Summary The process and the components The tooling Production back log estimation The handles and the estimated cost and delay.

Slides:



Advertisements
Similar presentations
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Advertisements

LHQ Coil 02 Winding and Curing Plan Miao Yu 03/21/13.
Christian Löffler Collaring to cold mass finishing 2 Outline Available tooling and operational status CMM of 5.5m coils Instrumentation Pairing.
11 T Dipole for DS Status of CERN Activities M. Karppinen CERN TE-MSC On behalf of B. Auchmann, L. Bottura, B. Holzer, L. Oberli, L. Rossi, D. Smekens,
EuCARD-HFM ESAC review of the high field dipole design, 20/01/2011, Maria Durante, 1/40 EuCARD-HFM ESAC Review of the high field dipole design Fabrication.
COIL & ASSEMBLY READINESS REVIEW, SEPT 2013 D. Smekens.
Preliminary Design of Nb 3 Sn Quadrupoles for FCC-hh M. Karppinen CERN TE-MSC.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Superconducting Large Bore Sextupole for ILC
Coil working group video-meeting P. Ferracin, J. C. Perez, S. Izquierdo Bermudez, X. Sarasola February 4th, 2014.
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
Fred Nobrega. 9 Dec 2014 Model Design & Fabrication – FNAL Fred Nobrega 2 Outline Background Mechanical Design Model Magnet Features Coil Technology and.
Thoughts about the MQXF development plan P. Fessia Thanks to discussions within the MDT section (P. Ferracin, J. C. Perez, E. Todesco, P. Ferracin), L.
P. Fessia, S. Krog-Pedersen F. Regis, L. Rossi
SC magnet developments at CEA/Saclay Maria Durante Hélène Felice CEA Saclay DSM/DAPNIA/SACM/LEAS.
FNAL QXF Curing Mold Miao Yu, FNAL 05/07/2013. FNAL Short Curing Press 2 2 meter long Capacity (pump psi) Max. force/cylinder kN (ton) Spacing cm(inch)
DOE Review of LARP – February 17-18, 2014 Coil Design and Fabrication Miao Yu February 17,
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
Follow-Up and Checkpoints of Harmonics in Collared Coils and Cold Masses E.Wildner AT-MAS-MA.
11 T Dipole Experience M. Karppinen CERN TE-MSC On behalf of CERN-FNAL project teams The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded.
11 T Dipole Status at FNAL Fred Nobrega January 21, 2014.
Fred Nobrega, Nikolai Andreev 21 September, 2015.
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
WP6 status Paolo Fessia. Summary Status of the WP6 and change of WP coordinator Lowβ quadrupole status Corrector status Cryostat status.
HIGH RAMP RATE SUPERCONDUCTING MAGNETS AT BNL Peter Wanderer BNL Archamps Workshop, March 2003.
FRESCA2 Technical Meeting 5-Validation of coil winding with Cu coils Françoise Rondeaux 09/06/ CEA-Irfu-SACM-LEAS - 5-Rondeaux- FRESCA2 Technical.
LARP Collaboration Meeting Racetrack Coil Fabrication
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
11 T Dipole Status May 2012 M. Karppinen CERN TE-MSC On behalf of CERN-FNAL collaboration.
Field Quality Workshop - Components - F. Bertinelli 1 Workshop on Field Quality Steering of the Dipole Production CERN, March 2003 Status and trends.
DOE Review of LARP – February 17-18, 2014 SQXF Coil Design and Fabrication Winding and Curing Miao Yu February 17,
Cold Mass and Assembly Tooling Design, Procurement Status and Assembly Plan Igor Novitski Fermilab 15 T Dipole Design Review April 2016 April 28-29,
CERN MBHSM0101 and Plan for Future Models F. Savary on behalf of the 11T Dipole Project Team.
First Q4 cold mass engineering follow up meeting 16/03/2016 Q4 Status update H. Felice, M. Segreti, D. Simon and JM. Rifflet.
Cold mass procurement, status and plan, QA-QC H. Prin With contribution from S. Becle, O. Housiaux, R. Principe, J.-L. Rudeiros Fernandez, F. Savary 3.
MQXFSD3 laminated structure J.C Perez N. Bourcey, B. Favrat, P. Ferracin, P. Moyret.
LARP CM15, SLAC, 11/3/2010GianLuca SabbiSummary of MS Parallel Sessions Summary of Magnet Systems Parallel Sessions GianLuca Sabbi LARP Collaboration Meeting.
MQXFS1 Protection heater delays vs. Simulations 9 May 2016 Tiina Salmi, Tampere university of technology Acknowledgement: Guram Chlachidze (FNAL), Emmanuele.
EuCARD-WP7-HFM meeting 15 November 2011 Status of construction of FRESCA2 dummy coil assembly Attilio Milanese, Juan Carlos Perez.
Closing Session Report
Hardware Challenges and Limitations
HL-LHC Magnet components and assemblies
Procurement Status Miao Yu 11/19/2013.
MQXC Nb-Ti 120mm 120T/m 2m models
Service channels between Tracker and PP1
Analytical Cost Model (16 T dipole)
Model magnet test results at FNAL
11 T Dipole Integration & Plans M. Karppinen
CSP 25th November 2010 Technical agreement number 3: overview
HO Corrector Magnets: decapole test and future plans
Rodger Bossert/Shlomo Caspi
D2 Status The contract for the construction of the short model
Agenda 9:00  - Welcome ASG speaker 9:10 -  Introduction -       P.Fabbricatore 9:25 - The D2   magnets in HL-LHC   -  E. Todesco.
11T Dipole – Single Aperture 2m Model
ERMC/RMM activities May 2017
Purchasing supplies at CERN
FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets
Functional Specification
Status report on MQYY (Q4)
CEA KE 2775 progress meeting WP3 – FRESCA 2 Magnet
DS11 T Transfer function, integral field and coil length
the MDP High Field Dipole Demonstrator
Analytical Cost Model (16 T dipole)
Analytical Cost Model (16 T dipole)
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
CEA Nb3Sn quadrupole magnet : test results and future
MQXF updates P. Ferracin October 9th, 2014.
11T Dipole for the LHC Collimation upgrade
Cooling aspects for Nb3Sn Inner Triplet quadrupoles and D1
QXF schedule and milestones
Presentation transcript:

Summary The process and the components The tooling Production back log estimation The handles and the estimated cost and delay

Clarification Collared coil production Cold Mass production CERN Back log From the measurement that triggers feed back to the moment when the corrected dipole gets to the same kind of measurements

The components I from SC Cable to Poles Copper wedges SC cable End Spacers Chips and wedge tips Inter-layer spacers winding curing CoilPole CERNCMA

The components II From Poles to Collared Coil Shim retainer 4 Poles Quench heaters Ground insulation 2 Dipoles Shims Collars Collaring 1 Collared Coil Collaring Rods Collar packs

Jeumont /Alstom Tooling Winding machine Winding machine 6 In. M a n. 6 Ou. M a n. Curing press + mould Curing press + mould Jeumont PMM Collaring press 6 In Shells 6 Out. shells

Ansaldo Tooling Winding machine Winding machine Winding machine Spare Winding machine 6 In. M a n. 6 Ou. M a n. Inner layer mould Outer layer mould Curing Press Collaring press CERN PMM Curing Press

BNN Tooling Winding machine Winding machine Winding machine Winding machine 6 In. M a n. 6 Ou. M a n. Curing press + inner layer mould Curing press + outer layer mould BNN PMM Collaring press

Back Log Estimation Total Back Log (number of collared coil) Production back log (Tprod X Rprod) Component stock back log

Collared Coil Production time divided in main phases firm I

Collared Coil Production time divided in main phases firm II

Collared Coil Production time divided in main phases firm III

Number of collared coil in parallel production

Production back log estimation Firm 1 collared coils week/CMAs 3 collared coils week/CMAs Winding back log Assembly back log Tot back log Winding back log Assembly back log Tot back log F I F II F III Total

The handles and their estimated cost and delay

Polar shims Delay of intervention: approx. 1 week to 4 weeks of production (shim procurement time) Cost of the intervention: max some thousands of CHF (1 set of shims about 1500 CHF, the cost will be equal to the number of set of shims not usable) Pole measurement Dipole assembly Collaring Shims

Mid plane insulation Delay of intervention: –Change of ground insulation: month of production (stock and intervention at the sub supplier) Cost of the intervention:average price to prepare ground insulation 9000 CHF/CC possible extra costs from 150 to1800 CHF/CC. Total extra cost: CHF to extra costs (i.e. 15 minutes more per layer is CHF) Pole measurement Dipole assembly Collaring Ground insulation

Copper wedges Delivery of modified copper wedges from the decision (14 working weeks) Modification of end spacer: –Machined pieces about 14 working weeks –Injected pieces longer For costs see after Copper wedges SC cable End Spacers Chips and wedge tips winding

New component production Copper wedges New geometry Drawings New tooling Approval manufacturer's drawings Production Acceptance Expedition to CMA 5 days 10 days 30 days 20 days 1 day 5 days Total time 70 Work. Days T0T0

Previous experience and cost estimation Decision 15/07/01 Drawing cross section 15/08/01 Delivery of end spacers for 2 CC and chips for 2 CC 15/11/01 Delivery of new profile for 10 magnet each CMAs: 30/11/01 Delivery of spacers 10 CC per CMAs 20/12/01 Delivery of molded chips 01/02/02 Cost I: 50 batches of copper wedges (500 magnets, i.e. cable delivered for 3/8) produced up to now CHF/profile for tooling Cost II: at least only for end spacers CHF (engineering + components) Cost III: quality problems

Correction of the magnetic length with nested laminations We can correct the magnetic length acting on the number of nested lamination 10 cm of extra nested lamination (Delta Bdl 7 units ): –10 cm more nested laminations: +660 CHF/CM –10 cm less iron lamination: -150 CHF/CM –10 cm net cost 1 magnet : +510 CHF/CM For 1 CMAs: about CHF Other possible schemes: –Nested laminations transfer between CMAs –Use of special full non magnetic laminations

ChangeMaterial delivery time back log Production back log Total Polar shims 12 CC 36 CC 3 CC 12 CC 3 -12CC CC Mid plane insulation 24 CC 72 CC 3 CC 12 CC 27 CC 84 CC Copper wedges 14 CC 140 CC 45 CC 88 CC 59 CC 230 CC Laminations 12 CM 48 CM 24 CM 36 CM 72 CM

Acknowledgements F. Bertinelli, C. Lanza, A.Schiappapietra, E. Todesco The whole MAS-MD and MAS-MA sections