Proton Improvement Plan (FY13 PMG Q3)
William Pellico, Fermilab PMG, Aug PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary Outstanding Issues Plans - Schedule FY13 Budget Updates FY13 Goals/Issues - Next Quarter Additional PIP Items
William Pellico, Fermilab PMG, Aug LossesFluxViability Shielding Improvements New Tuners Linac HP RF Dampers Cogging BPM systems RFQ Injector Booster Anode Supplies Collimation System LCW systems Transformers Beam Physics/Optics Booster Cavity Refurbishment Linac Notch Booster Solid State Linac Modulators Booster Notcher/Absorber PIP – Path to Higher Proton Throughput and Reliability Bias Supplies New Cavities Over 30 Tasks ~87 M $$ ~ 7 years of work
William Pellico, Fermilab PMG, Aug FY13 Q3 Task Summary – Highlights
PIP FY13 Milestone Summary William Pellico, Fermilab PMG, Aug The current RLS is out of date and is being updated. Effort to adjust RLS when changes to budget and labor occur is challenging. Not Completed Completed FY13 Q1 FY13 Q2 FY13 Q3
WBS 1.1 LINAC FY13 Q3 Summary Tasks at a Glance 6 William Pellico, Fermilab PMG, Aug Linac WBS TaskFY13 Q3 Progress Summary WBS High Level RF CPI reviewing costing and CPFF agreement as required by DOE WBS Linac Modulator Completed 2 stage test – Working on 3 cell configuration WBS Procurement Receipt of a new tube in July WBS Simulations and Studies Created an input file of DTLs, Manual written, TRACEWIN model WBS Linac Notch Creation Progress in beam shaping optics, 3D model of vacuum assembly WBS Power Distribution Hatch install approved (installed in Aug) WBS Vacuum System Valves for 400 MeV delivered (installed in Aug)
7 William Pellico, Fermilab PMG, Aug WBS 1.1 LINAC (Highlights) WBS Modulators WBS Linac Notch Creation WBS Power Distribution Hatch Install Modulator 3 Cell Testing Linac Notch Creation Detailed study DTL region Lattice in TraceWin 3D Print of laser cavity
8 William Pellico, Fermilab PMG, Aug WBS 1.2 Booster FY13 Q3 Summary Tasks at a Glance WBSTaskHighlight Cavity Refurbishment7 th cavity refurbished and certified (June 24 th ) New TunersDelivery of new low mu cores – pass high power test Delivery of new high mu cores – pass high power test Both mu’s have lower values; working with vendor Simulations & StudiesNew person working on optics Alignment & ApertureGradient magnet moves and alignment Notcher SystemOperational – working on short kickers/PS Radiation ShieldingAnalyses of radiation studies data; working with ES&H on proposal for shielding assessment addendum
William Pellico, Fermilab PMG, Aug WBS 1.2 Booster (Highlights) Notcher System Cavity Refurbishment Buildup of High Voltage Rack for Short Kickers Cavity preparing to repair flanges Cones and new cooling loops Labor intensive work
Saga of new ferrites for cavity tuners William Pellico, Fermilab PMG, Aug Testing Ferrite Core Low Power High Power Issues: Old Vendors Gone New vendors having difficulty making similar ferrites…. Looking for high Q, low loss and two values of mu ~(12, 20) TD ready to build tuners once we have ferrites
William Pellico, Fermilab PMG, Aug
WBS Accelerator Physics (Booster) WBS Alignment & Aperture Magnet moves Scans Location Long 16 Vertical Move This was the fourth area where we moved magnets…. More to come William Pellico, Fermilab PMG, Aug Tunnel Location mm
William Pellico, Fermilab PMG, Aug Budget and Labor Review Summary
William Pellico, Fermilab PMG, Aug FY13 To-date FTEs by OHAP – Fcst vs Act
FY13 To-date FTEs by Div – Fcst vs Act 15 William Pellico, Fermilab PMG, Aug
16 PIP Labor Usage (FTE) Planned Actual
William Pellico, Fermilab PMG, Aug M&S Task Totals 1.00 Program Management$187, Linac High Level RF$2,212, Linac Modulator$125, Linac Notch Creation$23, Linac Power Distribution$13, Cavity & Tuner Refurbishment$153, New Tuners$524, Booster Simulations & Studies$10, Booster Notcher$92, Booster Dampers$2, LCW$48, Power Distribution$25, Solid State Upgrade$580,264 Total M&S$3,998,025 PIP M&S BUDGETYTD OBS06/13 RIP BUDGET BALANCE w RIP'sYTD COST OCT-12 OBS NOV-12 OBS DEC-12 OBS JAN-13 OBS FEB-13 OBS MAR-13 OBS APR-13 OBS MAY-13 OBS JUN-13 OBS JUL-13 OBS Total All Labor & M&S K$ April - Correction for Solid State Task Closure 82% of FY13 Allocated
Supplemental Spending William Pellico, Fermilab PMG, Aug ID PIP Tasks Task Code 1 DTI switches and controller for extractor (and spare for Einzel Chopper) AD 2 Booster Transformer (MCC and spare breaker) AD 3 Buncher Solid State RF power AD 4 12 Scroll Pumps for Booster AD 5 Linac Roughing Station AD 6 Laser Amp for Linac Notcher AD 7 1 st Linac RFQ Turbo and Roughing station/controls AD MeV line pumps AD 10 2 nd Linac Booster roughing and turbo pumps stations AD 12 Replace 5 Booster valves AD 13 Linac Modulator (SLAC Version) AD 14 SS amp for Linac Driver system AD 15 Booster Anode Supply Transformers AD 16 Laser notch pulser AD MHz Circulator AD 18 Linac 55 chilled water pump and plumbing AD 19 3 rd Linac AD 20 Injector Solenoid and trim PS RF test ‘cave’ or shielded room AD Additional funds were provided in July – Although part of Q4 – This is a significant $$ and will have a positive effect on the schedule. Part of funds will be used to remedy the recent PS budgets which impacted PIP goals (7835 tubes). Part of funds will be used to put back track PIP items impacted from previous reductions (e.g. laser notcher). Part of funds will be used to move tasks forward (Refurb)
Plans - Schedule
William Pellico, Fermilab PMG, Aug Proton Source/PIP – FY13 Calendar Goals (PIP & PS) On Schedule Booster MI Startup Beam Dump/High Intensity Tuning Q2 OLD Tune-up Booster SS RF System Magnet Moves Alignment Refurbishment Optics/Harmonics Studies While waiting for users PIP continues to take advantage of Proton Source only operations :
Proton Improvement Plan Projection NOvA Shutdown g-2 Mu2e 8 GeV 120 GeV LBNE William Pellico, Fermilab PMG, Aug MiniBooNE Maybe
Additional PIP Items
Cooperation on Linac Power Amplifiers Brookhaven Linac is very similar design to Fermilab Low- Energy Linac Not interested at this point in any financial arrangement SLAC SOW to provide expertise and local oversight for the klystron prototyping LANL has sent information on their pursuit of a 200 MHz klystron (CPI). Interested but still pursuing Thales tube. William Pellico, Fermilab PMG, Aug
Nigel Tour of MI-60 / Cavity Refurbishment Work Nigel visit to MI-60 to try and understand why it is taking so long to refurbish cavities. Reassures us that once he is in charge – things will change. William Pellico, Fermilab PMG, Aug
PIP FY13 Q3 Summary & Concerns WBS 1.1 Linac Linac WBS efforts are in good shape Klystron effort continues – Business Services/CPI/PIP Modulator efforts continue with both SLAC and AD/EE support Simulation and Studies-> continue development code for DTL lattice, WBS 1.2 Booster Cavity Refurbishment – Labor & Time constraints Contract Employees Dosage (ALARA) – will need to rotate personnel Need to deal with operations vs. repair (MI startup) Booster shielding – progressing Booster Rep rate limit – still unresolved and require testing Booster has not found a ferrite that meets our High μ need Delaying new tuners Booster High Intensity/rep rate: MI starts up soon and will be first real test Supplemental Funding – Big Boost and will help PIP/FY14 William Pellico, Fermilab PMG, Aug