Proton Improvement Plan (FY13 PMG Q3). William Pellico, Fermilab PMG, Aug 21 2013 2 PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary.

Slides:



Advertisements
Similar presentations
PIP Update Oct Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken Domann.
Advertisements

Proton Source Workshop Booster Downtime Wednesday, December 8, 2010 T. Sullivan.
Proton Source Workshop December 7 & 8, 2010 John Reid December 8, 2010.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
PIP Update June 26 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
PIP Update Aug 15 th Agenda Summary Update – Current Activities Dennis Barak / Kiyomi Seiya - High-Power Ferrite Testing Ryan Crawford - Linac and.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Proton Improvement Plan (FY13 PMG Q4). William Pellico, Fermilab PMG, Nov PIP FY13 Q4 Summary Task Highlights Budget and Labor Review Summary.
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Proton Improvement Plan (FY12 PMG Q4). William Pellico, Fermilab PMG,October FY12 Summary Q4 Task(s) Summary – Highlights RFQ Injector Budget.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
Proton Improvement Plan (PIP) William Pellico PIP and MI 700 kW review 21 – 22 January 2015.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Proton Improvement Plan (FY13 PMG Q1). William Pellico, Fermilab PMG, January FY13 Summary Q1 Task Summary – Highlights RFQ Injector Budget.
All Experimenters Meeting PIP Report William Pellico on behalf of PIP team 4/7/2013.
PIP Update Jan Agenda Summary Update – Current Activities – Updates (Ken, Pat and John) – Additional Meetings/Notes.
Proton Improvement Plan Bob Zwaska July 7, 2014 All-Experimenters Meeting.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
Proton Improvement Plan William Pellico FRA Visiting Committee Meeting March 14-15, 2011.
PIP FY14 PMG W. Pellico 7/8/14 7/8/2014PIP PMG. PIP Activities RIL & Linac – 200MHz RF Power System High Level RF Linac Modulator 7835 Procurement – Accelerator.
2015 Shutdown Joe Compton 3/11/2015. RIL PIP Work  Install operational laser notcher  5 days  Dave Johnson & Todd Johnson.
PIP PMG Project Controls Elmie Evans-Peoples PIP PMG Oct 25, 2012.
Proton Improvement Plan Accelerator Sector Planning and Strategy Oct. 27 and 28 W. Pellico Bob Zwaska, Keith Gollwitzer, Fernanda Garcia Valery Lebedev,
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
PIP Update Sept. 18 th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Pat.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken.
PIP Update Oct Agenda Summary Update – Current Activities Updates/Talks: Dave Johnson – Linac Notching (laser)
PIP FY15 PMG W. Pellico PIP PMG March 5 th PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
PIP Update July 30 th Agenda Summary Update – Current Activities/Updates – Project Controls Update: K. Domann – Linac Lattice – Valeriy Kapin.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (Joe Compton - shutdown) – Additional Meetings/Notes.
PIP FY15 Q4 Report W. Pellico PIP PMG November 5 th 2015.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 07/01/2013.
PIP Budget Codes Budget FY12 Updates October 19, 2011 PIP Meeting.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
Accelerator Status and Plans
Proton Improvement Plan Overview Bob Webber July 13, 2011.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Alexander Valishev - Simplified Modeling of Space Charge Losses in Booster.
Proton Improvement Plan William Pellico Fermilab Institutional Review June 6-9, 2011.
PIP Update June 18 th Agenda Summary Update – Current Activities/Updates – Reid, Slabaugh.
Proton Improvement Plan William Pellico 44th Fermilab Users' Meeting June 1-2, 2011.
PIP Update April 10 th Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Eliana.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
Proton Improvement Plan (PIP) William Pellico Fermilab Annual Science and Technology Review September 5-7, 2012.
PIP Update April 3 rd Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
High Intensity Booster Operations William Pellico PIP II collaboration Nov. 9 th 2015.
PIP Update Dec 17 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
SNuMI: WBS 1.1 Booster Upgrades Eric Prebys $642K FY06$ (no contingency, no G&A) xx% contingency Main Injector & Recycler BNB NuMI Tunnel Booster Ring.
Proton Planning Eric Prebys FNAL Accelerator Division.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
Proton Plan PMG 4/18/05 E Prebys/J. Sims 1 Proton Plan Status March Report Eric Prebys Jeff Sims.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
PAC Meeting, December 12, Prebys 1 The Problem.
PIP Update March 6 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update May 28 th Agenda Summary Update – Current Activities/Updates – Ken Domann.
Proton Plan PMG 7/27/06 J. Sims 1 Proton Plan Cost and Schedule Report Jeff Sims.
PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.
Booster High Power RF at PIP-II Era John Reid February 18, 2014.
PIP Update May Agenda Summary Update – Activities – Budget – Plans Update Slides – Solid StateTom – ModulatorsRene – High Power Ferrite Testing.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Matt – Cavity Refurbishment) – Additional Meetings/Notes.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
High Power RF Systems for 2-8 GeV Fast Cycling Synchrotron PROJECT X (ICD-2) John Reid September 11, 2009.
Presentation transcript:

Proton Improvement Plan (FY13 PMG Q3)

William Pellico, Fermilab PMG, Aug PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary Outstanding Issues Plans - Schedule FY13 Budget Updates FY13 Goals/Issues - Next Quarter Additional PIP Items

William Pellico, Fermilab PMG, Aug LossesFluxViability Shielding Improvements New Tuners Linac HP RF Dampers Cogging BPM systems RFQ Injector Booster Anode Supplies Collimation System LCW systems Transformers Beam Physics/Optics Booster Cavity Refurbishment Linac Notch Booster Solid State Linac Modulators Booster Notcher/Absorber PIP – Path to Higher Proton Throughput and Reliability Bias Supplies New Cavities Over 30 Tasks ~87 M $$ ~ 7 years of work

William Pellico, Fermilab PMG, Aug FY13 Q3 Task Summary – Highlights

PIP FY13 Milestone Summary William Pellico, Fermilab PMG, Aug The current RLS is out of date and is being updated. Effort to adjust RLS when changes to budget and labor occur is challenging. Not Completed Completed FY13 Q1 FY13 Q2 FY13 Q3

WBS 1.1 LINAC FY13 Q3 Summary Tasks at a Glance 6 William Pellico, Fermilab PMG, Aug Linac WBS TaskFY13 Q3 Progress Summary WBS High Level RF CPI reviewing costing and CPFF agreement as required by DOE WBS Linac Modulator Completed 2 stage test – Working on 3 cell configuration WBS Procurement Receipt of a new tube in July WBS Simulations and Studies Created an input file of DTLs, Manual written, TRACEWIN model WBS Linac Notch Creation Progress in beam shaping optics, 3D model of vacuum assembly WBS Power Distribution Hatch install approved (installed in Aug) WBS Vacuum System Valves for 400 MeV delivered (installed in Aug)

7 William Pellico, Fermilab PMG, Aug WBS 1.1 LINAC (Highlights) WBS Modulators WBS Linac Notch Creation WBS Power Distribution Hatch Install Modulator 3 Cell Testing Linac Notch Creation Detailed study DTL region Lattice in TraceWin 3D Print of laser cavity

8 William Pellico, Fermilab PMG, Aug WBS 1.2 Booster FY13 Q3 Summary Tasks at a Glance WBSTaskHighlight Cavity Refurbishment7 th cavity refurbished and certified (June 24 th ) New TunersDelivery of new low mu cores – pass high power test Delivery of new high mu cores – pass high power test Both mu’s have lower values; working with vendor Simulations & StudiesNew person working on optics Alignment & ApertureGradient magnet moves and alignment Notcher SystemOperational – working on short kickers/PS Radiation ShieldingAnalyses of radiation studies data; working with ES&H on proposal for shielding assessment addendum

William Pellico, Fermilab PMG, Aug WBS 1.2 Booster (Highlights) Notcher System Cavity Refurbishment Buildup of High Voltage Rack for Short Kickers Cavity preparing to repair flanges Cones and new cooling loops Labor intensive work

Saga of new ferrites for cavity tuners William Pellico, Fermilab PMG, Aug Testing Ferrite Core Low Power High Power Issues: Old Vendors Gone New vendors having difficulty making similar ferrites…. Looking for high Q, low loss and two values of mu ~(12, 20) TD ready to build tuners once we have ferrites

William Pellico, Fermilab PMG, Aug

WBS Accelerator Physics (Booster) WBS Alignment & Aperture  Magnet moves  Scans Location Long 16 Vertical Move This was the fourth area where we moved magnets…. More to come William Pellico, Fermilab PMG, Aug Tunnel Location mm

William Pellico, Fermilab PMG, Aug Budget and Labor Review Summary

William Pellico, Fermilab PMG, Aug FY13 To-date FTEs by OHAP – Fcst vs Act

FY13 To-date FTEs by Div – Fcst vs Act 15 William Pellico, Fermilab PMG, Aug

16 PIP Labor Usage (FTE) Planned Actual

William Pellico, Fermilab PMG, Aug M&S Task Totals 1.00 Program Management$187, Linac High Level RF$2,212, Linac Modulator$125, Linac Notch Creation$23, Linac Power Distribution$13, Cavity & Tuner Refurbishment$153, New Tuners$524, Booster Simulations & Studies$10, Booster Notcher$92, Booster Dampers$2, LCW$48, Power Distribution$25, Solid State Upgrade$580,264 Total M&S$3,998,025 PIP M&S BUDGETYTD OBS06/13 RIP BUDGET BALANCE w RIP'sYTD COST OCT-12 OBS NOV-12 OBS DEC-12 OBS JAN-13 OBS FEB-13 OBS MAR-13 OBS APR-13 OBS MAY-13 OBS JUN-13 OBS JUL-13 OBS Total All Labor & M&S K$ April - Correction for Solid State Task Closure 82% of FY13 Allocated

Supplemental Spending William Pellico, Fermilab PMG, Aug ID PIP Tasks Task Code 1 DTI switches and controller for extractor (and spare for Einzel Chopper) AD 2 Booster Transformer (MCC and spare breaker) AD 3 Buncher Solid State RF power AD 4 12 Scroll Pumps for Booster AD 5 Linac Roughing Station AD 6 Laser Amp for Linac Notcher AD 7 1 st Linac RFQ Turbo and Roughing station/controls AD MeV line pumps AD 10 2 nd Linac Booster roughing and turbo pumps stations AD 12 Replace 5 Booster valves AD 13 Linac Modulator (SLAC Version) AD 14 SS amp for Linac Driver system AD 15 Booster Anode Supply Transformers AD 16 Laser notch pulser AD MHz Circulator AD 18 Linac 55 chilled water pump and plumbing AD 19 3 rd Linac AD 20 Injector Solenoid and trim PS RF test ‘cave’ or shielded room AD Additional funds were provided in July – Although part of Q4 – This is a significant $$ and will have a positive effect on the schedule. Part of funds will be used to remedy the recent PS budgets which impacted PIP goals (7835 tubes). Part of funds will be used to put back track PIP items impacted from previous reductions (e.g. laser notcher). Part of funds will be used to move tasks forward (Refurb)

Plans - Schedule

William Pellico, Fermilab PMG, Aug Proton Source/PIP – FY13 Calendar Goals (PIP & PS) On Schedule Booster MI Startup Beam Dump/High Intensity Tuning Q2 OLD Tune-up Booster SS RF System Magnet Moves Alignment Refurbishment Optics/Harmonics Studies While waiting for users PIP continues to take advantage of Proton Source only operations :

Proton Improvement Plan Projection NOvA Shutdown g-2 Mu2e 8 GeV 120 GeV LBNE William Pellico, Fermilab PMG, Aug MiniBooNE Maybe

Additional PIP Items

Cooperation on Linac Power Amplifiers Brookhaven Linac is very similar design to Fermilab Low- Energy Linac  Not interested at this point in any financial arrangement SLAC SOW to provide expertise and local oversight for the klystron prototyping LANL has sent information on their pursuit of a 200 MHz klystron (CPI). Interested but still pursuing Thales tube. William Pellico, Fermilab PMG, Aug

Nigel Tour of MI-60 / Cavity Refurbishment Work Nigel visit to MI-60 to try and understand why it is taking so long to refurbish cavities. Reassures us that once he is in charge – things will change. William Pellico, Fermilab PMG, Aug

PIP FY13 Q3 Summary & Concerns WBS 1.1 Linac  Linac WBS efforts are in good shape Klystron effort continues – Business Services/CPI/PIP  Modulator efforts continue with both SLAC and AD/EE support  Simulation and Studies-> continue development code for DTL lattice, WBS 1.2 Booster  Cavity Refurbishment – Labor & Time constraints Contract Employees Dosage (ALARA) – will need to rotate personnel Need to deal with operations vs. repair (MI startup)  Booster shielding – progressing  Booster Rep rate limit – still unresolved and require testing  Booster has not found a ferrite that meets our High μ need Delaying new tuners  Booster High Intensity/rep rate: MI starts up soon and will be first real test Supplemental Funding – Big Boost and will help PIP/FY14 William Pellico, Fermilab PMG, Aug