TC meeting 25.10.2013. LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove.

Slides:



Advertisements
Similar presentations
TC meeting /11/14TC meeting2 ALICE LS1 plan from now till MarchWeeks Install TRD infrastructure46 TRD4&5 (and counterweights removal)47.
Advertisements

LS1 planning meeting Activities weeks 13, 14 & 15 22/3/13LS1 planning meeting - A.Tauro2.
LHCb Upgrade Optical Fibers from Cavern to the Surface - what has been done ? - prototypes status and next coming steps - what is missing for final installation.
June 2004 Andrea Gaddi, PH-CMI USC Installation Commissioning Task Force 1st Run Meeting, June 3rd, 2004.
SR1 ongoing workH.Pernegger21/2/02 Ongoing work in SR1 and preparations for detector macro assembly Heinz Pernegger.
ALICE planning meeting /12/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 7&8 A.Tauro
Notes After TIG 17/7/08 HF+ Move out of garage: Aug 15* Platform+table+collars+racks+BP support (jack up for platform) = 3 days Controls for motors = 1.
1 5 December 2012 Laurent Roy Infrastructure / Electronics Upgrade -Cabling (long distance) -Rack and Crate (space, electrical distribution, cooling) -Detector.
winter shutdown preparatory meeting A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
winter shutdown planning A.Tauro
Installation and Commissioning Planning Leslie Camilleri Calorimeter Commissioning Meeting 5 th September 2006.
LS1 reference slides LS1 plans Detector’s plans Services and central systems availability 8/2/13LS1 planning meeting - A.Tauro1.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. 1 st June: PT100 electrical connection failure (Temp Chiller water In&Out) 1) it required an access to the cavern to be fixed 2) access.
LS1 planning meeting Comments on LS1 schedule Schedule reviewed last week with Yann + TC…  sequence after OD looked too squeezed  therefore.
ALICE Collaboration Meeting Heidelberg Services Update  Progress on services Detector cabling Gas systems Cooling systems  Rack footprint  Primary electrical.
SU ACTIVITIES PENDANT LS1 CMS ALICE. Antje Behrens | SU pendant LS1 day| | EDMS | page 2 CMS Quoi (quelles activités prévues pendant.
P2 status, LS1 planning A.Tauro - W.Riegler. Outline TS2 activities Detector activities during LS1 Proposal for ALICE recommissionig plan in 2014 Conclusions.
TS4 preparatory meeting TS4 – weeks Underground access possible in week 51 – as from Monday morning 9:30 –Ulli and Philippe will start.
winter shutdown preparatory meeting A.Tauro /12/11ALICE winter shutdown schedule - A.Tauro 1.
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
Injectors & LHC report K. Foraz on behalf of OSS members 14/06/2013LSC - K. Foraz1.
ALICE 5 o’clock meeting Wk 51. INDICO You’ll find this meeting here: – The full shutdown planning.
Claudio Bortolin. Drilling: – tungsten carbide tip welded on twisted ss cable – drill to operate the rotation – counter-flow at 200 mbar w/manometer to.
EN-CV interventions during YETS
ALICE TC meeting – Plans for the next technical stop A. Tauro.
TS planning meeting 7 to 11 Nov Technical stop Wk 45: Monday 7 th to Friday 11 th November Ramp down magnets (SL): Mon 8:00 – 8:30 (latest) RP search.
winter shutdown planning A.Tauro
winter shutdown planning A.Tauro
Activities related to Experiments during TS3 and YETS th November, 2015 M. Bernardini, M. Barberan With the support of S. Chemli and Experiments.
TS May 9-12 – Schedule SL instructions: Both magnets ramped down Monday May 9 th 7:00 latest Thursday: check with CCC before restarting magnets: – TE-EPC.
LS1 planning meeting /4/13 ALICE TBStatus of LS1 activities - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare.
ALICE planning meeting /2/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
TC meeting P2 planning wks 9&10 A.Tauro
ALICE Arturo Tauro Werner Riegler.
IBL CO 2 cooling planning 03 July 2013 Jan Godlewski, Bart Verlaat, Lukasz Zwalinski 1
André Augustinus Infrastructure  Turbines  Radmon  Thermocouple readout  Netgear redundancy  Other cavern items  Cooling CRs  Other CR and surface.
Michel RAYMOND – July 1 st, 2013 Technical Support Activities in PH-ADO-PO Summary of 2013 activities.
ALICE 5 o’clock meeting Wk 49. INDICO You’ll find this meeting here: – The full shutdown planning.
winter shutdown planning A.Tauro /1/12ALICE winter shutdown schedule - A.Tauro 1.
TC meeting P2 planning wks 5&6 A.Tauro
TS2 preparatory meeting A.Tauro. General information LHC- TS2: from Monday 31st 6am, to Friday 4th 5pm LHC beam stops on Monday morning.
LS1 planning meeting /7/13LS1 planning meeting - A.Tauro2 LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS.
1 Planning DCS WS L.Jirdén. 2 TPC HMPID ACORDE FE PC Console DSS Disk SRV DB-SRV App GW sensors actuators DSS sensors actuators PC room SXL2.
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 30/08/2013LSC - S. Baird, M. Bernardini1.
TS3 preparatory meeting 14/9/2012 TS3: 17-21/
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 20/09/2013LSC - EN-MEF-OSS1.
ALICE 5 o’clock meeting Wk INDICO You’ll find this meeting here: – The full shutdown planning.
LHCb Week 27/11-01/ D.LACARRERE on behalf of Expt Area Team1 Experimental Area Latest News from IP8  Radiation Shield – Upper & Front Parts  Structures.
TS3 preparatory meeting A.Tauro. General information LHC-TS3: from Mon 9 6am, to Fri 13 5pm LHC beam stops on Mon morning at 6:00.
TC meeting P2 planning wks 3&4 A.Tauro
ALICE planning meeting /11/10 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
ALICE planning meeting /1/11 ALICE planning meeting2 Outline ALICE Christmas break schedule –Access UX25, L3 and MNF Services interruption.
DCal-ALICE integration and installation plan and status A. Tauro.
ALICE Installation: Planning Meeting Agenda: 1- ALICE shutdown schedule 2- Miniframe removal sequence.
ALICE 5 o’clock meeting Wk 50. INDICO You’ll find this meeting here: – The full shutdown planning.
EYETS planning A.Tauro.
ALICE 5 o’clock meeting Wk 51.
TS2 preparatory meeting
LS1 planning meeting - A.Tauro
LS1 planning meeting
CMS Area Working Group Meeting
ALICE 5 o’clock meeting Wk
TS1 preparatory meeting
Shutdown conclusion, LS1 and LS2 planning - A.Tauro
LHCb & EYETS
ALICE 5 o’clock meeting Wk
K. Foraz on behalf of OSS members
Presentation transcript:

TC meeting

LS1 plan 2013Weeks Remove plug, mobile shielding, open doors8-9 Prepare for PHOS extraction, remove RB24 beampipe and PMD10 Remove PHOS cradle and modules, transfer TOF crates on SF11-13 Modify L3 services and install YP for TRD1714 Modify L3 services, remove TRD17 and rework LV distr. TRD , DCal tests in SXL Modify L3 services, open low-beta and swap Q5L8 magnet, DCal tests in SXL2, new UPSes20-23 Swap PHOS beams with DCal beams25-26 Install DCal support structure and rails27-30 DCal and PHOS services + complete support structure and rails31-37 Open Days – 28-29/ Install C-side DCal supermodules42-45 Rework LV distr. TRD TOF electronics repair49-51 Xmas pause52-1 Done 2 3/11/13TC meeting - A.Tauro Done

3/11/13 Detailed plan till end of the yearWeeks Open low-beta and install scaffolding, Test anti collision system (Fri PM)38 DCal rails (Manoel&Co), weld fences above L3 (Mon-Tue), OD preparations - OD39 Remove scaffolding (start Mon), remove OD tables, remove SU2 portable chiller, PHOS and DCal cooling pipes, remove TDI (Wed), start closing low-beta 40 Close low-beta, remove ACR tables41 Install 2 1/3 DCal supermodules, modify DCal infrastructure42 Install DCal 40 and 20deg (C-side), DCal and PHOS fibers43 Bring YP to SX2, install DCal 0deg (C-side), remove DCal infrastructure44 Bottom TRD counterweights (SR14, Mon-Tue), install “cheval” I-side (Thu AM), install YP rails O-side (Thu PM), install YP (Fri), bring TRD + rotator into SX2, install TRD racks (low-beta), T0 electronics relocation, welding HLS (Mon-Tue) 45 Remove TRD from rotator in SX2 and bring TRD into cleanroom (Mon), rework LV distr. TRD11, cables (SPIE), SSD rack intervention 46 Rework LV distr. TRD15, drill SPD filter SR8 (Mon), MTG search gas leaks, T0-V0 optical fibers, gas pipes (RENCO), cables (SPIE), EMCal and DCal SRU mounting modifications (Tue-Thu), reinstall T0-A (Wed) 47 Rework LV distr. TRD16 and install TOF rails, gas pipes (RENCO), cables (SPIE), EL-CO: test UPS control (Thu), unload DAQ equipment (Wed), gas pipes SG2-SD2 and SD2 (tbc) 48 TOF electronics repair, gas pipes (RENCO), cables (SPIE), remove HMPID pumping station49 TOF electronics repair, gas pipes (RENCO), cables (SPIE), scaffolding PX24 (CV corner)50 TOF electronics repair, move PX24 beam, delivery scaffolding PX24 (Wed)51 TC meeting - A.Tauro3 October November Dec

4 LS1 plan 2014Weeks PX24 scaffolding (w2-3 and w7-8) and new L3 ventilation ducts (w2-6)2-8 Extend SAA3 shielding9-15 Install top TRD counterweights16-17 Remove comp. magnet and Suspend Miniframe18-20 Install TRD with yellow platform (bottom), remove bottom counterweights21-25 ‘Un-suspend’ Miniframe, reinstall ZDCs26-27 Reinstall TRD1728 Concrete walls & TRD installation frame29-30 Install TRD4-5 (top) & counterweights31-32 Remove TRD infrastructure33-35 Reinstall and survey comp. magnet36 Reinstall and bakeout RB24 beampipe37-38 Reinstall PMD, ZEM and BCM and BLM39 Install 4 PHOS + 1CPV + 3 DCal (A-side) supermodules40-45 Close plug, L3 doors, reinstall shieldings /11/13TC meeting - A.Tauro 5 weeks TRD installation window enlarged to accommodate for SM production schedule

3/11/13 Detailed planWeeks PX24 scaffolding, L3 ventilation ducts, gas pipes (RENCO)2 PX24 scaffolding, L3 ventilation ducts, drill SPD filter SR8 (and 0, tbc), gas pipes (RENCO), T0 air cooling modification 3 L3 ventilation ducts (mobile crane Wed-Fri), gas pipes (RENCO)4 L3 ventilation ducts, gas pipes (RENCO)5 L3 ventilation ducts (mobile crane Mon-Wed), gas pipes (RENCO)6 PX24 scaffolding, gas pipes (RENCO)7 PX24 scaffolding (contingency), annual flammable gas detection maintenance (Wed-Fri) TC meeting - A.Tauro5 January February March April

Planning L3 ventilation ARCADE starts w2 (Mon 6.1) Ouvaroff starts w2 (Tue 7.1)  scaffolding pre- assembled in SX2 and installed in 2-3 days Mobile crane in SX2: – Wed 22.1 to Fri 24.1 (removal existing pipes) – Mon 3.2 to Wed 5.2 (installation new pipes) Work finished w6 Scaffolding removed w7-8 3/11/13TC meeting - A.Tauro6

3/11/13TC meeting - A.Tauro7

RENCO Spare pipes (SG2 to CR5)  will be finished before Xmas – w49-51: installation inside SD2 – w50 (Thu 12.12): installation pipes in SG-SD trench UX25 (MTG, TOF, PHOS)  January Test and end-chantier first two weeks February 3/11/13TC meeting - A.Tauro8

3/11/13TC meeting - A.Tauro9 ACR planning

ACR: drainage problem Intervention to isolate pipe scheduled from – Nacelle inside SX2 3/11/13TC meeting - A.Tauro10

Cabling & fibers campaigns Cabling: – 1 st cabling campaign (July-August) DCal, CO2, TOF – 2 nd cabling campaign (November-December)  ongoing T0, V0, AD, TRD, BCM, BLS, DCS, EN/CV/DC – 3 rd cabling campaign early next year CPV, PHOS, … Fibers: – 1 st fiber campaign (October) PHOS, EMCal and DCal – 2 nd fiber campaign (November) T0 and V0 – 3 rd fiber campaign (January-February 2014) Check all DAQ links from CR1 – Common order for patch cords sent out (estimated Delivery date ) T0, V0, AD, CPV, PHOS, TRD, DCal, EMCal and BCM 14/11/13LS1 progress - A.Tauro11 Please send us asap any request of cables to be installed

Services interruptions in 2014 EN-EL: – general maintenance 400V and 18kV switchboards – test AUG EN-CV: – maintenance cooling towers (SF2) – chilled water upgrade (phase II)  new chiller + commissioning – replacement UW pumps – maintenance detector cooling plants and relocation of PLCs Gas: – Gas Control Systems (GCS) migration from UNICO CPC5 to CPC6  each gas system stopped for 1-2 weeks for test 14/11/13LS1 progress - A.Tauro12 1 week blackout  no access to P2

14/11/13LS1 progress - A.Tauro13

Issues - 3/11/13TC meeting - A.Tauro14

EOY activities GS-ASE: test evacuation P2 Thu 26 December 3/11/13TC meeting - A.Tauro15