Engineering Approach EDM Collaboration Meeting 2-07 Jan Boissevain.

Slides:



Advertisements
Similar presentations
Final(?) Design of G0 Upstream Shielding Larry Bartoszek BARTOSZEK ENGINEERING 10/22/05.
Advertisements

Task 3.
EDM Collaboration Meeting, October 5-7, 2006 Valve R&D Steve Williamson UIUC.
VRVS, Jan. 2006CERN AB-ATB1 Safety Review Solenoid & Cryogenics CERN AB-ATB VRVS session, Jan
© Nintendo Game Document Game Development - Spring
23 October 2005MICE Meeting at RAL1 MICE Tracker Magnets, 4 K Coolers, and Magnet Coupling during a Quench Michael A. Green Lawrence Berkeley Laboratory.
FNAL-SCRF 会議報告 1. Cryomodule, Plug-compatible Interface ( 大 内) 2. High Pressure Code, 5K Shield (Tom Peterson)
Collab 5/26/06 #1 EDMEDM Martin Cooper, Los Alamos Co-spokesperson and Contract Project Manager for the EDM Project for presentation to The EDM Collaboration.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
Project Status Report Presenter Name Presentation Date.
EDM Magnetic Shielding (WBS 5) and Magnets (WBS 6) B. Filippone and B. Plaster Caltech Internal Cost and Schedule Review February 11, 2004.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
1 Preparation for the 3 He Injection Test 11/2007 MIT/BATES D. Dutta*, H. Gao, M. Busch, Q. Ye, X. Qian, W. Zheng, X. Zhu ( Duke University) ASU, BU, Caltech,
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
1 NEDM 4 He Purifier and Other Cryogenic Issues David G. Haase North Carolina State University Update on Cryovessel Engineering Evaporative Purification.
Type IV Cryomodule Proposal (T4CM) Don Mitchell, 16 JAN 2006.
Cryomodule Design and R&D during the EDR phase Robert Kephart With input from the T4 CM Collaboration.
The Four-Layer Conventional Magnetic Shield Brad Plaster, Caltech May 25, 2006  “Current” design  Estimated shielding factors  Production and time-scale.
EDMEDM EDM Fast Start, May 23, 2006He3S, Steven Williamson EDM Fast Start Helium-3 Services (He3S) Steven Williamson May 23, 2006.
January 4, 2007 Project Overview RHIC II Project Internal Cost Review Roberto Than Cryogenics Systems January 4, 2007.
EDMEDM EDM Collaboration Meeting Project Management Fast Start Summary Prepared by: John P. Tapia May 25, 2006.
ITER- TBM Planning and Costing Activity DCLL TBM Mechanical Design ( ) & TBM-Port Interface ( ) Presented by Mo Dagher December
EDMEDM EDM Collaboration Meeting 3-06 Jan Boissevain, P-25 March 2, 2006 NCSU EDM Experiment Design Status.
Response to TAC8 and Annual Review Recommendations John Haines Head of Target Division April 2, 2014.
E. Ihloff February 8, 2008 FNPB-UCN building usage by nEDM.
P25 Interface 5/19/08 #1 Martin Cooper, Los Alamos Co-spokesperson for the EDM Project for presentation to The nEDM Subsystem Managers Duke University,
Summary ( Cryomodule, Plug-compatible Interface) Norihito Ohuchi.
EDMEDM LANL Review of EDM Cost and Schedule Jan Boissevain for Walter Sondheim, P-25, Los Alamos February 11, 2005, at Los Alamos National Laboratory Conventional.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
EDM Collaboration Meeting, October 5-7, 2006 WBS He Services (He3S) “Homework” Steve Williamson.
Office of Nuclear Physics Collaboration Meeting 5/19/08 #1 nEDM Reworked Schedule Kim Selvage Project Controls Analyst.
EDM Engineering Issues General Mechanical Considerations EDM Cryostat Plan D ANSYS EMAG Calculations ANSYS MECH Calculations 3 June ‘03 J. Boissevain.
22 October 2005MICE Meeting at RAL1 Tracker Solenoid Overview Michael A. Green Lawrence Berkeley Laboratory MICE Collaboration Meeting 22 October 2005.
Slow controls R and D Chris Gould North Carolina State University and TUNL.
Summary of Valve Design Status for nEDM L. Bartoszek BARTOSZEK ENGINEERING 6/20/05.
TC Straw man for ATLAS ID for SLHC This layout is a result of the discussions in the GENOA ID upgrade workshop. Aim is to evolve this to include list of.
NEDM Collaboration Meeting 5/2008 Preliminary Engineering Report nEDM Central Detector John C. Ramsey Los Alamos National Laboratory.
EDM in ER2 at LANSCE Jan Boissevain LANSCE ER-2 Stake Holder Meeting
EDMEDM LANL Review of EDM Cost and Schedule Jan Boissevain, P-25 February 11, 2005, Los Alamos National Laboratory EDM Reference Design Tour of the Reference.
3 He R&D Plan at Los Alamos Takeyasu Ito Los Alamos National Laboratory EDM Collaboration Meeting May 26, 2006 Oak Ridge, TN.
EDM Assembly and Commissioning – or – How to Cut Two Years from the Project P. Huffman and V. Cianciolo.
EDM Fast Start Presentation WBS 11 – Assembly and Commissioning Vince Cianciolo, Paul Huffman May 23, 2006.
1 Cryogenic Design and the 4 He Evaporative Purifier David G. Haase, et al., North Carolina State University.
EDMEDM EDM Collaboration Meeting 6-05 Jan Boissevain, P-25 June 20, 2005, Los Alamos National Laboratory EDM Reference Design.
Status of Engineering Preparations for CD2/3A nEDM Collaboration Meeting – MIT Bates Jan Boissevain November 2, 2007.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
1 BNL LHC Hi-Lumi QXF Vertical Test Facility Status Update M. Anerella, H. Hocker, P. Joshi, P. Kovach, A. Marone March 28, 2016.
Long-Baseline Neutrino Facility LBNF Beamline optimization schedule Vaia Papadimitriou LBNF Beamline Manager Accelerator and Beam Interface Group Meeting.
Attempting to Cost Estimate the nEDM Upper Cryostat Larry Bartoszek, PE Bartoszek Engineering 12/2/04.
1 Building Design Progress Dan Wilcox March 2012.
NEDM Cost and Schedule Review, February 11, 2005 Upper Cryostat and Valves Cost and Schedule for WBS 3.2, 3.3, 3.4, and 8.2 L. M. Bartoszek D. H. Beck.
Office of Nuclear Physics R&D 12/14/06 #1 Risk Based R&D Plan Martin Cooper Los Alamos.
… getting there … 112/02/2014A. Fabich, EN-MEF-LE.
Cryovessel Engineering David Haase, Jan Boissevain, Ernie Ihloff WBS long lead time items Cryovessel Dilution Refrigerator Helium Liquefier.
Long-Baseline Neutrino Facility LBNF News and brief overview of Beamline plans for the next few months Vaia Papadimitriou Beamline Technical Board Meeting.
Specifications for the Integrated Tests II Paul Huffman.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
Design of the Injection Can
Totem Gas Systems ( T1 , T2 ) S. Haider PH / DT1.
Progress and Issues with VTS Upgrade
ILC-EDMS presentation 3D Visualisation Documents sharing
News and brief overview of Beamline plans for the next few months
S1-G cryomodule assembly status
The Big 6 Research Model Step 3: Location and Access
Installation of Photon Beam Transport to FEH
Process for Organising Software Development Activities
Project Management Considerations
Bunker Project Schedule/Budget
SNS PPU CRYOMODULE FDR Magnetic Shields Gary Cheng June 10, 2019.
WUL Monolith Inner & Outer Shielding
Presentation transcript:

Engineering Approach EDM Collaboration Meeting 2-07 Jan Boissevain

Drawings Time estimate varies from 2 to 10 hours/drawing # of drawings: ~1000 As much as possible, we will define interfaces and write specifications. Vendors will create drawings and provide documentation (model if possible) During the next year, make a test case and measure the time

Major Purchases Big Dilution Refigerator –Define pump system and piping –Define interface to Cryo-vessel Helium Liquefier 4 Layer MuMetal Shield Beam Line

High Priority Tasks Define Dilution Refrigerator Design Interface between Cryo-vessel and MuMetal Shield assembly => MuMetal support structure Design Cryo-vessel – especially the central volume

Engineer Availability Jan Boissevain100% Matthew Busch25% John Ramsey25% Ernie Ihloff25% Larry Bartoszek25% Chris Daurer25% NCSU Engineer??

Conclusions? CD2 review probably should be delayed –$$ drive the schedule –No “New Starts” R&D finish time should be delayed