June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota

Slides:



Advertisements
Similar presentations
Leicester SRC, 3-5 Dec 2007 Systems engineering at detector level Tim Stevenson.
Advertisements

GLAST LAT ProjectLAT Engineering Meeting, April 1, 2003 GLAST Large Area Telescope: Performance & Safety Assurance Darren S. Marsh Stanford Linear Accelerator.
STEREO IMPACT Preliminary Design Review 2001-September 11,12 David Curtis1 IMPACT Project Overview.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
THEMIS INSTRUMENT PER 1 UCB, May, 2005 EMC / Mag Instrument Test Plan & Results Michael Ludlam University of California - Berkeley.
GoetzFIELDS iPDR – I&T SPP/FIELDS Integration and Test Preliminary Design Review Keith Goetz University of Minnesota 1.
Solar Probe Plus FIELDS Monthly Management Telecom Sep 17, 2012.
Telecom 1 9/17/2012 SPP/FIELDS Solar Probe Plus FIELDS Monthly Management Telecom Sep 17, 2012.
NASA’s Goddard Space Flight Center LRO Integration and Test Joanne Baker GSFC Code 568 August 16-17, 2005.
THEMIS-SCM THM – SCM – CDR – 08-April-2004 in Velizy
Timothy QuinnFIELDS iCDR – EGSE Solar Probe Plus FIELDS Instrument CDR Electrical GSE Timothy Quinn UCB 1.
SPP Spacecraft Emulator (SCE) Introduction
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Test Plan Michael Ludlam Space Sciences Laboratory.
GLAST LAT ProjectI&T&C Pre PDR Presentation– Oct. 2, I&T&C Organization Chart I&T&C Manager Elliott Bloom WBS I&T Engineer B. Grist WBS
GoetzFIELDS iCDR – I&T Solar Probe Plus – FIELDS Integration and Testing Instrument CDR Keith Goetz University of Minnesota 1.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW Boom PER 30 June RBSP EFW Spin Plane Booms Greg Dalton Space Sciences.
THEMIS Instrument CDR 1 UCB, April 19-20, 2004 Boom Electronics Board (BEB) Engineering Peer Review Apr. 20, 2004 Hilary Richard.
24-1 MAVEN IPSR October 30,31, 2012 Particles and Fields Package Pre-Ship Review October 30,31, : ATLO Support Dave Curtis Mars Atmosphere and Volatile.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
THEMIS Mission PDR/CAR 1 UCB, November 12-14, 2003 Instrument Integration & Test Dr. Ellen Taylor University of California - Berkeley.
MAVEN CDR May 23-25, 2011 Particles and Fields Package Critical Design Review May , 2011 Integration and Test Dave Curtis PFP Package Manager Mars.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Overview and Status Keith Goetz University of Minnesota.
STEREO IMPACT Critical Design Review 2002 November 20,21,22 Acuña1 MAGNETOMETER (MAG) M. H. Acuña NASA/GSFC Laboratory for Extraterrestrial Physics.
THEMIS IDPU PDR I&T REQUIREMENTS- 1 UCB, October 16, 2003 I&T REQUIREMENTS Ellen Taylor University of California - Berkeley.
Solar Probe Plus A NASA Mission to Touch the Sun March 2015 Instrument Suite Name Presenter's Name.
Solar Probe Plus Fluxgate Magnetometer QSR – Oct SPF MAG Quarterly Report – Oct 2014 The MAG EM1 (EQM) (board and frame at right) was successfully.
GLAST LAT Project LAT System Engineering 1 GLAST Large Area Telescope: LAT System Engineering Pat Hascall SLAC System Engineering Manager
FM1 Instrument Suite Pre-Ship Review (PSR)INT- 1 UCB September 21, 2005 THEMIS FM1 INSTRUMENT SUITE PRE-SHIP REVIEW (PSR) INTEGRATION AND TEST PLANS Jeremy.
Solar Probe Plus FIELDS Fluxgate Magnetometer QSR – June 2015 June 16, SPF MAG Quarterly Report – June 2015 MAG FM1 electronics PCB assembled (see.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes 3-4 Sept. 2008EFW INST+SOC PDR447 Command, Telemetry, and Ground Support Equipment (CTG)
GoetzPre-PDR Peer Review October 2013 FIELDS Time Domain Sampler Peer Review Keith Goetz University of Minnesota 1.
TRIO-CINEMA 1 UCB, 2/08/2010 Integration and Test Program Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
4-1 MAVEN IPER May 22-23, 2012 Particles and Fields Package Pre-Environmental Review May , Verification Dave Curtis, PFP Package Manager.
Solar Probe Plus FIELDS Instrument PDR Management Peter Harvey, PM Lindsey Hayes, DPM University of California
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW CDR /30-10/1 9 EFW Overview and Status Keith Goetz University of Minnesota.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes RBSP/EFW I-PER 21 January EFW Systems Engineering Michael Ludlam Space Sciences.
Timothy Edward Quinn FIELDS iPDR – GSE Solar Probe Plus FIELDS Instrument PDR GSE Timothy Edward Quinn UCB 1.
FM4/FM5 IPSRSYS - 1 UCB, May 5, 2006 THEMIS INSTRUMENT SUITE FM4/FM5 PRE-SHIP REVIEW SYSTEM OVERVIEW Ellen Taylor University of California - Berkeley.
1 SWEA pre-CDR Peer Review Particles and Fields Package (PFP) SWEA pre-CDR Peer Review Integration with PFP, Qualification, ATLO 2011 March 28 Dave Curtis.
RBSP Radiation Belt Storm Probes RBSP Radiation Belt Storm Probes Sept 30 – Oct RBSP EFW ICDR1 Integration and Test Michael Ludlam (EFW Systems Engineer)
1 PFP IPDR 2010/6/ Particles and Fields Package (PFP) Instrument Preliminary Design Review Integration & Test David Curtis, PF Package Manager.
THEMIS-SCM SCM – OVERALL RESSOURCES – STATUS versus REQUIREMENTS ItemSpecificationStatus Sensor Bandwith Sensor Sensitivity Up to 4 kHz 1 pT/√Hz at 10.
TRIO-CINEMA 1 UCB, 2/08/2010 System Design Dave Curtis UCB/SSL Space Sciences Laboratory University of California, Berkeley.
Power Philip Luers NASA/GSFC Code 561 August 16-17, 2005.
FIELDS MEP Thermal Vacuum Cycling iPER
Solar Probe Plus – FIELDS SCM FM2 Instrument Pre-Ship Review
Solar Probe Plus – FIELDS V1234 PA/Antenna Instrument Pre-Ship Review
Solar Probe Plus FIELDS MEP iPSR SOC Marc Pulupa April 10, 2017
Solar Probe Plus – FIELDS Main Electronics Package
Gayle K. Martin November 14, 2016
SPF MAG Quarterly Report – Feb 2015
EIDP Status. Solar Probe Plus FIELDS Main Electronics Package iPSR Management Apr 10, 2017.
CINEMA System Engineering
(EFW Systems Engineer) University of California, Berkeley
Agenda. Solar Probe Plus FIELDS Main Electronics Package iPER Agenda Feb 2, 2017.
Solar Probe Plus – FIELDS Main Electronics Package
Mars Atmosphere and Volatile EvolutioN (MAVEN) Mission
GLAST Large Area Telescope:
Solar Probe Plus – FIELDS Verification Instrument mini-PER (V5)
THEMIS Mission Assurance
FIELDS SCM Thermal iPER
FIELDS Keith Goetz Solar Probe Plus A NASA Mission to Touch the Sun
Solar Probe Plus FIELDS Main Electronics Package iPER EMC Feb 2, 2017
0.0 Instrument Suite Name Presenter’s name
Systems Engineering Bob Goeke.
Launch and On-orbit Checkout
Integration and Test Organization Chart
CONTOUR NGIMS Electronics Test History
Integration and Test Organization Chart
Presentation transcript:

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test SPP/FIELDS Integration and Test SOC Critical Design Review Keith Goetz University of Minnesota 1

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test FIELDS Block Diagram 2

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test I&T Plans Philosophy –Requirements are verified as early as possible at a low level Verifies subsystems, Retires risk –Requirements are verified at the highest level of assembly possible Often involves verifying a requirement at several levels –Maintain flexibility in test sequencing to maintain schedule Tests on ETU/EM ✔ –Substantial environmental test program on EM hardware –FIELDS EM units have been assembled, integrated and tested –Includes TV Tests on Flight Units –Full environmental test program on Flight units Typical Test Levels: –Subassembly (circuit board): functional –Component (e.g. V1, MAG, SCM, MEP): functional, mass properties, vibration, TV, deployments, magnetics –Instrument: functional, calibration, interface, EMC, TV 3

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Planned ETU I&T Flow 4

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Planned FM I&T Flow 5

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Procedures Each test will be documented by a Test Procedure –Test procedure shall identify IRD requirements to be verified by the test –Test procedure shall include pass/fail criteria –System Engineer, QA, Subsystem lead to sign off on procedure before use –System Engineer, QA to sign off on completed as-run procedure –QA to ensure Red-lines to be transferred into procedure before next use Each completed test to be documented by a Test Report –ETU and subassembly test reports may be a combination of the as-run procedure and lab notebook –System Engineer to sign off on test reports, and determine if test adequately verifies associated requirements Discrepancies found during tests to be documented in a Problem Failure Report (PFR) –Starting with first functional tests at FM subassembly level –Includes any problem (including software) not immediately identified as a test setup or operator problem which cannot stress the flight article –QA will track PFRs to closure with concurrence of the Failure Review Board (includes APL) 6

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Calibrations Co-I hardware institutions will deliver fully calibrated sub- assemblies Once FIELDS instrument is fully integrated –Several verification cals in ambient and at temperature –Timing –SWEAP Antennas – as mechanical elements – can be tested separately 7

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Interfaces Interface tests verify interfaces meet requirements from ICD and/or specifications. FIELDS ETU well tested with APL S/C mini emulators FIELDS FM to be tested with APL S/C full emulators FIELDS TDS ETU/FM to be tested with SWEAP (at UCB) At other times (prior to Observatory I&T) interfaces simulated with GSE –Board, Component level tests performed with Board Interface Simulation GSE –Instrument-level tests performed with: APL-provided spacecraft emulators Command and Telemetry GSE software Stimulation GSE or internal test signal SWEAP simulator (FIG) Deployment actuator simulators –GSE functionality, design described in GSE section 8

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Mechanical Testing Antenna mechanisms can be tested independently of electronics Full functional testing Vibration TV Where appropriate, testing will include whips FIELDS Contamination Control Plan documents how FIELDS will meet Project contamination control requirements 9

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Thermal Testing Tests per SPP Environmental Spec –1 survival and 6 operational thermal vacuum cycles –Temperature ranges detailed in thermal presentation Per FIELDS V&V and T&C plan –V1-V4 PAs in one range –V5 PA in one range –MAG sensors (at GSFC) –SCM assembly (at LPC2E) –MEP is the simplest Includes all sensors –Antenna mechanisms Proposed Thermal Balance test using ETU FIELDS boom and ETU sensors – fall

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test EMC Tests Tests per EMECP Electro-Static Discharge Test (EM only) DC Magnetics (sniff test) Surface Charging / Electrostatic Cleanliness Ground Bonding and Isolation Turn On/Off Transients CE, CS, RE, RS Tests as detailed in EMECP –ETU will only do CE measurements on the bench ✔ 11

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test S/C-level I&T FIELDS and APL have had discussions w/r/t S/C level I&T FIELDS integration will involve a number of hardware elements (~20) FIELDS magnetic sensors will have protective enclosures FIELDS will have external stimulus to support CPT functional testing Antennas will not be deployed at Spacecraft level –Too hard to implement off-loading GSE at spacecraft level –First motion without whips Actuator simulators will be provided to perform simulated boom deployments –Simulators contain flight-like resetable actuators (or equivalent loads) –Simulators attach to S/C deployment harnessing –Simulators can be used at spacecraft-level TV 12

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test FIELDS Flight Configuration 13

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test FIELDS Bench Testing Configuration 14

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test FIELDS CPT Configuration 15

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test FIELDS Flight Configuration 16 SOC

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test GSE Evolution SOC development will flow naturally from GSE GSE and GSEOS are fully functional with FIELDS EM –FIELDS1 and FIELDS2 EMs GSE and GSEOS will continue with FM development –At all hardware institutions UCB, UMN, LASP, GSFC –Used for all commanding FIELDS1/FIELDS2 –Used for acquiring all telemetry FIELDS1/FIELDS2 –Will move with us to APL for S/C level I&T GSE and GSEOS will evolve into components of SOC after launch –Used to build, test and send command loads –Used to operate EM test-beds at UCB and UMN 17

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Commissioning - 1 FIELDS has a number of critical steps in the commissioning period Deployment of the magnetometer boom (day ~3) –Turn on and check out FIELDS MEP –Turn on and check out FIELDS MAGs Command for high rate MAG data –Turn on and check out FIELDS SCM Command for SCM configuration –Gather background data - stowed –Deploy MAG Boom –Gather background data - deployed 18

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Commissioning - 2 Deployment of the V1234 Antennas (day ~30) –Turn on and check out FIELDS MEP Command for data acquisition –Deploy Antennas Deploy V1 –Gather background data - stowed –Deploy V1 –Gather background data – deployed Deploy V2 –Gather background data - stowed –Deploy V2 –Gather background data - deployed Deploy V3 –Gather background data - stowed –Deploy V3 –Gather background data - deployed Deploy V4 –Gather background data - stowed –Deploy V4 –Gather background data – deployed –Survey deployed antenna beam patterns 19

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Commissioning - 3 Observe Probable Interference from TWTA (day ~30) –Start TWTA X-band contact –Turn on FIELDS MEP Command for data acquisition –Turn off TWTA –Send FIELDS science data to spacecraft SSR –Turn on TWTA by timed command –Playback recorded data –Repeat 20

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Commissioning - 4 Observe Interactions with Other SPP Instrument (day ~40) –Start TWTA X-band contact –Turn on FIELDS MEP Command for data acquisition –Turn on SWEAP Test inter-instrument interface Run in noisy mode –Turn on EPI (2) Run in noisy mode –Turn on WISPR Run in noisy mode –Repeat in reverse order looking for interference 21

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Commissioning - 5 Observe Interactions with SPP Spacecraft (day TBD) –Start TWTA X-band contact –Turn on FIELDS MEP Command for data acquisition –Turn on other instruments as desired –Run reaction wheel speed program –Run SA flap and feather –Run HGA motion survey –Repeat - looking for interference 22

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Commissioning - 6 Observe SPP Spacecraft Attitudes (day TBD) –Start TWTA X-band contact –Turn on FIELDS MEP Command for data acquisition –Turn on other instruments as desired –Run some rolls – fast –Run some slews Run a roll while slewed –Repeat 23

June 16, 2015SPP/FIELDS SOC CDR: Integration & Test Conclusion Instrument I&T plans are in good shape –Previous experience helps Spacecraft I&T plans are getting started –Previous experience helps here too FIELDS SOC is ready to move forward 24