BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning.

Slides:



Advertisements
Similar presentations
6 th April 2010 MP3 weekly summary – issues and follow-up 0v1 M. Zerlauth for the MP3-CCC shift crew.
Advertisements

MP3 report – week 17 19/4/2010 – 25/04/ interventions MP3/QPS team in CCC Monday Morning Meeting : 26th of April 2010.
Frédérick BORDRY – LHCMAC 22- 6th December 2007 Review of the experience of LHC powering: short-circuit tests and sector 7-8 and start of powering sector.
1 Powering Tests and Safety Electrical Safety Hugues Thiesen Power Converter Group.
New HV test specification for the LHC N. Catalan for the EI section.
TE-MPE –TM, 16/05/2013, Mateusz Bednarek, TE/MPE-EE ELQA testing during and beyond LS1.
CRYOGENICS AND POWERING
Acknowledgments: O.Aberle – F.Bertinelli – J.C.Billy - O.Capatina - J.Casas - L.Ceccone - S.Claudet J.Coupard - K.Dahlerup - R.Denz - K.Foraz - J.J.Gras.
1 Copper Stabilizer Continuity Measurement Project CSCM Mini Review Powering Implementation H. Thiesen 30 November 2011.
Powering Group of Circuit Doubts and proposals of the procedure reviewing team (Gianluigi, Rob, Sandrine, Matteo, Boris) Ref document: LHC-MPP-HCP-071.
Session th January 2010 R.Schmidt TE/MPE Hardware Commissioning 2010 and beyond R.Schmidt.
MP3 report : W49 (6 slides, 6’) J.Ph Tock for the MP3 team Since oral report last week (24 th of November) 1JPhT – LMC 1st of December 2010.
Upgrades and Activities of 13kA EE systems during LS1 Bozhidar Panev TE-MPE-EE
Operational tools Laurette Ponce BE-OP 1. 2 Powering tests and Safety 23 July 2009  After the 19 th September, a re-enforcement of access control during.
Chamonix Risks due to UPS malfunctioning Impact on the Superconducting Circuit Protection System Hugues Thiesen Acknowledgments:K. Dahlerup-Petersen,
1 Second LHC Splice Review Copper Stabilizer Continuity Measurement possible QC tool for consolidated splices H. Thiesen 28 November 2011 K. Brodzinski,
1 Copper Stabilizer Continuity Measurement Project Copper Stabilizer Continuity Measurement Status & Plans – May 2011 MPE-TM – 12 May 2011 M. Koratzinos,
TE-MPE LS1 review 02/06/2015, Mateusz Bednarek, TE/MPE-EE ELQA during LS1 – the “unexpected” activities New developments Exceptional NCs Other tests.
Training LHC Powering R. Denz Quench Protection System R. Denz AT-MEL.
TE-MPE-CP, RD, 09-June Enhanced Diagnostics & Supervision for Quench Heater Circuits R. Denz TE-MPE-CP.
AT-MEL-PM, R. Denz, CERN, CH-1211 Geneva 23 1 QPS system and its risks  Principal risks  General remarks  Quench heater circuits  Quench detection.
For more info:
MPE Review – June 2, 2015 A. Erokhin, TE-MPE-EE Upgrade, IST and Powering tests of the Upgrade, IST and Powering tests of the 600A Energy Extraction Systems.
MP3 recommendations from June 2013-Feb 2014 Arjan Verweij on behalf of the MP A. Verweij, LSC meeting 7/2/2014 One of the tasks of the MP3 is.
Recent cross-wiring issue and implication for circuits protection Bozhidar Panev TE-MPE-CP
M. POJER, ON BEHALF OF THE USUAL BUNCH OF SUSPECTS… S UPERCONDUCTING CIRCUITS RE - COMMISSIONING AFTER THE 2011 C HRISTMAS BREAK.
Power Converters and DC cablesSlide 1/.. LHC - HC review Hugues THIESEN – AB/PO Thursday, 12 May 2005 Water cooled cables warm bus bars power converter.
NQPS commissioning …a long way to go. Topics nQPS component overview Enhancements in Firmware Commissioning diagram Detailed task list Summary.
SAFETY DURING HARDWARE COMMISSIONING, 18 October 2007, D. Bozzini, AT/MEL-EM 1 Safety during Hardware Commissioning Davide Bozzini on behalf of the ELQA.
MP3 List of main Issues during March 2010 MP3 - Team.
1 15 April 2010: Post Mortem Analysis by M.Zerlauth Automated analysis of Powering Events – Progress update.
[R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] HWC Workshop ( ) Consolidation and major changes that have impact on the powering circuits.
1 J. Mourao (TE/MPE/CP) Enhanced DQHDS functionality  Status for 2011  Increase Magnet diagnostic capabilities  Our proposals.
MPE Workshop for LS1 / 22 & 23 Nov. 2012, G. D’Angelo TE/MPE-EE ELQA during LS1 train, Special measurements and NCs Magnet replacement: AIV Splices consolidations:
Review of Sector th of February Tunnel Access During Powering Tests Hugues Thiesen, AB-PO.
AT-MEL Group Meeting, CERN, 1211 Geneva 23 1 ElQA activities during hardware commissioning N. Catalan Lasheras.
MP3- MIC-C S1-2 A22R1- 19/08/2009 G.D’Angelo on behalf of Elqa team MP3 MIC-C test campaign in S1-2 Special guest: A22R1 (MB2413)  MIC-C in the ARC results.
LHC Machine Status Report Mike Lamont for the LHC team Acknowledgements: Mirko Pojer, Matteo Solfaroli, Katy Foraz et al.
HWC with nQPS Splice Monitoring Zinur Charifoulline & Bob Flora Real Time (~10 sec) BUS Voltage Energy Extraction Trip 300 µV threshold on Un-bypassed.
Conclusions on UPS powering test and procedure I. Romera Acknowledgements: V. Chareyre, M. Zerlauth 86 th MPP meeting –
Machine Protection Review, R. Denz, 11-APR Introduction to Magnet Powering and Protection R. Denz, AT-MEL-PM.
TE/MPE-MS MPE-TM meeting 14/06/2012, Richard Mompo Updated ELQA test procedure Co-authors: Nuria Catalan Lasheras Mateusz Bednarek Giorgio D’Angelo Richard.
MPE Workshop for LS1 Summary of Global Activities Thanks to Speakers Arjan Verweij Hugues Thiesen Zinur Charifoulline Kajetan Fuchsberger.
Training LHC Powering - Markus Zerlauth Powering Interlocks Markus Zerlauth AB/CO/MI.
MPP Meeting 07/03/2007 MPP Main Ring Magnet Performance Panel Meeting Wednesday 7th March 2007 Agenda: 1)Matters arising 2)Recommendations for the case.
An invitation to an open discussion We are team reviewing its performance globally We want to help each other to reach the objectives We know the other.
CSCM (Thermal Amplifier) Sequence and detailed planning 07/10/2011 M.Solfaroli Thanks to: K.Brodzinski, G.D’Angelo, M.Koratzinos, M.Pojer, R.Schmidt, J.Steckert,
Machine Protection Review, Markus Zerlauth, 12 th April Magnet powering system and beam dump requests Markus Zerlauth, AB-CO-IN.
Training LHC Powering – Blanca Perea Solano From Individual System Tests to Powering to Nominal Blanca Perea on behalf of Hardware Commissioning Coordination.
Hardware Commissioning Review, R. Denz, 12-May Superconducting circuits: what remains to be done during hardware commissioning R. Denz AT-MEL-PM.
Quench behavior of the main dipole magnets in the LHC By Gerard Willering, TE-MSC On behalf of the MP3-CCC team Acknowledgements TE-MSC, MP3, BE-OP, TE-MPE,
Main MPE Activities during YETS/EYETS/LS2 and the Provision of Resources Andrzej Siemko Andrzej Siemko TE-MPE1.
Mikhail Ovsienko TE-MPE-EE
Powering LHC magnets version 30/3/2007.
Minimum Hardware Commissioning – Disclaimer
Powering the LHC Magnets
MPE main activities planned for LS2
Status of ELQA equipment and related software
Powering from short circuit tests up to nominal
Re-Commissioning (IST) of Electrical Systems: QPS, EE & PIC
Detailed global view on protection and detection of the circuits
3 issues identified in review
Rüdiger Schmidt and Karl Hubert Mess
Machine Protection Xu Hongliang.
+ many slides from various colleagues (KH, Rudiger, Paul, …)
(damaged board on RQD/F)
M. Zerlauth, I. Romera 0v1.
Andrzej Siemko (CERN) and Marco Zanetti (MIT)
Review of hardware commissioning
Other arguments to train two sectors to 7 TeV
Presentation transcript:

BCWG - 16/11/20102 Content WHY do we need a HW Commissioning campaign? WHAT are we going to do? HOW are we going to do it? ElQA QPS Powering Tests Planning (draft) Overlook (4TeV) Miscellaneous M.Pojer/M.Solfaroli

BCWG - 16/11/20103 WHY Lots of activities will be performed in the LHC underground Activities cannot be fully controlled We cannot ensure a 100% correctly functioning machine protection system Cryogenic intervention: Warming up of the arc magnets below 80 K DFBs will warm up above 80 K (as already happened in short technical stops) M.Pojer/M.Solfaroli

BCWG - 16/11/20104 WHAT Assume operation at 3.5 TeV Monitoring of electrical integrity of some circuits (high current circuits of the arc and spool pieces) during warm- up and cool-down will be installed ELQA will be performed ONLY for the circuits with a current above 600A QPS – QH firing (scheduled once per year): as risk of damage during the test is higher than risk of failure when needed (redundancy of quench heaters and very limited number of beam induced quenches), heater firing tests ONLY for magnets whose cables are disconnected –no systematic heater firing for MB and for MQ magnets M.Pojer/M.Solfaroli

BCWG - 16/11/20105 WHAT Circuit protection requires correct operation of the interlocks (QPS, PIC, PC) and EE --> Almost all tests to verify the correct functioning of interlocks will be performed Reduced number of other tests, according to expert requirements Heat run for all circuits will be performed (8hours) as last step M.Pojer/M.Solfaroli

BCWG - 16/11/20106 HOW - ElQA The ElQA team and equipment: Equipment for testing up to 4 sectors in parallel 5 teams available inside the ElQA team (2 teams per sector + 1 (per MIC) needed) –> up to 2 sectors in parallel NEEDS (for one sector) 2 teams for HV ElQA 1 team for MIC M.Pojer/M.Solfaroli

BCWG - 16/11/20107 Snubber capacitors: Installed only for RB circuits –ONLY ONE SECTOR will be connected for testing (assuming re-commissioning to 3.5TeV) –ELQA to be done (separately) Old global main bus-bar detector taken out in all sectors Quench heater power supplies switches: –test during switch off to identify weak switches Test of the third (Z) switch of 600 A citrcuits (within test step of HC) Upgrade all Q9 and Q10 voltage divider (Q10 R2 done) – test within the normal HWC sequence HOW - QPS M.Pojer/M.Solfaroli

BCWG - 16/11/20108 HOW - PTs Simplification of test execution: Excluding high current tests (RB, RQD) a test step with same current level can be done before the previous test step is signed Signature of tests to be cleaned up (not required that several teams sign the same test) Parallel tests of several circuits - Global Power Abort will be disabled (re-enabled after the tests) M.Pojer/M.Solfaroli

BCWG - 16/11/20109 HOW - PTs Circuit typeTestEstimation RB (8) PIC2~30 min 5/8 PIC tests 4/13 other tests (+2 if 4TeV) PLI1.d2 Unipolar Powering Failure~10min PLI2.b2 Energy Extraction from QPS I_Interm_1~20min PLI3.d2 Unipolar Powering Failure~15min PNO.b2 Energy Extraction from QPS~30min RQD/F (16) PIC2~30 min (per circuit) 5/8 PIC tests 2/12 other tests PLI2.b3 Energy Extraction from QPS 13kA~20min PNO.b3 Energy Extraction from QPS 13kA~30min M.Pojer/M.Solfaroli

BCWG - 16/11/ HOW - PTs Circuit typeSectorEstimation IPQs (78) PIC2~15min 3/6 PIC tests 1/7 other tests (+ PNO.a7) PNO.c3 Fast Power Abort IPQ~35min IT (8) PIC2~20min 3/6 PIC tests 2/16 other tests PNO.d12 PC Failure at +10% of PNO~10min PNO.d13 PC Failure at -10% of PNO~10min IPD (16) PIC2~15min 3/6 PIC tests 2/4 other tests PNO.c2 Fast Power Abort IPD~20min 600A EE (202) PIC2~10min 3/6 PIC tests 2/6 other tests PLI3.b1 Energy Extraction from QPS 600A~5min PNO.d3 Bipolar Powering Failure 600A~15min 600A no EE (72) PIC2~10min 3/6 PIC tests 1/4 other tests PNO.d3 Bipolar Powering Failure 600A~15min M.Pojer/M.Solfaroli

BCWG - 16/11/ HOW - PTs Circuit type SectorEstimation 600A no EE crow (136) PIC2~10min 3/6 PIC tests 1/4 other tests PNO.d3 Bipolar Powering Failure 600A ~15min 80 – 120A (284) PIC2~2min 1/3 PIC tests 1/4 other tests PNO.d1 Bipolar Powering Failure~10min 60A (752) PNO.d1 Bipolar Powering Failure~10min 1/3 other tests TOT 1792/3672 PIC tests - 49% 1690/5878 other tests - 29% (of course including the 60A) …+8h Heat run and GPM check M.Pojer/M.Solfaroli

BCWG - 16/11/ Cryo Maintains CRYO 19/ / / /0134 – 81 27/0112 – 45 01/0223 M.Pojer/M.Solfaroli

13 DSO tests 2 shifts – 13h 7am - 8pm 3 shifts 7/7 days 3 shifts 7/7 days 3 shifts 7/7 days First sector in Phase I powering

BCWG - 16/11/ Overlook - 4TeV 4 TeV considerations: We don’t expect a significant delay Current in RB: 6770 A instead of 5925 A (1 more step) Values for current in corrector magnets (M.Giovannozzi) QPS rating might need to be reviewed Snubber capacitors: needed for RB (to be connected) to be clarified for RQD/F RQX.R1 – voltage reduction Symm nQPS threshold (800 mV) to be lowered? dI/dt: RB time constant to be increased to 68 s RB.A78 high voltage tested only to 1.6 kV - to be confirmed Splice safety to be confirmed by ongoing simulations M.Pojer/M.Solfaroli

BCWG - 16/11/ MISCELLANOUS RRR measurements Simulation validation tests Re-test of circuits where PC replaced Inner Triplet tests: PC trips when power permit removed Some special test for selected circuit (refer to MP3) Snubber caps: Energy extraction at different current levels ( kA) M.Pojer/M.Solfaroli

BCWG - 16/11/ CONCLUSIONS We are confident that HWC will be short and quick –All SW already used –No heavy modification on circuits –No mayor modification on procedure –Strongly reduced number of tests Possible commissioning to 4 TeV wouldn’t take much –Studies on technical showstopper ongoing Difficulties in finding people to cover the shifts could slow down the commissioning time LHC should be ready for operation by 18 Feb. M.Pojer/M.Solfaroli