2006 Hurricane Preparedness June 5, 2006 Sumter Electric Cooperative, Inc R. Ben Brickhouse: Director of Engineering & IT John J. LaSelva: Director of.

Slides:



Advertisements
Similar presentations
Utility Needs and Smart Grid for Major Storm Events July 11, 2013 Edward Gray, PE Director – Transmission and Distribution Engineering.
Advertisements

Florida Public Service Commission 2007 Hurricane Preparedness Briefing May 23, 2007 Kissimmee Utility Authority Ken Davis Vice President Engineering &
FPUA Storm Readiness 2007 Florida Public Service Commission Internal Affairs May 23, 2007 Craig Brewer- Superintendent of Electric T&D.
Lee County Electric Cooperative 2006 Hurricane Preparedness Plan.
Hurricane Season Preparedness Briefing Gulf Power Company June 5, 2006.
Progress Energy Florida 2007 Hurricane Preparedness Florida PSC Hurricane Preparedness Meeting May 23, 2007.
Florida Public Service Commission Internal Affairs Hurricane Season Preparation Paul Davis, Director Energy Control Center June 5, 2006.
JEA Storm Readiness 2006 Florida Public Service Commission Internal Affairs June 5, 2006 Presenter: Ted Hobson, VP, Fuels, Purchased Power & Compliance.
After the Storm: Using GIS for Damage Assessment and Restoration October 2004 O ne GIS, Inc. One Platform, One Solution, One Company…
FPL Hurricane Assessment Operating Committee January 25, 2005.
Westar Energy Emergency Preparedness and Restoration TFR Meeting June 26, 2012 Jim Tyler Director, Distribution Services.
2011 Windstorm “Be Prepared: Preventing Disaster/ Planning for Recovery” South Bay Cities Council of Governments 13 th Annual General Assembly February.
Stray Current Investigations A Method of Troubleshooting Stray Current on Underground Residential Distribution (URD) Loops Stacey Mighty Malcolm Distribution.
August Comprehensive Reliability Plan for Montgomery County, Maryland.
Feeder Maintenance Program. The purpose of the Cooperative is to provide safe, reliable, low-cost energy services in fiscally responsible partnership.
Nelson Hydro Downtown Conversion July 26, 2010 Project Overview.
New Product Overview Homac STORM SAFE™ Connector Systems Presented by: Presented by: Roy Jazowski - Director of R&D Mark Hammer – Director of Marketing.
Dealing with Catastrophic Storm Issues January 2009 SE Missouri Ice Storm Missouri PSC Storm Workshop Presented by Dave Wakeman Manager, Distribution Operating.
IMPACTS OF LARGE DISTRIBUTED GENERATORS ON CENTERPOINT ENERGY’S DISTRIBUTION SYSTEM 1 Presented by Ed Briggs, P.E. Manager of Electric Distribution Planning.
1 March 1, 2007 Report An Overview October 30, 2006 – Staff Workshop.
Distribution Management System Implementation at Florida Power & Light
Dayton Power and Light Patrick Slone EMS Safety Coordinator.
1 Entergy Transmission Asset Preservation Department 2004 Objectives Entergy Transmission Planning Summit New Orleans, LA July 10, 2003.
Experience you can trust. Hurricane Hardening Commission Staff Workshop on Electric Utility Infrastructure Richard E. Brown, PhD, PE Tallahassee,
Electric Infrastructure Workshop Gulf Power Company January 23, 2006.
SDG&E Electric Reliability Reporting CPUC Workshops May 26-27, 2015.
Introduction & Opening Remarks l Hurricanes of 2004 & 2005 highlight the need for a fresh look at these issues l We support this effort and will be active.
Florida Power & Light 2006 Hurricane Preparedness Plan June 5, 2006 Presented by: Geisha Williams.
January 2009 SEMO Ice Storm Extreme Measures IEEE-PES St Louis Chapter Meeting June 18, 2010 Presented by David Wakeman Vice President, Energy Delivery.
Experience you can trust. 1 Electric Infrastructure Hardening Rebuilding Utility Infrastructure LSU Center for Energy Studies Bill Snyder
Lee County Electric Cooperative 2007 Hurricane Preparedness Activities.
FPSC Electric Utility Infrastructure Workshop Florida Municipal Electric Utilities Alan Shaffer Assistant General Manager - Delivery Lakeland Electric.
Utility Engineers, PC.  Generation  Transmission  Distribution.
Electric Utility Infrastructure Commission Staff Workshop January 23, 2006.
1 Case Study: Pacific Gas & Electric Company San Francisco Lifelines Council Edwards Salas Senior Vice President, Engineering and Operations, PG&E February,
Florida Municipal Electric Utilities May 6, 2009 Paul Kalv, Director City of Leesburg Electric Department Florida Public Service Commission Docket No.
1 Verizon Florida, LLC Hurricane Season Preparation PSC Workshop – May 6, 2009.
Tampa Electric Company 2009 Hurricane Season Preparation Regan Haines Director, Energy Delivery May 6, 2009.
Glades Electric Cooperative Infrastructure Miles of Line 2,213  Overhead Dist.2,180  UndergroundDist. 33  Transmission 87 16,402 meters Average 7.
2009 Hurricane Season Preparations Florida Public Utilities Company May 6, 2009.
2015 HURRICANE SEASON PREPARATIONS March 18, 2015.
2014 Hurricane Season Preparation Informal Meeting for Electric Utilities with Florida Public Service Commission Staff March 26, 2014.
2009 Hurricane Preparedness Richard Shaheen Sr. Director, Engineering & Technical Services May 6, 2009.
Hurricane Season Preparation Briefing Florida Public Service Commission May 1, 2008 Kevin Wailes General Manager – Electric Utility.
Tampaelectric.com Presented to the Florida Public Service Commission May 1, 2008 Tampa Electric Company 2008 Hurricane Season Preparation Regan Haines.
© 2012 San Diego Gas & Electric Company. All copyright and trademark rights reserved. Wildfires, Vegetation Management and Powerlines Presented to Senator.
2009 Hurricane Season Preparedness Briefing Gulf Power Company Presented by Andy McQuagge Power Delivery Services Manager May 6, 2009.
2008 Hurricane Season Preparedness Briefing Gulf Power Company Presented by Andy McQuagge Power Delivery Services Manager May 1, 2008.
2015 Storm Readiness Report Kurt Miller, Director of Engineering Suwannee Valley Electric Cooperative, Inc.
2014 Storm Preparedness Jeff Brewer – Manager of Engineering Tri-County Electric Cooperative, Inc.
2015 Hurricane Season Preparedness Briefing Jorge Puentes Engineering Manager – Northeast and Northwest Divisions March 18, 2015.
Verizon Florida, LLC Hurricane Season Preparation PSC Workshop – May 1, 2008.
2014 Hurricane Season Preparedness Briefing Jorge Puentes Technical Projects Manager – Northeast and Northwest Divisions March 26, 2014.
Informal Meeting with FPSC Staff 2015 Hurricane Season Preparation March 18, 2015.
Bywater Reliability Update Gary Huntley Entergy New Orleans, Inc. Regional Manager Entergy New Orleans, Inc. July 28, 2010.
Permanent Solutions to Temporary Loads: An Alternate Approach to Electrical System Design for Short Term and Mobile Industrial Loading Presented by: Eli.
Florida Keys Electric Cooperative Association, Inc. Storm Hardening Florida Public Service Commission May 1, 2008 Scott Newberry, CEO John Stuart, COO.
Resiliency and Reliability
Utility Needs and Smart Grid for Major Storm Events
Impact of Hurricane Ike on
2008 Hurricane Season Preparations
Florida Public Service Commission
Hurricane Preparedness Plan 2008
Pacific Power Seismic Preparedness Update
Progress Energy Florida 2008 Hurricane Preparedness Florida PSC Hurricane Preparedness Meeting May 1, 2008.
2007 Hurricane Season Preparations
Florida PSC 2014 Hurricane Season Preparation
Florida PSC Hurricane Preparedness Meeting May 6, 2009
2007 Hurricane Season Preparedness Briefing
Presentation transcript:

2006 Hurricane Preparedness June 5, 2006 Sumter Electric Cooperative, Inc R. Ben Brickhouse: Director of Engineering & IT John J. LaSelva: Director of Reliability & Operations

SECO Overview 7 Counties in Central Florida 150,000+ members 8.7% member growth rate 2

SECO Electrical System Overview Overhead Distribution: – –4537 circuit miles – –149,000 poles – median pole age is 17 yrs Underground Distribution (URD) – –1845 circuit miles Transmission Facilities: – –72 miles of 69kv transmission circuits – –1250 structures 43 Substations 3

  Reliability Based Design   On-going Asset Management   Vegetation Management   Restoration Plan Steps to Hurricane Preparedness: 4

SECO Reliability Based Design Transmission: – –Joint transmission planning with Progress Energy Florida for capacity and reliability – –Minimize all radial transmission delivery points – –All new transmission structures are “Spun Concrete” versus wood – –Designed per NESC “Extreme” wind loading criteria 5

SECO Reliability Based Design Substation: – –All new and renovated substations: “Low Profile” steel “Ring Bus” configured and designed for multiple power transformers with load transfer capability – –All existing and new substations: Connections for SECO’s mobile transformers SCADA control including individual feeder telemetry 6

SECO Reliability Based Design Distribution: – –Designed per “Rural Utility Service (RUS)” and “National Electric Safety Code (NESC)” specifications for 100 mph wind loading – –~80% of new subdivision construction is URD – –New OH feeder circuits are constructed to reliability based model feeder standards for maximizing both conductor sizing and sectionalizing capability 7

SECO On-Going Asset Management Asset Inspections: – –Transmission: Ground / climbing inspection completed in structures will be replaced with spun concrete poles 5 year cycle – –Thermographic Inspections: Transmission: Annually Substation: Bi-monthly “ALL” OH Feeder Lines: Every 18 months URD Facilities: Reliability dictates 8

SECO On-Going Asset Management Distribution: –Pole inspections: Ground line & visual - Current 9 year cycle begun in Going to 8 yr in – 2005: – –37,599 Inspected – –255 Rejected and replaced (0.7% rejection) –URD Inspections: Full inspection was complete in Will implement an 8 yr cycle in “State of the Art” fully integrated GIS / Design / OMS / Storm Center Systems – General Electric 9

SECO – Vegetation Management 3 year trim cycle of all OH facilities since 1996 Hurricanes in 2004: Trees - Primary cause of outages SECO lost 662 poles in 3 hurricanes (0.4%) Poles Up Wires Down 10

Post Hurricane Evaluation of Trim Policies: Conclusions: Trees were major cause of outages Increased tolerance by members for aggressive trimming Increase budget expenditures for long term gains (Increased 30% in 2006) Actions Taken: Entire system assessed by ACRT (Consultant) – –2% trees contacting lines (industry 10%) Revised specifications: – –Species specific – –Increase to remove trees vs. trim – –Implemented “Ground to Sky” for new circuit projects 11

BEFORE 12

AFTER 13

BEFORE 14

AFTER 15

BEFORE 16

AFTER 17

BEFORE 18

AFTER 19

SECO: Disaster Recovery Plan 20

Restoration Model PLAN MATERIALLOGISTICS PERSONNEL 21

SECO’s Emergency Plan Prior to Storm Season Plan Reviewed / Updated Planning with Local EOC’s Materials Staged Logistics Pre-Arranged –Caterers, fuel, hotels, buses, tents, ice, water, etc. Personnel –Florida / Southeast Mutual Aid, establish contracts with vegetation crews and line crews 22

SECO Restoration Priority 1. 1.Transmission Lines 2. 2.Substations 3. 3.Feeders Emergency Services (Hospitals, Special needs Shelters and Shelters) 4. 4.Fused Laterals / Taps 5. 5.Individual Homes 23

Customer Newsletter: Explains restoration process at the beginning of storm season Paid Advertisements: Appear in the daily newspapers 1 & 2 days prior to storm impact 24

SECO’s Emergency Plan Hurricane Predicted – –Activate Plan (Pull the Trigger) – –Run “Damage Prediction and Manpower” Model: Based on historical damage – –Materials / Manpower / Logistics Activated pre-landfall 25

Sept Daily MWH Sales “Stick to the Plan” Storm Impact 26

Conclusions   SECO currently designs a reliable transmission, substation, and distribution system based on RUS and NESC standards   SECO currently performs inspections on all its assets – frequency is increasing in 2007   SECO has an aggressive vegetation management program that was revised post 2004 hurricanes   SECO has a disaster recovery plan that is reviewed, revised, and institutionalized based on “Lessons Learned” by both SECO and the industry 27

Questions? 28