Running scenario 2009/10 Run through components – and then synthesis.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

1 Commissioning ABT Equipment in the LHC Jan Uythoven ABT TCM 13/01/2015.
Beam commissioning strategy Global machine checkout Essential 450 GeV commissioning System/beam commissioning Machine protection commissioning.
Monday 4 th to Friday 8 th Technical stop  Coordination: Katy Foraz  Machine back to Operations Friday evening on schedule Major cryogenics intervention.
Injection test? Mike Lamont For initial discussion.
Lot’s of time lost due to cryo problem in IR8. Major impact, therefore review of MD program… Start discussion here, please let us know your input. Will.
Preconditions for operating at 5 TeV in 2010 Session th January 2010 J. Wenninger BE/OP How to safely reach higher energies and intensities? Settings.
LHC progress with beam & plans. Of note since last time Transverse damper Beta beating in the ramp Collimation set-up at 450 GeV & validation LBDS – systematic.
Premature Dumps in 2011 Acknowledgements: A.Macpherson, G.Papotti, M.Zerlauth M.Albert LHC Beam Operation Workshop December 2011.
LHC status & 2009/2010 operations Mike Lamont. Contents Consolidation – brief recall Splices Operational energies Potential performance Present status.
CONTENT: Beam characteristics and parameters Filling schemes Operational settings OP procedure and COLL setting Planning Shift breakdown To define the.
LHC Sector Test1 LHC Sector Test - Beam IntroductionMike LamontIntroductionMike Lamont Proposed tests with beamBrennan GoddardProposed tests with.
Stefano Redaelli Beam Department - Operations Group Operational Aspects of the Phase II Crab Cavity System LHC-CC09 3 rd LHC Crab Cavity Workshop European.
1 Beam Plans for Accelerator Systems: The Machine Protection System Jan Uythoven On behalf of the MPWG and the MPS Commissioning WG Special thanks to R.Schmidt,
Friday to Saturday 02:00: Machine closed. 09:00: Cryogenics all OK. Preparing pre-cycle. 10:00: Pre-cycle started. 11:30: Pre-cycle finished. 14:00: Beam.
LHC progress Report LHCC Wednesday 23 rd March 2011.
R. Assmann - LHCCWG Two Beam Operation R.W. Aßmann LHCCWG Acknowledgements to W. Herr, V. Previtali, A. Butterworth, P. Baudrenghien, J. Uythoven,
RHIC Run14 Time Meeting. Run14 Status – Apr. 15 Operations running well, 12 stores over the past 7 days with 1 lost to another “super quench”. Testing.
RHIC Run14 Time Meeting. Run14 Status – Apr. 22 Operations running well, 12 stores over the past 7 days with 1 “super store” of 17 hours. Repositioned.
Mariusz Sapinski BI/BL Acknowledgements: 1 Planning of quench tests - LMC158 Draft planning of beam induced quench tests at the end of 2013 run LHC Machine.
LHC Progress Friday 30 th October 2015 Coordination Week 44: Massimo Giovannozzi, Wolfgang Hofle, Jorg Wenninger.
Schedule IT General Schedule 9 th, September 09 Today.
LHC Machine Checkout & Dry Runs Strategy Acknowledgements: R.Alemany, R.Giachino M. Albert LHC Beam Operation Workshop June 2014.
Dry runs and cold checkout Markus Albert, Reyes Alemany, Rossano Giachino, Delphine Jacquet, Verena Kain, Belen Salvachua Ferrando, Matteo Solfaroli Camillocci.
1 Commissioning and Early Operation – View from Machine Protection Jan Uythoven (AB/BT) Thanks to the members of the MPWG.
Last night Lhc closed 15:00 Beam on Ti 8 /Ti2 Prepulse check synchronisation ok with LHCb /RF 17:00 Open Point 4 PC’s and RF 19:00 LBDS energy tracking.
1 Machine considerations and constraints for the Safe Injection Flag and Safe Beam Flag Jörg Wenninger AB-OP-SPS Introduction to ‘injection flags’ Machine.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
1 Commissioning and Operation of the machine protection system L. Ponce Acknowledgements: M. Zerlauth, J. Wenninger, D. Wollmann, V. Chetvertkova, G. Valentino,
Injection and protection W.Bartmann, C.Bracco, B.Goddard, V.Kain, M.Meddahi, V.Mertens, A.Nord, J.Uythoven, J.Wenninger, OP, BI, CO, ABP, collimation,
Outline of 2014/2015 plans V. Kain, M. Lamont, J. Wenninger 6/18/2013Optics Measurement and Correction Review
06:00 – Ongoing injection problems on beam 2  07:42 – Start of injection investigations  11:11 – Injection problem fixed. Resteering of transfer line.
Saturday 11.9 ● From Friday – Minimum required crossing angle is 100  rad in 2010 – Plenty of aperture at triplets: > 13  (n1 > 10) – Can stay with 170.
CONTENT: Beam characteristics and MP concerns BI configuration Operational settings Collimators Planning Shift breakdown Thanks to: P.Baudrenghien, G.Bellodi,
Cryo back at 17:30 Beam back at 19:00 IR2 aperture until ~03:00 Since then no beam from the SPS:  Connector problem on MKD  Connector eroded, needs to.
Progress with Beam Report to LMC, Machine Coordination W10: Mike Lamont – Ralph Assmann Thanks to other machine coordinators, EIC’s, operators,
Commissioning Strategy - Chamonix LHC Commissioning with Beam Overall Strategy Mike Lamont AB-OP 17 th January 2005 Chamonix XIV B.D.S.
Tue 23/8 – Wed 24/8 09:00 Start 90 m optics run – Preparation and verification of the collimation functions – Re-generation of functions for Transverse.
Ralph Assmann, Giulia Papotti, Frank Zimmermann 25 August 2011
DRY RUNS 2015 Status and program of the Dry Runs in 2015
LHC Commissioning with Beam
Wednesday :06 Dump fill 3533: interlock BPMS in IP6
LHC schedule.
The LHC - Status Is COLD Is almost fully commissioned
Summary of week 7 Hardware Commissioning:
Status of the BLHC ….work in progress! Mike Lamont CERN/AB 18/01/2008
Monday 11/07: Recovery Plenty of accesses.
Machine plans - Alignment workshop
Week 46 Week 46: Machine coordinators: Roger Bailey – Gianluigi Arduini Main aims of the week: Stable beams with ions Scheduled stop for ion source refill.
MPSC Procedures An update
LHC Morning Meeting - G. Arduini
Mike Lamont 4th HERA and the LHC workshop 26th May 2008
Beam requirements and operational scenarios in 2010
LHCCWG Meeting R. Alemany, M. Lamont, S. Page
Summary of Week 16 G. Arduini, J. Wenninger
Week 35 – Technical Stop and Restart
MD#2 News & Plan Tue – Wed (19. – 20.6.)
Planning at 5 o’clock meeting Friday
450 GeV Initial Commissioning with Pilot Beam - Beam Instrumentation
Overall commissioning strategy for protons (estd. 2005)
LHC Beam Operations Past, Present and Future
BI cont. *** Summary Matching Monitor test *** We only had ~15minutes of inject and dump, but managed to see a profile with ~9e9 p (!)
Aims for the week Recover from technical stop and precycle at 10A/s
Machine plans - CMS startup workshop
Summary for LPC (March 7th, Ralph Assmann)
LHC Morning Meeting - G. Arduini
Wednesday 23/2 Thanks CRYO!!!.
Another Immortal Fill….
Beam commissioning plans, 2007 and 2008
What systems request a beam dump? And when do we need them?
Presentation transcript:

Running scenario 2009/10 Run through components – and then synthesis

Chamonix Baseline  1 month commissioning  10 month proton physics  1 month Lead Ions  “Short technical stop over Christmas period”  Shutdown – end September 2010  Built in slip potential LHC April 2009 “The CERN Management today confirmed the restart schedule for the Large Hadron Collider resulting from the recommendations from the Chamonix workshop. The new schedule foresees first beams in the LHC at the end of September this year, with collisions following in late October. A short technical stop has also been foreseen over the Christmas period. The LHC will then run through to autumn next year, ensuring that the experiments have adequate data to carry out their first new physics analyses and have results to announce in The new schedule also permits the possible collisions of lead ions in 2010.”

Before full beam commissioning Hardware Commissioning Dry runs  Controls, LBDS, Injection, RF, Collimators etc. etc.  Underway seriously since March Thanks to LHC EICs and operators – days shifts explicitly for this Machine Protection Commissioning  In parallel with HWC Machine Checkout  Sector by Sector as the circuits become available  Global before taking beam LHC April 2009

Beam Tests TI8  6/7 June - successful TI2  Next weekend – 11/12 July TI2/TI8  29/30 August Injection test – beam 1  End W /27 September – in agreement with Alice, possibly ions LHC April 2009

Beam commissioning - what we learnt in 2009? Very rapid progress  multiple system commissioning in parallel (probably too much) Key beam instrumentation in reasonable shape  still much to do but basic functionality is there  only initial measurements made Reasonable magnetic model of the machine Optics and aperture measurements encouraging Key systems only just started  Injection and protection, LDBS, Collimation, RF, Magnets  Machine Protection with beam LHC April 2009

Rapid shake-out of snap-back and ramp with very safe beams Full Machine Protection Commissioning will need a well adjusted & understood machine LHC April 2009

Beam -proposal LHC April 2009 Global Machine Checkout Essential 450 GeV Commissioning System/beam Commissioning Machine Protection Commissioning 4 TeV beam & collisions 450 GeV collisions Ramp commissioning to 1 TeV Full Machine Protection Commissioning Pilot physics System/beam Commissioning

BC plan 1/3 Establish circulating beams (phase A.3 – fast track)  Key instrumentation and measurements Tune, chromaticity, coupling, optics, orbit acquisition and correction  RF capture and adjustment  LDBS – phase 1  Essential machine protection for 450 GeV+ LBDS, BLMs, BIS, experiments  Collisions at 450 GeV  few shifts LHC April 2009 EnergySafeVery Safe 4501 e121 e11 1 TeV2.5 e e10 4 TeV2.4 e10probe

MPS 450 GeV Ring and injection BIS fully commissioned:  All USER_INPUTs operational  BEAM_PERMIT loops operational. Fully commissioned clients (of course only non-beam part):  All injection BIC inputs.  PIC and WIC inputs.  PIC configuration is ‘light’ – all maskable.  Vacuum inputs.  Collimator inputs.  Experiment inputs.  SIS experiments protection.  BTV inputs (also SIS).  BLM inputs.  LBDS – 450 GeV OP. 9 Jorg Wenninger

BC plan 2/3 Ramp to low energy (~1 TeV) with safe beam  appropriate machine protection established  snapback, FiDeL predictions, etc.  RF  Q, Q’, orbit (10 Hz) measurements,  aim for circulating beam at 1 TeV  LDBS > 450 GeV  repeat until 2 Test collision procedure and possibly squeeze mechanics at 1 TeV LHC April 2009

BC plan 3/3 Commission Machine Protection appropriate for low intensity to 4 TeV:  FMCMs, PIC, Collimators, TCDQ, BLMs, BPM interlocks, SMPs, RF frequency, LBDS… Beam and system commissioning - ramp to 4 TeV  beam dump, collimators, BLMs, RF…  Tune, Q’, coupling, orbit… Two Machine protection appropriate for increased intensity and squeeze commissioning. Pilot physics LHC April 2009

Christmas Technical Stop Given need to provide coverage for:  Personnel Safety: Access, Radio Protection, SOs etc.  LHC expert coverage Controls, Beam Instrumentation, ABT, ABP, Survey, RF, Magnet, QPS, Cryogenics, Power converters, collimation, MP3, ELQA, vacuum, RP, access, industrial controls, machine protection  Other: IT, safety, transport  Injectors: operations plus expert coverage  Full LHC OP shift coverage (bearing in mind 2010) Proposal:  Stop LHC with beam ~19 th December 2009  Earliest restart ~ 4 th January 2010  Could possibly use weekends either end -12 days stop LHC April 2009 Would clearly need to define flat-line conditions, required support etc. over the break.

Xmas - delta LHC April 2009 PiquetExpertCCC

Questions Can we do it effectively?  Machine availability compromised by lack of expert coverage? Can we do it safely?  Will nQPS/EE etc be fully debugged etc?  Will the machine protection system be fully commissioned? Status of LHC beam commissioning?  Initial commissioning Requires comprehensive expert coverage across the board. Critically Machine protection system qualification could still be ongoing. Extensive expert presence required.  Pilot physics Foresees low intensity physics running combined with system commissioning with beam, MPS commissioning, squeeze development etc. Expert presence required.  Stable physics running Even with unchallenging betas, intensities… very optimistic LHC - running over Christmas 20th May

Maintenance needs Injectors  Making the assumption that essential maintenance can be performed before, after or in the shadow of LHC technical stops LHC  Number of important issues to be addressed  Careful coordination will be required  However: no extended maintenance period appear to be required by LHC systems during the October 2009 through September 2010 run LHC April 2009

Monthly technical stop Programmed 3 days including recovery and re-closure of ring  QPS plus power converters, controls, R2E etc.  Cool-down will become an issue Mon – Wed allowing weekday time for re-setup with beam Followed by one day set-up with beam and systematic checks of machine protection system Clearly if major breakdowns occur at other times – advantage will be taken. Injector maintenance in parallel is an option [Have not considered scheduling of MD…] LHC April 2009

Injectors 2009 (v3.5) LHC April 2009

LHC 2009 LHC April 2009

LHC 2010 – very draft LHC April 2009

Conclusions 4 stroke commissioning before beam beam tests as last year Staged MPS commissioning and fast track for first low intensity collisions Full MPQ qualification before intensity increase followed by interleaved physics and commissioing. Stop for 2 weeks at Christmas No major injector/LHC driven maintenance required Monthly maintenance periods are foreseen Preliminary schedule for 2009/2010 shown LHC April 2009