Summary Session Infrastructure and Operation P.Collier & Ph. Lebrun.

Slides:



Advertisements
Similar presentations
André Augustinus 16 June 2003 DCS Workshop Safety.
Advertisements

H. MAINAUD DURAND, A. HERTY, A. MARIN, M. ACAR PERMANENT MONITORING OF THE LHC LOW BETA TRIPLETS: LATEST RESULTS AND PERSPECTIVES.
SAFETY FOLLOW-UP HL-LHC PROJECT WP17 – Infrastructures meeting S. La Mendola, Jose Gascon DGS/SEE 09 July 2015.
HSE Preliminary General Requirements for FCC layout and air management A. Henriques & M. Widorski on behalf of the HSE Unit 17/12/2014 FCC I&O Meeting.
Machine Detector Interface for the HL (MDI) CERN, April 15, 2011 Austin Ball, Helmut Burkhardt, Marzio Nessi.
Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.
Global Design Effort 1 Conventional Facilities and Siting Overview A. Enomoto, J-L. Baldy, V. Kuchler GDE.
Global Design Effort - CFS for Asian Single Tunnel Configuration Design Progress Masanobu Miyahara KEK.
CLIC CES Webex 12 Nov Summary: – Set of fire safety measures defined in CERN Safety Report – Proposed Structure for CLIC/ILC Fire Safety Report Fabio.
Geotechnical & Civil Engineering Studies Future Circular Colliders (FCC)
The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded by the European Commission within the Framework Programme 7 Capacities Specific Programme,
FCC Week 2015 Program of I&O presentations Ph. Lebrun 25 February 2015.
FCC Tunnel Civil Engineering and Geology John Osborne (CERN GS-SE) 4 April 2014.
WP2 Superbeam Work Breakdown Structure Version 2 Chris Densham (after Marco Zito version 1 )
Global Design Effort - CFS TILC09 and GDE AAP Review Meeting - Tsukuba, Japan 1 GDE ACCELERATOR ADVISORY PANEL REVIEW CONVENTIONAL FACILITIES.
1 CLIC / ILC Collaboration for CES issues JOHN OSBORNE – CES 8 April 2009.
CLIC Implementation Studies Ph. Lebrun & J. Osborne CERN CLIC Collaboration Meeting addressing the Work Packages CERN, 3-4 November 2011.
John Osborne : GS-SEM Civil Engineering 19 May 2009 Report on behalf of CLIC Civil Engineering and Services (CES) WG CTC 19 May 2009 Tunnel Cross Section.
ST/MAforLHC April 2003Sixth ST workshop1 Summary of ST/MA deliverables for LHC Luigi Scibile for the ST/MA group.
10/2010 IWLC2010 Global Design Effort 1 Brief Overview of Interaction Region Conventional Facilities in RDR Times Presenter Tom Lackowski.
The fourth Baseline Technical Review (BTR) - Conventional Facilities and Siting March 2012 All changes made to the CFS 2007 Reference Design during.
Transport of the CLIC Modules and Elements CLIC Workshop October 2007 Two Beam Hardware and Integration Working Group Keith Kershaw (CERN)
1 Target Station Design for Neutrino Superbeams Dan Wilcox High Power Targets Group, Rutherford Appleton Laboratory NBI 2012, CERN.
Beam loads & dump concepts T. Kramer, B. Goddard, M. Benedikt, Hel. Vincke.
Radiation Protection aspects for SHIP Doris Forkel-Wirth, Stefan Roesler, Helmut Vincke, Heinz Vincke CERN Radiation Protection Group 1 st SHIP workshop,
An introduction to Energy aspects at CERN June 2014.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Experimental Areas Studies Lessons learnt at CMS M Gastal & CMS Technical Coordination (A Ball, W Zeuner)
LIU external beam dump review External beam dump option A: branching off from LSS6 J.L. Abelleira Thanks to: F. Velotti, B. Goddard, M. Meddahi, H. Vincke,
3/20/11 ALCPG11 Global Design Effort 1 CFS Detector Hall Considerations Tom Lackowski.
ILC D RAFT P ROJECT S CHEDULE K LYCLUSTER 500GeV K Foraz & M Gastal ILC Mechanical & Electrical Review and CFS Baseline Technical Review Many thanks to.
Extraction and beamline progress B.Goddard TE/ABT.
Cryostat & LHC Tunnel Slava Yakovlev on behalf of the FNAL team: Nikolay Solyak, Tom Peterson, Ivan Gonin, and Timergali Khabibouline The 6 th LHC-CC webex.
The first question is really "Why do you need a control system at all?” Consider the following: What good is an airplane if you are a pilot and you.
Upgrade PO M. Tyndel, MIWG Review plans p1 Nov 1 st, CERN Module integration Review – Decision process  Information will be gathered for each concept.
The integration of 420 m detectors into the LHC
Review of FCC tunnel footprint & implementation Introduction & scope Philippe Lebrun Review of FCC tunnel footprint & implementation CERN, 11 June 2015.
MEF - Machines & Experimental Facilities March 2013 Project meeting Activities in Linac4 tunnel and building in 2013 March 2013 Project meeting 14/03/2013J.Coupard1.
Proton-Driven Plasma Wakefield Acceleration CERN Project Structure Edda Gschwendtner, CERN Lisbon Meeting, 22 June 2012Edda Gschwendtner, CERN2.
Cryogenic Cooling Schemes for the SPL U. Wagner TE-CRG.
Outcome of the FCC Week 2015 Input for work program in the second year of the study Ph. Lebrun FCC Infrastructure & Operation Meeting 22 April 2015.
FCC Infrastructure & Operation studies: outcome of the kick-off meeting and work program Ph. Lebrun & P. Collier 2 nd FCC Infrastructure & Operation meeting.
SPS movable table Joanna Swieszek, Kurt Artoos (EN-MME) 14/04/2016.
Design considerations for the FCC electrical network architecture FCC week 2016, Rome, April 2016 Davide Bozzini - CERN/EN/EL With the contribution.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
COOLING & VENTILATION PLANTS M. Nonis – CERN EN Department / CV Group Annual Meeting of the FCC study – Rome 14 th April 2016.
SuperB Integration SuperB Experimental hall. Related topics of Slac D&D activities.
Workshop summary Outline  Workshop’s aims  Highlights from the presentations (my selection!)  Costing Exercise – What we learnt  Summary - Roadmap.
SuperB Experimental hall General considerations on the Babar experimental area Preliminary space requirements hall proposal. A floor plan. Specification.
E- source kick-off meeting e- Source RDR- Conventional Facility & Siting Overview Fred Asiri/SLAC.
H. Hayano(KEK), B. Petersen(DESY), T. Peterson(FNAL),
Experimental Hall in Mountain Regions
FCC Underground Infrastructure
Civil Engineering for FCC-eh and LHeC
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
CLIC Civil Engineering Update
Conventional Facility & Siting (CF&S) Overview for the Positron Source
1st FCC Infrastructure & Operation meeting
CLIC Civil Engineering & Infrastructure
Acknowledgements to all FCC study teams
Innovative He cycle Francois Millet.
Tunnel Cross Section Studies
CLIC / ILC Collaboration for CFS works
FCC Civil Engineering update
Accelerator and Experiment Interface Session: LS2, LS3
Joint Meeting SPS Upgrade Study Group and SPS Task Force
COOLING & VENTILATION INFRASTRUCTURE
CLIC Civil Engineering Update
RDR Baseline Layouts for Interaction Region
FCC Week 2019 Civil Engineering Summary
Presentation transcript:

Summary Session Infrastructure and Operation P.Collier & Ph. Lebrun

Participation Quite a lively session 31 participants (8 from outside CERN) No structured set of presentations  Presented the proposed WBS  Presentation on the Geological study Went round the table to discuss the individual infrastructure systems and concepts to see the next steps  CE  Cooling/Ventilation  Survey  Cryogenics  Operation – Reliability  Safety –RP aspects  Safety systems  Cabling and electrical distribution

Civil Engineering – next steps ARUP presented their workplan: Stage 1: Development of geological model and GIS alignment decision aid tool Stage 2: Identification of key alignment layout optimisation requirements and constructability Stage 3: Refinement of above stages and establish concept for Pre-Feasibility Stage Stage 1: Feb 2014  June 2014 Stage 2: July 2014  Dec 2014 Stage 3: Jan 2015  May 2015

CE Discussion: Stage 1 is quite general – basic geology of the region Mentioned that other specific studies exist.  Several ideas – invited to contact John with possible links As we enter stage 2 there needs to be a limited number of options to study in more depth:  A requirements document is needed by early summer setting out the parameters of the (limited number of) options to study.  This could include constraints/requirements on:  the number of tunnels  Surface points/shafts  footprint/form of the machine  Inclination and planarity Preparation of such a document is the responsibility of the I&O coordination group  The timescale is rather short!!  Take into account all aspects including spoil at the relevant level of detail. Nothing is cast in concrete at this point – but we cannot study everything!!

Cooling & Ventilation General consensus concerning Ventilation  The maximum heat load should be taken by water cooling  The ventilation system should rather be determined by legislative requirements for access and safety  The length of sectors is important – but CV can actually help define or constrain this.  The use of multiple tunnels as mechanisms for ventilation needs to be elaborated.  Intermediate shafts – just big enough for CV and emergency access should be considered Water Cooling:  Cooling towers will most likely be required, but these are not so easy to sell to the general population  Possibilities for waste heat recovery – for the CERN surface installations?  Synchronization between production and need!!  Dumping heat into the tunnel surroundings? (CE models exist)  Use of Lake water discussed for part of the machine – but would this work if different temperatures were delivered to different parts of the machine?

Survey We need to extend the present CERN co-ordinate system!  Link the CERN system to the Swiss and French systems  Accuracy and quality of the data is different.  Minor inaccuracies here can have a major impact on the scale of FCC.  Number of access points is an important factor for the accuracy of the alignment! What are the constraints on the machine being at a specific inclination? What are the constraints on the machine being in a plane?? Alignment accuracy in the experiments  FCC-ee seems an extreme case with the mm beta*  Alignment of the machine to the detector – taking into account earth movements during and after excavation! FCC-ee seems to be the driver here!

Cryogenics A lot of basic scaling work has been done! Major areas of study:  Pushing the state of the art cryo-plant (presently ~25kW) versus the complexity of multiple plants.  Separate Cryo feedline?  Minimizing the He Inventory in conjunction with the magnet(RF) designers Location:  Nominally the 4.5K cryoplants would be on the surface and the 1.9K plants in the tunnel  But hydrostatic pressure is an important consideration here and the depth of the tunnel might be problematic  Discussion if we should consider underground intermediate caverns for infrastructure  Lower visibility on the surface  Still accessible during operation  Simplify hydrostatic pressure constraints.

Reliability General discussion on reliability of components, sub-systems, systems and the accelerator as a whole Consensus that this will be key to making the machine(s) work WBS contains WU on accelerator simulation that could help developing early fault detection and fault prevention scenarios. A model would need to be developed and could be fed with data from existing LHC monitoring data. Today we do not have the required analytics infrastructures to work on detecting patterns and correlations. Other labs can contribute to this LHC is the nearest in scale, but is a ‘young’ machine Tevatron attempted this kind of analysis and has a 25-year history of improvements and ‘tweaks’. Every facility has the same problem on different scales Tests, ideas and pilot schemes are directly applicable to operating facilities world-wide “We can study for the future while improving the reliability of our existing facilities”

Transport, handling Experience shows that redundant lifts would make life much easier!! Maintenance during operation also very desirable, Horizontal transport between shafts is a challenge if the distance becomes large Inductive powering systems look promising Monorail technologies are not advised if they are also to be used for the installation of large loads. Can envisage personal transport systems of 20-30km/h underground Should we consider an underground intervention system? Discussion on robotics/remote handling Clearly desirable in ’hot’ areas of the machine Less obvious for the rest. General survey/video remote facilities are clearly interesting everywhere. Design machine and systems with remote/automated intervention in mind from the beginning on

RP Issues Choice of materials is important to minimize activation Electronics gets more radiation sensitive as feature density increases. Possibility to have controllers close to machine, but radiation protected would be desirable Noted that the ee and the hh machines are very different: hh is very clean in the arcs – but not in the experimental SS and in the beam cleaning LSS ee is relatively clean in the LSS, all the main radiation is concentrated in the arcs! Need a simple study of the radiation field in the different cases. This can be refined as we make progress Basically looking at the impact on surrounding materials Input for the decision on the need for a service tunnel … a safety/access tunnel We need this for R2E Safe access Infrastructure installation

Conclusions Lots to do!!!!! External collaborators are keen to be involved! In the next 6 months we need to produce a requirements doc for the CE studies with a limited number of options!!!! Beginning of a consensus around the table that we cannot manage with a single tunnel! Still possibilities of a large split tunnel RP and safety will be the key factors here If the service and safety areas are sufficiently far away they can be accessible during operation of the machine. Reliability is considered as critical Not enough discussion on electrical distribution and surface vs. tunnel distribution of services.  Still, indications that a complete underground distribution of services might be necessary.