Production Planning and Control
APP does not account for the detailed timing of flow within the production system MRP material requirement planning was developed to deal with the complexity of these problems.
Difference between Aggregate production planning and Material requirement planning? Aggregate production planning do not account for the detailed timing of flow with in the production
When a master schedule is proposed, the first problem is to convert it efficiently into the requirements for purchased and manufactured parts. This is referred to performing a parts explosion T o present a formal description of the problem, lets divide item produced into three categories, end items, subassemblies and parts. Notations End items “e” Sub assemblies “s” Parts “p”
Let bill of material for an end product is defined by row vector B i B i =(b i1, b i2,…… b ij) Where b ij is the number of items j required to make directly 1 unit of item i. This is the representation of number of parts in one unit This is the representation of total quantity of parts