 cells, asymmetric disk (Ø80 mm), external diameter reference, internal cooling. RF DISTRIBUTION WAVEGUDE WITH WFM & DAMPING MATERIAL VACUUM MANIFOLD DAMPING MATERIAL TD 26 ( CONCEPTUAL DESIGN ) COOLING CIRCUIT LOADS CONNECTION BEAM RF REF. SHPERES G. Riddone, CERN,

Assembly of accelerating structures 2010/9/1732 T18 structures tested at SLAC/KEK showed excellent test results consequent validation of design, machining and assembly procedure NLC/JLC fabrication technology: validated to 100 MV/m (baseline for future CERN X-band accelerating structures) Higo, LINAC10, Tsukuba G. Riddone, 06/09/2010 CERN strategy

Baseline procedure 2010/9/1733 Diamond machining (sealed structures) H2 diffusion bonding/brazing at ~ 1000 ˚C Cleaning with light etch Vacuum baking 650 ˚C > 10 days J. Wuang Higo, LINAC10, Tsukuba G. Riddone, 06/09/2010

Vacuum brazing versus hydrogen brazing 2010/9/1734 Higo, LINAC10, Tsukuba Vacuum brazingHydrogen brazing Extensive program launched to improve our understanding on the influence of different thermal cycles on the copper surface G. Riddone, 06/09/2010 One of the key differences

X-band collaboration 2010/9/17Higo, LINAC10, Tsukuba35 KEK, Tsinghua, IHEP Structure design & fabrication High power KEK CERN & European labs. Design & fabrication High power CERN SLAC conducts Structure fabrication High power SLAC Basic research KEK / SLAC CERN/KEK collaboration etc CLIC US-HG Asian collab. CERN/SLAC collaboration UK In 2010

Conclusion CLIC BDR requirement – CLIC undamped structures T18 meet at 100 MV/m – CLIC damped structures TD18 meet at 90 MV/m – Need to confirm the long-term stability Important parameters were identified – Such as Sc and  T – New designs were made and to be tested in 2010 Fabrication technology – SLAC/KEK scheme is being reproduced by CERN – Problems are identified to be improved X-band collaboration – Worldwide collaboration is expanding centered at CLIC but also in other applications 2010/9/1736Higo, LINAC10, Tsukuba