ME4182 Progress Report Team: Future Crew Technologies Chris Biggers Simon Cole Chuck Devane Ray Cortes Victor Renteria Tejuan Rowe Professor: Dr. Lipkin Date: September 5, 2001
Agenda zProblem Statement zDesign Partition zProject Plan zTask Assignments
Problem Statement éDesign a new fuel tank for the test vehicle (2002 Ford Explorer) éDesign casing for battery, electronics, and controller éSafety test new fuel tank éPerform engineering analysis on the battery casing éConsider impact of the additional weight on vehicle performance éInstall newly designed components on test vehicle
Design Partition m “Take Apart the Truck” Remove spare tire Remove gas tank / fuel lines Dismantle exhaust system
Design Partition (cont.) m Design the new parts Gas tank configuration Battery box configuration Reroute fuel lines Determine fuel pump size / flow rate m Material Design Select battery box material / fasteners Select gas tank material / fasteners
Project Plan m Each member was assigned specific tasks m Each task has its own due date m The team will critique the individual work in progress to then integrate into overall design m Order and manufacture necessary parts m Assemble the new parts into the truck
Task Assignments ã Conceptual Designs - Group ã Patent/Product Search - Chris Biggers ã Selection Analysis (HOQ) - Chuck Devane ã Design Partition (Function Tree) - Victor Renteria ã Presentations - Group ã Layout Drawings - Simon Cole ã Engineering Analysis - Ray Cortes
Task Assignments (cont.) ã Part Drawings - TeJuan Rowe ã Prototype Building - Chris, Chuck, Ray ã Prototype Testing - Simon, TeJuan, Victor ã Posterboard Display - Chris, Chuck ã Final Paper - Group ã Website - SimonCole