- LESS CONST. BUDGET - PREMIUM QUALITY - SHORT CONST. PERIOD - RELIABLE SAFETY - NO CRANE REQUIRED - LIGHT & EASY INSTALL Clear AccessManual Transfer Simple Erection HYUNDAI FEATURES Make to order for each project High Quality Finishing
“High Efficiency Slab System” “Three Main Components Only” “No throwing of Formwork” AluminiumFormwork SLAB “50% Less Labours”
: Install Wall Reinforcement : Erect Wall Panels : Erect Deck Panels : Install Slab Reinforcement 5-8 days Per Floor SYSTEMATIC: 5-8 days Cycle : Pour Concrete Zone Casting Everyday HYUNDAI FORM Day 1Day 2Day 3 Day 4Day 5
AluminiumFormwork Everything cast together - wall - column - beam - staircase - liftcore
AluminiumFormwork Light weight Panel No need tower crane Lightweight panel, easily handle by Workers
AluminiumFormwork Quick & Easy to shift
Hyundai AluminiumFormwork Fast & Easier of installation & dismantle
AluminiumFormwork Short training time
AluminiumFormwork Reuse up to 200 times !
AluminiumFormwork Less wastage & damage Lesser hidden cost
AluminiumFormwork Lesser and cheaper Labour System formwork labour: Rm13.00 / m2 Conventional labour: Rm18.00 / m2
AluminiumFormwork Strip early Wall 10 hours, Slab 2 days Formwork 1 level Props 2 levels
AluminiumFormwork No need do any Plastering Reduces Cost of Architectural Touch up
ALUMINIUM VS Conventional (Conventional slow by 4-5 months) TIME = MONEY !!! 1)Bank interest 2)Operation expenses (tower cranes, labour and others) 3)Worker 4)Rubbish expenses